ER26-3650-000 · 2026-09-18 · North American Electric Reliability Corporation, Midwest Reliability OrganizationReliability First Corporation, SERC Reliability Corporation

Motion to Intervene and Comments of North American Electric Reliability Corporation et al. re Midcontinent Independent System Operator, Inc.'s 08/28/2026 filing

PDF page 1

1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
Midcontinent
Independent
System
Operator, Inc.
)
)
)
Docket No. ER26-3650
MOTION TO INTERVENE AND COMMENTS OF THE
NORTH AMERICAN ELECTRIC RELIABILITY CORPORATION, MIDWEST
RELIABILITY ORGANIZATION, RELIABILITY FIRST CORPORATION, AND SERC
RELIABILITY CORPORATION
On August 28, 2026, the Midcontinent Independent System Operator, Inc. (“MISO”) filed proposed revisions to MISO’s Open Access Transmission, Energy and Operating Reserve Markets Tariff (“Tariff”) with the Federal Energy Regulatory Commission (the “Commission” or “FERC”) to establish certain Interconnection Reliability Requirements for Large Loads (the “IRR Proposal”).1  The IRR Proposal2 was MISO’s initial step responding to the Commission’s June 2026 Order Instituting Proceeding Under Section 206 of the Federal Power Act directing MISO to examine tariff provisions to support the interconnection of large load with the Bulk-Power System (“BPS”).3  While acknowledging regional differences and market rules, the Commission highlighted five categories of focus:  (i) efficient transmission service application and study; (ii) potential cost shifting; (iii) co-location arrangements; (iv) new transmission services for flexible large loads; and (v) a process to study generating facilities serving electrically proximate large

1 18 C.F.R. §§ 385.206, 385.212, and 385.214 (2026).
2 Midcontinent Independent System Operator, Inc.’s Interconnection Reliability Requirements for Large Loads, Docket No. ER26-3650 (Aug. 28, 2026) [hereinafter IRR Proposal].
3 See, e.g., Midcontinent Independent System Operator, Inc., Order Instituting Proceeding Under Section 206 of the Federal Power Act, 195 FERC ¶ 61,212 (2026) (“Show Cause Order” or “SCO”).  The Commission issued parallel orders tailored to five other regional transmission organizations/independent system operators (“RTOs/ISOs”), which are together referred to as the “Show Cause Orders.”

PDF page 2

2

loads and large co-located load.  MISO’s IRR Proposal stated that it intended to promote visibility, ramp rate, and disturbance ride-through requirements applicable to large loads.

Pursuant to Rules 212 and 214 of the Federal Energy Regulatory Commission’s
(“Commission”) Rules of Practice and Procedure, the North American Electric Reliability Corporation (“NERC”), Midwest Reliability Organization (“MRO”), ReliabilityFirst Corporation (“RF”), and SERC Reliability Corporation (“SERC”) (collectively, “NERC and the Regional Entities”) move to intervene and comment on the IRR Proposal.4  NERC and all six Regional Entities (collectively, the “ERO Enterprise”) are dedicated to ensuring effective and efficient reduction of risks to the reliability and security of the grid, including supporting entities in identifying and mitigating potential threats to BPS reliability.

North America is entering a period of unprecedented load growth, with NERC Long-Term Reliability Assessments (“LTRAs”) noting that demand is higher than at any point in the last two decades.5   This projected increase in North American electricity demand is largely driven by computational load, such as data centers for artificial intelligence and other uses underpinning the digital economy, interconnecting with the BPS.6 MISO’s IRR Proposal states, for example, that,

4 NERC accomplishes its mission with the support of the six Regional Entities who help NERC support reliability across various interconnections with differing needs and characteristics. The six Regional Entities are MRO, Northeast Power Coordinating Council, Inc., RF, SERC, Texas Reliability Entity, Inc., and Western Electricity Coordinating Council. NERC’s relationship with the Regional Entities is governed by Regional Delegation Agreements or “RDAs” filed with the Commission every five years. 18 C.F.R. § 39.8.
5 NERC, 2025 Long-Term Reliability Assessment (Jan. 2026), https://www.nerc.com/globalassets/our- work/assessments/nerc_ltra_2025.pdf [hereinafter 2025 LTRA]; NERC, 2024 Long- Term Reliability Assessment at 8 (Dec. 2024, updated July 2025), https://www.nerc.com/pa/RAPA/ra/Reliability%20Assessments%20DL/NERC_Long%20Term%20Reliability%20 Assessment_2024.pdf. NERC develops the Long-Term Reliability Assessments annually in accordance with the NERC Rules of Procedure and Title 18, § 39.112 of the Code of Federal Regulations; this is also required by Section 215(g) of the Federal Power Act, which instructs NERC to conduct periodic assessments of the North American BPS.
6 Id.  Please note, in using the term computational load, NERC references that term as used in its assessments and draft registry criteria and Reliability Standard work.  MISO’s IRR Proposal includes MISO’s definition of computational load which may have differences.

PDF page 3

3

“[a]s NERC has observed [in the LTRA], the largest contributor to this accelerated demand growth is data center additions, with 18 GW of data center loads projected [in MISO] by 2035.”7 The ERO Enterprise has been working urgently with stakeholders on clear and consistent measures to support the reliable interconnection of computational loads. As outlined in NERC’s large load action plan, these efforts include revisions to NERC registry criteria and Reliability Standards for submission to the Commission by year-end, and further efforts such as disturbance ride-through performance requirements are underway with filing(s) to the Commission targeted in 2027.  MRO, RF, and SERC are the NERC Regional Entities which support activities in the MISO area.  Therefore, NERC and the Regional Entities move to intervene and comment to provide information on the record regarding efforts to harmonize these activities with those being led by stakeholders, such as MISO, under parallel processes.8

7
IRR Proposal, at 5 (citing the 2025 LTRA, at 15).
8 These comments are focused only on matters as related to section 215 of the FPA, the ERO Enterprise declines to comment on matters outside of its purview.

PDF page 4

4

I. NOTICES AND COMMUNICATIONS
Notices and communications with respect to this filing may be addressed to the following:9 Candice Castaneda*

Senior Counsel
Marisa Hecht*
North
American
Electric
Reliability
Corporation
1401 H Street, N.W., Suite 410
Washington, D.C. 20005
(202) 400-3000
(202) 644-8099 – facsimile
candice.castaneda@nerc.net
marisa.hecht@nerc.net

Julie Peterson*
Vice President General Counsel and Corporate
Secretary
Midwest Reliability Organization
380 St. Peter Street Suite 800
Saint Paul, MN 55102
Julie.Peterson@mro.net
Niki Schaefer*
Vice President and General Counsel
ReliabilityFirst Corporation
3 Summit Park Drive, Suite 600 • Cleveland,
Ohio  44131
niki.schaefer@rfirst.org

Holly Hawkins*
Vice President and General Counsel
Rebecca Poulsen*
Assistant General Counsel
SERC Reliability Corporation
13320 Ballantyne Corporate Place, Suite 200
Charlotte, NC  28277
704-357-7372
hhawkins@serc1.org
rpoulsen@serc1.org

II. MOTION TO INTERVENE
NERC and the Regional Entities have a substantial interest in this proceeding as the IRR Proposal includes market rules which would complement their activities under section 215 of the FPA.10  By enacting the Energy Policy Act of 2005 and section 215 of the FPA,11 Congress entrusted the Commission with approving and enforcing rules to ensure the reliability of the BPS,

9 Persons to be included on the Commission’s service list are identified by an asterisk. NERC respectfully requests a waiver of the Commission’s rules 18 C.F.R. § 385.203 (2016) to allow the inclusion of more than two persons on the service list.
10 See, e.g., IRR Proposal, at 3.
11 16 U.S.C. § 824o.

PDF page 5

5

and with certifying an Electric Reliability Organization (“ERO”) charged with developing and enforcing mandatory Reliability Standards, subject to Commission approval. The Commission certified NERC as the ERO in 2006.12 As the ERO, NERC’s mission is to ensure effective and efficient reduction of risks to the reliability and security of the grid.13 NERC is responsible for developing and enforcing mandatory Reliability Standards applicable to BPS entities on NERC’s compliance registry and conducting assessments of the reliability and adequacy of the BPS.14 NERC develops Reliability Standards in accordance with Section 300 (Reliability Standards Development) of the NERC Rules of Procedure (“ROP”) and the NERC Standard Processes Manual.15 NERC’s compliance registry includes those entities which meet registry criteria under Section 500 and Appendix 5B of the ROP.  The ERO Enterprise is responsible for monitoring, assessing, and enforcing compliance with Reliability Standards in the United States in accordance with Section 400 (Compliance Enforcement) of the ROP and the NERC Compliance Monitoring and Enforcement Program.16

Since 2024, the ERO Enterprise has been assessing how to address potential issues associated with large levels of computational load interconnecting with the BPS.  As discussed in NERC comments, as supplemented, on the Advanced Notice of Proposed Rulemaking on reforms

12
N. Am. Elec. Reliability Corp., 116 FERC ¶ 61,062, order on reh’g and compliance, 117 FERC ¶ 61,126 (2006), order on compliance, 118 FERC ¶ 61,030, order on compliance, 118 FERC ¶ 61,190, order on reh’g, 119 FERC ¶ 61,046 (2007), aff’d sub nom. Alcoa Inc. v. FERC, 564 F.3d 1342 (D.C. Cir. 2009).

13 NERC, Who We Are, https://www.nerc.com/who-we-are.
14 16 U.S.C. § 824o(d)-(e), § 824o(g).
15 The NERC Rules of Procedure are available at https://www.nerc.com/globalassets/who-we-are/rules-of- procedure/nerc-rop.pdf. The NERC Standard Processes Manual is available at https://www.nerc.com/globalassets/who-we-are/rules-of-procedure/Appendix-3A.pdf.
16 The NERC Compliance Monitoring and Enforcement Program is available at https://www.nerc.com/globalassets/who-we-are/rules-of-procedure/appendix-4c.pdf.

PDF page 6

6

to ensure timely and orderly interconnection of large loads,17 NERC has been actively pursuing an accelerated action plan to develop (i) technical justification; (ii) registry criteria updates to the ROP; and (iii) Reliability Standards to account for computational load.18  On July 16, 2026 (the “July 16th Order”), the Commission directed NERC to file registry criteria and Reliability Standards to address computational load by December 31, 2026.19  The Commission also directed NERC to file a work plan by March 1, 2027, detailing next steps for additional Reliability Standards pertaining to computational load integration.  As a result, no other party can adequately represent NERC and the Regional Entities’ interests in this proceeding. Therefore, the parties request that the Commission grant this motion to intervene and comment as within the public interest.

III. COMMENTS
Consistent with the July 16th Order, the ERO Enterprise has prioritized near-term measures, such as foundational Reliability Standards and registry criteria addressing computational loads, while preserving flexibility for subsequent refinements, such as plans to develop ride-through requirements next year, as additional experience is gained with large load interconnections.20 The ERO Enterprise is working as quickly as possible with stakeholders to advance integration of computational load in a manner that sustains continued reliability and resilience. Based on risk

17 Department of Energy, Secretary of Energy’s Direction that FERC Initiate Rulemaking Procedures and Proposal Regarding the Interconnection of Larg Loads Pursuant to the Secretary’s Authority Under Section 403 of the Department of Energy Organization Act (Oct. 23, 2025) (“ANOPR”); Interconnection of Large Loads to the Interstate Transmission Sys., Notice Inviting Comments, Docket No. RM26-4-000 (Oct. 27, 2025).
18 Comments of the North American Electric Reliability Corporation in Response to Notice Inviting Comments, Docket No. RM26-4-000 at 1-2, 5-6 (Nov. 21, 2025) (“NERC ANOPR Comments”); NERC Additional Comments on Large Loads ANOPR (March 20, 2026) (“Supplemental ANOPR Comments”). 19 Order Directing the North American Electric Corporation to File Reliability Standard(s) Pertaining to Computational Load Integration, 196 FERC ¶ 61,031 (2026) [hereinafter July 16th Order].  See also, 16 U.S.C. § 824o(d)(5).
20 July 16th Order at P 11.

PDF page 7

7

prioritization, the ERO Enterprise and others are working towards foundational expectations to mitigate the immediate reliability risks associated with computational load.  MISO’s filing is an example of contributions by those across the electric and computational load industries to advance reliability in the face of this change.  Due to the urgency of these near-term measures, the ERO Enterprise, MISO, and other stakeholders working to mitigate risk are acting in parallel rather than sequentially, creating potential for some differences. While all stakeholders collaborate to minimize these differences, different timelines and internal governance processes may yield slightly different outcomes.

Regardless of the parallel development, MISO’s IRR Proposal seems generally consistent with pending Reliability Standards efforts.  The ERO Enterprise and RTO/ISO stakeholders, including MISO, have forums and groups established to continue ensuring consistency to the extent possible. For example, NERC’s Reliability and Security Technical Committee (“RSTC”) subgroups, computational load drafting team Project 2026-02, the short-term advisory group for foundational standards, and an ERO Enterprise and RTO/ISO computational load advisory group provide crucial input to help synchronize and harmonize parallel efforts advance.  In particular, the RTO/ISO computational load advisory group was developed and designed to foster coordination on these issues, with a specific focus on the potential performance requirements for computational loads across interconnections.21

 Through parallel processing, extensive and extraordinary stakeholder outreach, and carefully organized comment periods, NERC is striving to rapidly advance reliability and consistency as knowledge grows.  Despite the urgent and parallel actions, the ERO Enterprise has

21 NERC’s large loads action plan webpage provides further examples of outreach and coordination, https://www.nerc.com/initiatives/large-loads-action-plan.

PDF page 8

8

retained a transparent  stakeholder process with robust industry involvement, including computational load entities, that facilitates further harmonization across actions. At each step of the pending project for foundational Reliability Standards, the ERO Enterprise expedited processes where feasible, while maintaining transparency and effective consensus-building through a concerted effort to involve computational load entities in the standards development process.  At the inception of the Reliability Standards development project, for example, NERC’s Standards Committee appointed a drafting team based on diverse industry experts that included computational load entities, RTOs/ISOs, and members of NERC Standing Committees.  In light of the July 16th Order, the Standards Committee also granted waivers to permit shorter balloting and comment periods in the standards development process. Recently, the RSTC applied expedited processing for a computational load disturbance ride-through performance Standard Authorization Request in anticipation of presenting the request to the Standards Committee in the fall of 2026. The RSTC meetings in September included multiple presentations on the work being done to study and respond to the needs associated with computational load.

The ERO Enterprise anticipates that industry will continue to rapidly refine its understanding of what is needed to support reliable computational load integration.  As the ERO Enterprise and industry learn more about the needs associated with computational load, criteria (such as ride-through requirements) may need to be adjusted. Earlier in the year, the RSTC approved a roadmap of upcoming high-priority standards development projects – with the most urgent being the disturbance ride-through performance project mentioned above. To that end, the ERO Enterprise requests that the Commission consider expedited evaluation of future efforts stating that they seek to harmonize with NERC Reliability Standard requirements.  NERC also plans to request expedited Commission review of NERC’s proposed registry criteria and

PDF page 9

9

Reliability Standards filings later this year to support clear, consistent expectations and help ensure that foundational requirements can begin to become effective before the end of next year.

IV. CONCLUSION
WHEREFORE, for the reasons stated above, NERC and the Regional Entities respectfully request that the Commission accept the comments herein.

Respectfully submitted,
/s/ Candice Castaneda

Candice Castaneda
Senior Counsel
North American Electric Reliability
Corporation
1401 H Street, N.W., Suite 410
Washington, D.C. 20005
(202) 400-3000
(202) 644-8099 – facsimile
candice.castaneda@nerc.net

Counsel for the North American Electric
Reliability Corporation

Date: September 18, 2026

PDF page 10

CERTIFICATE OF SERVICE

I hereby certify that I have this day served a copy of this document upon all parties listed on the official service list compiled by the Secretary in the above-captioned proceeding, in accordance with the requirements of Rule 2010 of the Commission’s Rules of Practice and Procedure (18 C.F.R. § 385.2010).

Dated at Washington, D.C., this 18th day of September, 2026.