ER26-3650-000 · 2026-09-18 · North American Electric Reliability Corporation, Midwest Reliability OrganizationReliability First Corporation, SERC Reliability Corporation

Motion to Intervene and Comments of North American Electric Reliability Corporation et al. re Midcontinent Independent System Operator, Inc.'s 08/28/2026 filing

Text extracted from the eLibrary original (SHA-256 e5387b95b9558176…). Download the original from the official source.

Contents · 4 sections
  1. I. NOTICES AND COMMUNICATIONS p. 4
  2. II. MOTION TO INTERVENE p. 4
  3. III. COMMENTS p. 6
  4. IV. CONCLUSION p. 9

Read topic-matched comments in ER26-3650

Topics in the text: Registry access · Cost allocation · Connecting load and generation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Registry access

The Commission issued parallel orders tailored to five other regional transmission organizations/independent system operators (“RTOs/ISOs”), which are together referred to as the “Show Cause Orders.” 2 loads and large co-located load.
Read this passage Filed comments: Registry access

I. NOTICES AND COMMUNICATIONS

printed heading

NOTICES AND COMMUNICATIONS Notices and communications with respect to this filing may be addressed to the following:9 Candice Castaneda* Senior Counsel Marisa Hecht* North American Electric Reliability Corporation 1401 H Street, N.W., Suite 410 Washington, D.C. 20005 (202) 400-3000 (202) 644-8099 –…
Read this passage

II. MOTION TO INTERVENE

printed heading · Topic match: Registry access

The Commission certified NERC as the ERO in 2006.12 As the ERO, NERC’s mission is to ensure effective and efficient reduction of risks to the reliability and security of the grid.13 NERC is responsible for developing and enforcing mandatory Reliability Standards applicable to BPS entities on NERC’s…
Read this passage Filed comments: Registry access

III. COMMENTS

printed heading · Topic match: Registry access

To that end, the ERO Enterprise requests that the Commission consider expedited evaluation of future efforts stating that they seek to harmonize with NERC Reliability Standard requirements.
Read this passage Filed comments: Registry access

IV. CONCLUSION

printed heading

CONCLUSION WHEREFORE, for the reasons stated above, NERC and the Regional Entities respectfully request that the Commission accept the comments herein.
Read this passage

CERTIFICATE OF SERVICE

printed heading

Dated at Washington, D.C., this 18th day of September, 2026. /s/ Candice Castaneda Candice Castaneda Counsel for the North American Electric Reliability Corporation