Motion for Leave to Answer and Answer of the Data Center Coalition re the 10/13/2026 Answer of Midcontinent Independent System Operator, Inc. et al
The Data Center Coalition answers MISO's October 13 answer and repeats that substantive large-load reliability requirements belong in the Tariff, not unfiled Business Practice Manuals, and that FERC should reject the proposal without prejudice.
Asks FERC to: Reject the IRR proposal without prejudice to a revised MISO filing that puts the requirements in the tariff, uses objective classification criteria and ties transition protections to commercial commitments.
Second-round answer on MISO's post-E-8 filing, arguing it falls short of the clear and consistent framework the E-8 order contemplates.
E-8 MISO: Show cause or propose tariff changes in 60 days (p. 5)
Key points
- DCC says MISO's tariff names new requirements without giving their substance, and the definition and revocable exemptions add uncertainty.
MISO’s proposed tariff revisions in this proceeding tell transmission customers that they will be subject to new reliability requirements but without providing any detail on the substance of the requirements that will be applied. PDF p. 2
- DCC says MISO keeps discretion to require compliance from customers it nominally exempts, using criteria not filed with FERC.
MISO can unilaterally define, change, and apply reliability requirements as it deems fit and without meaningful Commission oversight. PDF p. 3
- DCC invokes the Rule of Reason: practices that significantly affect terms of service must be filed.
where, as here, requirements significantly affect the terms and conditions of jurisdictional service, they must be included in the tariff and remain subject to Commission oversight. PDF p. 4
- DCC argues unfiled BPM requirements may be unenforceable against customers.
raises serious questions as to whether these standards are enforceable against transmission customers at all. PDF p. 5
- DCC lists three elements a revised filing should include.
places the substantive requirements and standards required by Section 205 and the Rule of Reason in the tariff, (2) adopts objective and transparent Large Load classification and aggregation criteria PDF p. 5
Contents · 5 sections
Read topic-matched comments in ER26-3650
Topics in the text: Cost allocation · Connecting load and generation · Reliability and curtailment
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) Midcontinent Independent System Operator, Inc. ) Docket No.Read this passage
I. ANSWER
printed heading
DCC therefore respectfully requests leave to file this answer and asks the Commission to consider this answer in its deliberations in this proceeding. 4 Midcontinent Indep.Read this passage
A. MISO Has Not Demonstrated That Its Proposal To Leave The Substance Of
printed heading · Topic match: Cost allocation
The only reference to ramp smoothing in MISO’s proposed tariff revisions is a single statement in Section 37A.7 that ramp limits shall 17 MISO Answer at 22. 18 Id. 19 Id. at 24-25. - 7 - include “any reduction/ramp smoothing provided by generation or other resources[.]”20 Notwithstanding MISO’s…Read this passage Filed comments: Cost allocation
B. MISO Has Not Demonstrated That Its Proposed Large Load Definition Is Just
printed heading
MISO Has Not Demonstrated That Its Proposed Large Load Definition Is Just And Reasonable Or Provides Customers Adequate Notice 1.Read this passage
C. MISO Has Not Demonstrated That Its Transition Framework Will Minimize
printed heading · Topic match: Connecting load and generation
In practice, a facility in the final stages of development that can come online in the near term without the construction of significant transmission upgrades could be required to delay energization to redesign its equipment, while a project that must wait years for transmission construction could…Read this passage Filed comments: Connecting load and generation
II. CONCLUSION
printed heading
CONCLUSION For the foregoing reasons, DCC respectfully requests that the Commission reject the IRR proposal without prejudice to MISO filing a revised proposal consistent with DCC’s comments and this answer.Read this passage
CERTIFICATE OF SERVICE
printed heading
Dated at Washington, D.C., this 3rd day of November 2026. /s/ Stephen J.Read this passage