Joint Comments, Request for Clarification and Limited Protest of Coalition of MISO Transmission Customers et al. to Midcontinent Independent System…
Text recognized by OCR from a scanned original with no text layer; quotes may carry recognition errors. (SHA-256 48ecf0be58966e64…). Download the original from the official source.
Contents · 3 sections
Read topic-matched comments in ER26-3650
Topics in the text: Cost allocation · Retail and wholesale authority
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
The Large Energy Users appreciate MISO's work and responsiveness during the stakeholder process, but submit these Comments and Limited Protest to ensure that the proposed Tariff language is consistent with the underlying interconnection reliability objectives and to ensure that matters that…Read this passage
EXECUTIVE SUMMARY
printed heading · Topic match: Cost allocation
Second, the proposed tariff language in Section 37A.4 is ambiguous and, if not clarified, creates the possibility of burdensome real-time forecasting requirements for all Large Loads including conforming or non-computational loads' where the terms of such real-time forecasting requirements are not…Read this passage Filed comments: Cost allocation
A. The Commission Should Require MISO to Clarify Exemption Scenarios in
printed heading
Section 37A II.2, subsection (a) states, "A Large Load that has a Service Commencement Date on or prior to December 4, 2026, shall be exempt from all requirements set forth in this Section 37A with respect to the portion of the Large Load that has procured Transmission Service as of the Service…Read this passage
B. The Commission Must Not Impose Unreasonably Onerous Real Time
printed heading
The Commission Must Not Impose Unreasonably Onerous Real Time Forecasts in Section 37A.4 for Non-Computational Loads & "FERC may accept or reject the proposal.Read this passage
CERTIFICATE OF SERVICE
printed heading · Topic match: Cost allocation
While the grid capacity will catch up the short-term costs those investments must not be passed on to families, seniors, and small busi- nesses, many of whom don't want data centers in their communities in the That is why I am proud to cosponsor the bipartisan Ratepayer Protection Act, because…Read this passage Filed comments: Cost allocation