ER26-3650-000 · 2026-09-18 · Sierra Club, Natural Resources Defense Council and 5 others

Protest of Sierra Club et al. re Midcontinent Independent System Operator, Inc.'s 08/28/2026 filing

Seven public interest organizations protest MISO's large-load reliability filing, arguing its exemptions leave about 30 GW free of ramp and ride-through rules, that critical details sit in manuals, and that FERC should reject it.

Asks FERC to: Reject MISO's Interconnection Reliability Requirements filing as not just and reasonable.

Protests MISO's first filing after the E-8 order as exceeding what that order directed and shifting reliability costs to other customers, the cost-shifting concern at the core of E-8.

E-8 MISO: Show cause or propose tariff changes in 60 days (p. 5) E-8 MISO: Minimum cost recovery / security (P 119, p. 74)

Key points

  1. The organizations say the filing lets at least 30 GW of large load ramp fast and trip offline without limits.
    give at least 30 gigawatts (“GW”) of large load, though likely more, an unrestricted ability to ramp at eye-watering speeds and trip offline unexpectedly PDF p. 1
  2. MISO would fully exempt loads in service by December 4, 2026 and partly exempt loads tied to MTEP 2026 or EPR projects.
    large loads with a Service Commencement Date on or prior to December 4, 2026 will be entirely exempt from any reliability requirements PDF p. 2
  3. They say the exemptions go beyond the Show Cause Order and shift cost from large loads to other customers.
    MISO’s proposed exemptions go far beyond what the Commission’s Show Cause Order directed, represent a broad cost shift from large loads to other MISO customers PDF p. 2
  4. They cite a PJM event in which 3.8 GW of load tripped, about a tenth of the load MISO would exempt.
    PJM recently narrowly averted blackouts when 3.8 GW of load–a mere tenth of the load MISO proposes to exempt–tripped offline instantaneously. PDF p. 4
  5. They argue MISO has not shown any study of the reliability effect of the exemptions.
    if MISO has conducted any studies or analysis of the reliability impact of its proposed exemptions. PDF p. 3
  6. They object that most critical restrictions sit in Business Practices Manuals, which limits enforcement.
    MISO proposes to put most of the critical restrictions of the IRR Filing in Business Practices Manuals (“BPMs”). PDF p. 2
  7. An attached declaration puts the exempt load near a quarter of MISO's current summer peak.
    This makes 30,000 MW more than 24% of MISO’s current peak summer demand, and 20% of MISO’s peak summer demand with the new large loads in-service. PDF p. 29
Contents · 14 sections
  1. I. Introduction p. 1
  2. II. Argument p. 2
  3. A. The Commission should not allow broad exemptions from reliability p. 2
  4. B. The Commission should ensure harmonization of MISO and NERC p. 16
  5. C. MISO improperly defers critical details for each requirement to BPMs. p. 18
  6. III. Conclusion p. 23
  7. Attachment A p. 26
  8. I. Introduction p. 27
  9. II. Purpose of Declaration p. 28
  10. III. Analysis p. 28
  11. A. Recent events which inform my understanding of the impact of data centers on the reliability of p. 28
  12. B. Contextual comparison of 30,000 MW to MISO’s current peak demand. p. 29
  13. C. My opinion of MISO’s proposed exemptions. p. 29
  14. IV. Conclusion p. 30

Read topic-matched comments in ER26-3650

Topics in the text: Cost allocation · Reliability and curtailment · Filing procedure

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

1 UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION Midcontinent Independent ) Docket No.
Read this passage

I. Introduction

printed heading

ER26-3650, Accession No. 20260828-5278 (Aug. 28, 2026) [hereinafter “IRR Filing”]. 2 ability, as MISO proposes to put most of the critical restrictions of the IRR Filing in Business Practices Manuals (“BPMs”).
Read this passage

II. Argument

printed heading

II.
Read this passage

A. The Commission should not allow broad exemptions from reliability

printed heading · Topic match: Cost allocation

FERC, 76 F.4th 352, 357 (5th Cir. 2023). 7 degree the costs actually caused by the customer who must pay them”22 To implement the principle, courts and the Commission “compar[e] the costs assessed against a party to the burdens imposed or benefits drawn by that party.”23 To meet the cost causation…
Read this passage Filed comments: Cost allocation

B. The Commission should ensure harmonization of MISO and NERC

printed heading

MISO proposes to make its tariff effective as of December 4, 2026, a mere 27 days before NERC will file its standards, and many of the requirements will not be applicable until September 1, 2027.51 Under MISO’s current proposed exemption framework, it is unlikely many, if any, large loads would be…
Read this passage

C. MISO improperly defers critical details for each requirement to BPMs.

printed heading

The Commission determines which terms must be in the tariff, as opposed to a BPM, pursuant to the rule of reason.
Read this passage

III. Conclusion

printed heading

Conclusion MISO’s IRR Filing creates broad, dangerous exemptions to reliability requirements that MISO proposes to inappropriately house in BPMs.
Read this passage

CERTIFICATE OF SERVICE

printed heading

Dated this 18th day of September, 2026. /s/ Jonah Baskin Jonah Baskin Associate Attorney Sierra Club Environmental Law Program 50 F St.
Read this passage

Attachment A

printed heading

Attachment A 1 Declaration of Andrew Siebenaler I, Andrew Siebenaler, declare as follows:
Read this passage

I. Introduction

printed heading

I am an electrical engineer and the Managing Consultant - Transmission at Energy Futures Group.
Read this passage

II. Purpose of Declaration

printed heading

I am familiar with MISO’s proposed reliability requirements and the proposed application of the requirements. 9.
Read this passage

III. Analysis

printed heading

III.
Read this passage

A. Recent events which inform my understanding of the impact of data centers on the reliability of

printed heading

Recent events which inform my understanding of the impact of data centers on the reliability of transmission systems. 12.
Read this passage

B. Contextual comparison of 30,000 MW to MISO’s current peak demand.

printed heading

Contextual comparison of 30,000 MW to MISO’s current peak demand. 15.
Read this passage

C. My opinion of MISO’s proposed exemptions.

printed heading

In my professional opinion, MISO’s August 28th filing creates reliability risks by exempting approximately 30,000 MW of large load from reliability requirements.
Read this passage

IV. Conclusion

printed heading

In conclusion, under the exemptions proposed by MISO to the reliability requirements for large loads, a magnitude of load equivalent to roughly one-quarter of MISO’s current summer peak, or equivalent to the combined summer peak demand of LRZs 1 and 2, is at risk of operating in unexpected ways, or…