Motion for Leave to Answer and Answer of Coalition of MISO Transmission Customers et al. to the Joint Protest of the Sierra Club et al
Six large industrial customer groups answer the protests of MISO's large-load reliability filing and defend its grandfathering provisions as protecting existing manufacturers, with cost-shift concerns left to MISO's later filing.
Asks FERC to: Accept MISO's grandfathering and transition provisions and treat cost-shifting objections as belonging to MISO's forthcoming cost-shift filing.
Answers protests of MISO's first post-E-8 filing, citing the order's instruction to protect existing commercial arrangements and placing cost-shift protections in MISO's separate filing due under the abeyance deadline.
E-8 MISO: Show cause or propose tariff changes in 60 days (p. 5) E-8 MISO: Cost-recovery agreement (P 6(b), p. 6)
Key points
- The Large Energy Users say the grandfathering terms balance reliability against commercial certainty for existing manufacturers.
strike a balance between managing reliability issues caused by new Large Loads, while protecting commercial certainty for existing manufacturers and industrial customers. PDF p. 2
- They point to the E-8 order's statement that the proceeding aims at prospective reforms, not disruption of existing arrangements.
This proceeding is not intended to disrupt existing commercial arrangements, but rather to establish prospective reforms. PDF p. 3
- They describe MISO's two exempt categories: service commencement by December 4, 2026, and MTEP 2026 or EPR-linked projects.
Large Loads with a Service Commencement Date on or prior to December 4, 2026 PDF p. 4
- They say the protestors have not shown that long-standing industrial loads cause the reliability concerns.
The Show Cause Order is aimed at recent and exponential growth of Large Loads, not at large customers who have been reliably participating in MISO for decades. PDF p. 5
- They say cost-shift concerns belong in MISO's separate cost-shift filing, due November 16, 2026.
these concerns are more appropriately addressed in a future filing specifically focused on cost shifting risk among transmission customers. PDF p. 6
- They argue the proposal reflects the stakeholder process and deserves deference.
The Commission affords an appropriate amount of deference to consensus-based proposals developed during the stakeholder process. PDF p. 7
Contents · 7 sections
- I. MOTION FOR LEAVE TO ANSWER
- II. ANSWER
- A. MISO’s Grandfathering/Transition Proposal is Just and Reasonable and
- B. The Public Interest Organizations and Consumer Interest Advocates Have
- C. Concerns about Cost Shifting Risk among Transmission Customers are More
- D. MISO’s Proposal Reflects Feedback Provided During the Stakeholder
- III. CONCLUSION & REQUEST FOR RELIEF
Read topic-matched comments in ER26-3650
Topics in the text: Cost allocation · Registry access · Filing procedure
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Registry access
ER26-3650-000 MOTION FOR LEAVE TO ANSWER PROTESTS AND ANSWER OF THE LARGE ENERGY USERS Pursuant to Rules 212 and 213 of the Federal Energy Regulatory Commission’s (“FERC” or “Commission”) Rules of Practice and Procedure,1 the Coalition of MISO Transmission Customers (“CMTC), the Illinois Industrial…Read this passage Filed comments: Registry access
I. MOTION FOR LEAVE TO ANSWER
printed heading
MOTION FOR LEAVE TO ANSWER The Large Energy Users respectfully request leave to file this Answer.Read this passage
II. ANSWER
printed heading
II.Read this passage
A. MISO’s Grandfathering/Transition Proposal is Just and Reasonable and
printed heading
MISO’s Grandfathering/Transition Proposal is Just and Reasonable and Consistent with the June 18, 2026 Show Cause Order’s Objective to Protect Existing Commercial Arrangements.Read this passage
B. The Public Interest Organizations and Consumer Interest Advocates Have
printed heading
The North American Electric Reliability Corporation (“NERC”) has highlighted numerous reliability challenges presented by emerging Large Loads, and electrical characteristics of computational loads specifically.9 The PIOs accurately discuss the Commission’s cost-causation principle10 and assert…Read this passage
C. Concerns about Cost Shifting Risk among Transmission Customers are More
printed heading · Topic match: Cost allocation
The Large Energy Users appreciate the cost shifting and transparency concerns raised by the PIOs and Consumer Interest Advocates; however, these concerns are more appropriately addressed in a future filing specifically focused on cost shifting risk among transmission customers.Read this passage Filed comments: Cost allocation
D. MISO’s Proposal Reflects Feedback Provided During the Stakeholder
printed heading · Topic match: Cost allocation
ER26-3650-000, at 2-4, 8-9, 22; see also Prepared Direct Testimony of Beibei Li at 22:18-23:5, 34:12-39:22 (detailing the various stakeholder meetings, workshops, and feedback requests since 2024). 16 See, e.g., Sw.Read this passage Filed comments: Cost allocation
III. CONCLUSION & REQUEST FOR RELIEF
printed heading
CONCLUSION & REQUEST FOR RELIEF WHEREFORE, the Coalition of MISO Transmission Customers, the Illinois Industrial Energy Consumers, Association of Businesses Advocating Tariff Equity, the NIPSCO Large Customer Group, the Louisiana Energy Users Group, and the Texas Industrial Energy Consumers…Read this passage
CERTIFICATE OF SERVICE
printed heading
Dated this 2nd day of October 2026. /s/ Victoria A.Read this passage