ER26-3552-000 · 2026-10-08 · Natural Resources Defense Council, Sierra Club and 2 others

Motion for Leave to Answer and Answer of Community Organizations and Clean Energy Advocates to Midcontinent Independent System Operator, Inc.’s 09/23/2026 Answer

Community Organizations and Clean Energy Advocates (Sierra Club, NRDC and others) answer MISO's September 23 response on the ZGIA, with testimony from Grid Strategies' Houtan Moaveni, and say operational, cost-shift and program-limit gaps remain.

Asks FERC to: Find MISO's ZGIA filing deficient and direct MISO to cure its operational, cost allocation, transparency, program limit and hybrid resource gaps before accepting it.

Reply in ER26-3552 contesting MISO's ZGIA, MISO's co-location response to the E-8 order, on operational enforcement, cost shifting and transparency grounds the filers tie to the E-8 order.

E-8 MISO: Services for flexible / co-located loads (P 6(d), p. 7) E-8 MISO: Cost-recovery agreement (P 6(b), p. 6) E-8 MISO: Show cause or propose tariff changes in 60 days (p. 5)

Key points

  1. The filers say MISO's answer leaves the ZGIA's deficiencies in place.
    MISO’s Answer does not redress the deficiencies of its proposal. PDF p. 1
  2. They say the 20-second Transient Tolerance Window is still unjustified.
    MISO did not justify the tariff’s use of a twenty-second Transient Tolerance Window PDF p. 5
  3. They say key operating terms belong in the tariff, not the Business Practice Manual.
    It is well-established precedent that key terms must be included in the tariff. PDF p. 6
  4. They say termination is MISO's only remedy for injection failures, with nothing at the scale of an injection event.
    The contractual remedy that MISO has proposed functions only as a “last-resort backstop,” offering no consequence other than termination and nothing that operates on the timescale of an injection event. PDF p. 9
  5. They say cumulative ZGIA and DPP grid impacts would be resolved in MTEP, which spreads costs to load.
    The Commission should reject the filing as deficient because both MISO’s filing and MISO’s Answer fail to either refute such cumulative impacts or justify their resolution in MTEP, which socializes costs to load more broadly. PDF p. 15
  6. They say upgrades needed if a ZG resource never materializes would be socialized through MTEP.
    if a ZG resource does not materialize and thus causes the underlying transmission need to re-emerge, the resulting transmission upgrades that would still be needed to serve the associated load would be broadly socialized via MTEP. PDF p. 16
  7. They propose a list of ZGIA data for MISO to publish, starting with quarterly requests by size, technology, location and status.
    Mr. Moaveni instead recommends that the Commission direct MISO to publish: the ZG requests received in each quarterly study period, with megawatt quantity, technology, location, and status; PDF p. 18
  8. They say the filing ignores resource adequacy effects of generation dedicated to specific loads, and seek program-wide limits.
    the Filing does not examine how a growing share of generation dedicated to specific loads affects resource adequacy for the rest of the system. PDF p. 19
  9. They welcome MISO's hybrid resource clarifications and ask for a broader directive.
    the Commission should issue a broader directive to confirm the other points under discussion in the tariff as well. PDF p. 20
  10. They conclude by asking FERC to direct MISO to cure the deficiencies before accepting the filing.
    ask the Commission to use its authority to direct MISO to cure the deficiencies with filing before accepting it. PDF p. 21
Contents · 36 sections
  1. B. MISO’s Answer Fails to Disprove or Justify the ZGIA Process’s Creation of Potential p. 2
  2. C. MISO’s Answer is Nonresponsive to Key Concerns Related to the Lack of Overall Limits p. 2
  3. D. MISO’s Answer Provides Some Helpful Clarification Regarding Hybrid Resource p. 2
  4. ATTACHMENT A: TESTIMONY OF HOUTAN MOAVENI, GRID STRATEGIES…….24 p. 2
  5. A. MISO’s Answer Does Not Cure Concerns with ZGIA’s Operational Requirements. p. 4
  6. B. MISO’s Answer Fails to Disprove or Justify the ZGIA Process’s Creation of p. 13
  7. C. MISO’s Answer is Nonresponsive to Key Concerns Related to the Lack of Overall p. 18
  8. D. MISO’s Answer Provides Some Helpful Clarification Regarding Hybrid Resource p. 20
  9. CONCLUSION p. 21
  10. ATTACHMENT A p. 24
  11. I. Introduction p. 26
  12. A. My name is Houtan Moaveni. I am a Vice President at Grid Strategies LLC, where I advise on p. 26
  13. A. The purpose of my testimony is to evaluate the Zero Injection Generator Interconnection p. 27
  14. II. Summary of Findings p. 28
  15. A. MISO proposes a new form of interconnection service, ZG Interconnection Service, for a p. 28
  16. A. Based on my review of the Filing, I have identified the following issues: p. 29
  17. III. Enforceability of the Operating Requirements p. 32
  18. A. MISO proposes the following: p. 32
  19. A. The proposed measures do not provide adequate assurance that the zero-injection obligation p. 34
  20. A. The proposed contractual remedy functions only as a last-resort backstop. It offers no p. 35
  21. A. Only in part. The standard that determines whether an injection is permitted is not in the Tariff, p. 42
  22. A. Only in part. The requirements to verify compliance with the proposal’s operational provisions p. 47
  23. IV. Modeling Assumptions and Cost Allocation p. 50
  24. A. Two features of MISO’s proposal bear on who bears transmission costs and when. The first is p. 50
  25. A. MISO attributes much of the value of a ZGIA to transmission planning. MISO’s witness states p. 50
  26. A. The models used to study ZG requests exclude the pending interconnection queue. MISO states p. 55
  27. A. Yes. The ERAS process has produced executed interconnection agreements, and one of them p. 58
  28. A. No. The Filing contains several provisions that bear on the question, but none of them functions p. 60
  29. A. No. The Filing’s one meaningful transparency provision is that executed ZGIAs will be filed p. 63
  30. V. Eligibility and Limitations on the ZGIA Process p. 65
  31. A. MISO states that the requirements are facially neutral, fuel-agnostic, and open to any resource p. 65
  32. A. The Filing imposes several project-level eligibility constraints, while the program as a whole p. 66
  33. A. The Filing contains no sunset date for the ZGIA process. It contains no aggregate cap on the p. 67
  34. A. There are two principal consequences. First, the Filing does not examine how a growing share p. 69
  35. VI. Conclusion p. 70
  36. A. Yes. p. 70

Read topic-matched comments in ER26-3552

Topics in the text: Connecting load and generation · Cost allocation · Reliability and curtailment

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Cost allocation

MOTION FOR LEAVE TO ANSWER AND ANSWER Pursuant to Rule 213(a)(3) of the Federal Energy Regulatory Commission’s (“FERC”) Rules of Practice and Procedure,1 Community Organizations and Clean Energy Advocates respectfully submit this Motion for Leave to Answer and Answer to MISO’s Answer filed on…
Read this passage Filed comments: Cost allocation

B. MISO’s Answer Fails to Disprove or Justify the ZGIA Process’s Creation of Potential

printed heading · Topic match: Cost allocation

B.
Read this passage Filed comments: Cost allocation

C. MISO’s Answer is Nonresponsive to Key Concerns Related to the Lack of Overall Limits

printed heading

C.
Read this passage

D. MISO’s Answer Provides Some Helpful Clarification Regarding Hybrid Resource

printed heading

D.
Read this passage

ATTACHMENT A: TESTIMONY OF HOUTAN MOAVENI, GRID STRATEGIES…….24

printed heading · Topic match: Cost allocation

ER25-1674 last year. 4 cost allocation methods that shift certain types of costs from ZG resources by socializing them more broadly; and the lack of system-wide limits on the ZGIA process, of which MISO fails to appropriately consider the broader implications.
Read this passage Filed comments: Cost allocation

A. MISO’s Answer Does Not Cure Concerns with ZGIA’s Operational Requirements.

printed heading · Topic match: Connecting load and generation

It is well-established precedent that key terms must be included in the tariff.23 This precedent is important.
Read this passage Filed comments: Connecting load and generation

B. MISO’s Answer Fails to Disprove or Justify the ZGIA Process’s Creation of

printed heading · Topic match: Cost allocation

MISO further avers that the transparency measures requested by Community Organizations and Clean Energy Advocates are not required of requests in the Definitive Planning Phase, and that MISO does not propose to reduce any generally applicable transparency requirement.82 As Mr.
Read this passage Filed comments: Cost allocation

C. MISO’s Answer is Nonresponsive to Key Concerns Related to the Lack of Overall

printed heading · Topic match: Reliability and curtailment

Moaveni explains, “the Filing does not examine how a growing share of generation dedicated to specific loads affects resource adequacy for the rest of the system.”88 Moreover, at a time in which the high cost of new entry continues to be prohibitively expensive and capacity prices continue to…
Read this passage Filed comments: Reliability and curtailment

D. MISO’s Answer Provides Some Helpful Clarification Regarding Hybrid Resource

printed heading · Topic match: Connecting load and generation

Moaveni notes four areas of uncertainty that such a framework would 91 Community Organizations and Clean Energy Advocates Protest at 16-18. 92 Id. at 26-27. 93 MISO Answer at 20-21. 94 Id. at 21. 95 Id. at 20. 96 Moaveni Testimony at 41. 21 create for hybrid resources, “where the defining…
Read this passage Filed comments: Connecting load and generation

CONCLUSION

printed heading · Topic match: Cost allocation

Doshi Ada Statler Christine Powell Aaliyah Adkins Earthjustice 311 S.
Read this passage Filed comments: Cost allocation

CERTIFICATE OF SERVICE

printed heading

DATED: October 8, 2026 /s/ Ada Statler Ada Statler Earthjustice 180 Steuart St. #194330 San Francisco, CA 94105 astatler@earthjustice.org
Read this passage

ATTACHMENT A

printed heading · Topic match: Cost allocation

ER26-3552-000 ) Testimony of Houtan Moaveni in Support of the Protest of Community Organizations and Clean Energy Advocates
Read this passage Filed comments: Cost allocation

I. Introduction

printed heading

I.
Read this passage

A. My name is Houtan Moaveni. I am a Vice President at Grid Strategies LLC, where I advise on

printed heading

I am a Vice President at Grid Strategies LLC, where I advise on energy policy, siting and permitting, transmission planning, and generation interconnection.
Read this passage

A. The purpose of my testimony is to evaluate the Zero Injection Generator Interconnection

printed heading · Topic match: Connecting load and generation

Page citations to the MISO Answer are to the pages of the filed PDF. 3 A properly designed zero-injection interconnection service could facilitate generation dedicated to serving new load and avoid unnecessary transmission construction, and MISO narrowed the product in several respects during its…
Read this passage Filed comments: Connecting load and generation

II. Summary of Findings

printed heading · Topic match: Connecting load and generation

Please summarize MISO’s proposed new form of interconnection service.
Read this passage Filed comments: Connecting load and generation

A. MISO proposes a new form of interconnection service, ZG Interconnection Service, for a

printed heading · Topic match: Connecting load and generation

MISO proposes a new form of interconnection service, ZG Interconnection Service, for a generating facility that connects at the same voltage level of the same substation as a Point of Withdrawal of an identified load, and that serves only that load.3 The amount of interconnection service is capped…
Read this passage Filed comments: Connecting load and generation

A. Based on my review of the Filing, I have identified the following issues:

printed heading · Topic match: Connecting load and generation

ZGIA studies exclude pending Interconnection Requests without executed agreements, and the Definitive Planning Phase (DPP) base case is not updated for ZGIAs approved mid-cycle.
Read this passage Filed comments: Connecting load and generation

III. Enforceability of the Operating Requirements

printed heading

What measures does MISO propose to ensure that resources with ZGIAs comply with the operating requirements?
Read this passage

A. MISO proposes the following:

printed heading

Equipment obligations in the agreement: The interconnection customer must install communications and monitoring equipment enabling it to monitor the demand of the associated load; install equipment enabling it to reduce injections to a level not exceeding that demand within the Transient Tolerance…
Read this passage

A. The proposed measures do not provide adequate assurance that the zero-injection obligation

printed heading

The proposed measures do not provide adequate assurance that the zero-injection obligation will be met, in three respects.
Read this passage

A. The proposed contractual remedy functions only as a last-resort backstop. It offers no

printed heading · Topic match: Connecting load and generation

The injection-limiting 12 scheme must act whenever the load’s withdrawal falls, not only when the load trips entirely, and termination removes the load’s dedicated supply for the remainder of the term, long after the event that triggered it.
Read this passage Filed comments: Connecting load and generation

A. Only in part. The standard that determines whether an injection is permitted is not in the Tariff,

printed heading

The standard that determines whether an injection is permitted is not in the Tariff, and the Tariff does not specify what a resource must do to stay within it.
Read this passage

A. Only in part. The requirements to verify compliance with the proposal’s operational provisions

printed heading · Topic match: Connecting load and generation

At a minimum, those criteria should specify the maximum permitted export and its duration; the time within which the limiting action must begin and the rate at which output must then be reduced; the required behavior on loss of communications between the load and the generating facility, or loss of…
Read this passage Filed comments: Connecting load and generation

IV. Modeling Assumptions and Cost Allocation

printed heading · Topic match: Cost allocation

How could MISO’s proposal affect responsibility for transmission costs?
Read this passage Filed comments: Cost allocation

A. Two features of MISO’s proposal bear on who bears transmission costs and when. The first is

printed heading

Two features of MISO’s proposal bear on who bears transmission costs and when.
Read this passage

A. MISO attributes much of the value of a ZGIA to transmission planning. MISO’s witness states

printed heading · Topic match: Filing procedure

Specifically, the Answer explains that the ZG Interconnection Study must find that a project requires no Network Upgrades beyond the interconnecting substation, and concludes that “the ZGIA process does not permit MISO simply to defer broader Network Upgrades and their associated costs.”41 MISO…
Read this passage Filed comments: Filing procedure

A. The models used to study ZG requests exclude the pending interconnection queue. MISO states

printed heading · Topic match: Connecting load and generation

MISO’s Answer states that a ZG resource seeking Energy Resource Interconnection Service (ERIS) or Network Resource Interconnection Service (NRIS) must submit a new Interconnection Request and proceed through the DPP on the same footing as other requests,53 which is correct as to injection rights;…
Read this passage Filed comments: Connecting load and generation

A. Yes. The ERAS process has produced executed interconnection agreements, and one of them

printed heading · Topic match: Connecting load and generation

A §§ A5, A6-1, A6-2. 35 as resembling the ERAS process in its study aspects, timing, and financial obligations,59 and ZGIA studies likewise exclude pending requests without executed agreements.
Read this passage Filed comments: Connecting load and generation

A. No. The Filing contains several provisions that bear on the question, but none of them functions

printed heading · Topic match: Connecting load and generation

The upgrades at issue are those needed to serve the associated load, which are determined later, in a different process, under different cost allocation rules.
Read this passage Filed comments: Connecting load and generation

A. No. The Filing’s one meaningful transparency provision is that executed ZGIAs will be filed

printed heading · Topic match: Cost allocation

MISO’s Answer responds that these disclosures are not required of requests in the Definitive Planning Phase, and that MISO does not propose to reduce any generally applicable transparency requirement.68 MISO is not reducing existing transparency, but the question is whether existing procedures…
Read this passage Filed comments: Cost allocation

V. Eligibility and Limitations on the ZGIA Process

printed heading

Eligibility and Limitations on the ZGIA Process Q.
Read this passage

A. MISO states that the requirements are facially neutral, fuel-agnostic, and open to any resource

printed heading · Topic match: Connecting load and generation

MISO has stated in the stakeholder process that charging by a storage resource with a ZGIA “will follow the same process as other storage resources – storage charging is not considered during the interconnection queue process; instead, it is studied as an obligation to secure transmission service…
Read this passage Filed comments: Connecting load and generation

A. The Filing imposes several project-level eligibility constraints, while the program as a whole

printed heading

The Filing also includes one express process-wide throughput limit, under which MISO will study no more than ten Interconnection Requests in each quarterly study period, with overflow rolling forward in submission order.75 That is a throughput constraint governing the rate at which requests are…
Read this passage

A. The Filing contains no sunset date for the ZGIA process. It contains no aggregate cap on the

printed heading · Topic match: Connecting load and generation

It contains no locational or electrical concentration limit, so ten requests in a single quarter may be located at electrically adjacent substations, with the 75GIP § 3.11.2. 43 cumulative short-circuit and protection effects discussed in Section IV.
Read this passage Filed comments: Connecting load and generation

A. There are two principal consequences. First, the Filing does not examine how a growing share

printed heading · Topic match: Reliability and curtailment

A ZG resource may not serve any load other than its associated load, and its capacity credits must be used in a Fixed Resource Adequacy Plan or Reliability-Based Demand Curve opt-out rather than offered into the Planning Resource Auction.79 Whether that matters depends on whether the pathway…
Read this passage Filed comments: Reliability and curtailment

VI. Conclusion

printed heading

VI.
Read this passage

A. Yes.

printed heading

ER26-3552-000 ) VERIFICATION I, Houtan Moaveni, pursuant to 28 U.S.C. § 1746, state, under penalty of perjury, that: I am the same Houtan Moaveni referred to in the foregoing document entitled “Testimony of Houtan Moaveni in Support of the Protest of Community Organizations and Clean Energy…
Read this passage