PJM informational filing on the September 30, 2026 Members Committee vote on governance term sheets
PJM informs FERC that its Members Committee approved a Members term sheet by a two-thirds sector-weighted vote on September 30, 2026, in the confidential governance talks under AD26-7, and that state representatives find it unsatisfactory.
A PJM governance update in AD26-7. It has no direct tie to a show cause directive, though it concerns the stakeholder process surrounding PJM's large-load filings.
Key points
- Confidential talks facilitated by FERC's Dispute Resolution Service began September 1.
on September 1st, representatives of PJM, the states in the region, Members, and stakeholders commenced confidential and privileged discussions facilitated by FERC's Dispute Resolution Service. PDF p. 1
- The Members term sheet won the required two-thirds vote over the PJM and Consumer Advocates term sheets.
The Members term sheet, sponsored by a group of PJM Members, received the requisite sector-weighted two-thirds majority vote of the PJM Members Committee PDF p. 1
- PJM reports that the Organization of PJM States and the Governors' Collaborative do not view the approved term sheet as satisfactory.
the Organization of PJM States, Inc., the PJM Governors' Collaborative and other state representatives do not view the approved term sheet as satisfactory. PDF p. 1
Read topic-matched comments in AD26-7
Topics in the text: Registry access
What the document says
PDF p. 1
The Members term sheet won the two-thirds sector-weighted Members Committee vote.
The Members term sheet, sponsored by a group of PJM Members, received the requisite sector-weighted two-thirds majority vote of the PJM Members Committee PDF p. 1
PDF p. 1
Neither PJM's own term sheet nor the Consumer Advocates' reached even a majority.
Neither PJM’s nor the Consumer Advocates’ term sheet received the requisite two-thirds or even a majority vote. PDF p. 1Filed comments: Registry access
PDF p. 1
PJM says the states and governors do not find the approved term sheet satisfactory.
the Organization of PJM States, Inc., the PJM Governors’ Collaborative and other state representatives do not view the approved term sheet as satisfactory. PDF p. 1
Elsewhere in the record
Other parties on the same questions, in their own documents.
- States object to members controlling access to FERC OPSI and PJM Governors’ Collaborative governance negotiating team
- LaCerte points to gridlock in PJM’s stakeholder process Commissioner David LaCerte
- Rosner links investment signals to state confidence Commissioner David Rosner
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Registry access
The Members term sheet, sponsored by a group of PJM Members, received the requisite sector-weighted two-thirds majority vote of the PJM Members Committee, and advanced over a PJM term sheet and over a Consumer Advocates term sheet.Read this passage Filed comments: Registry access
CERTIFICATE OF SERVICE
PDF bookmark
Legal Operations Analyst I Office of General Counsel PJM Interconnection, L.L.C. 2750 Monroe Blvd.Read this passage