AD26-7: the filed comments

These passages match a topic and a request or argument in the same sentence. A filing can quote another party. Read its page before attributing a position.

Cost allocation

PERSISTENCE ANALYTICS GROUP LLC

AD26-7-000 · 2026-07-02

Before Notice to Proceed (NTP), PJM and relevant stakeholders should have a structured way to evaluate whether demand, power deliverability, interconnection timing, contractual support, cost allocation, and execution readiness are sufficiently verified. PDF p. 2

PERSISTENCE ANALYTICS GROUP LLC

AD26-7-000 · 2026-07-16

Response to Panel 1 Questions 1 and 3: PJM Board Accountability and Governance Reform The PJM Board's role should include ensuring that major planning, market, and reliability decisions are supported by decision-grade evidence before they create durable financial obligations for ratepayers. PDF p. 2

Organization of PJM States, Inc.

AD26-7-000 · 2026-07-21

Second, should OPSI agree on resource adequacy or transmission cost allocation reforms, PJM or the Transmission Owners (“TOs”) should provide that solution to FERC in a way that FERC can accept it. PDF p. 1

PJM Legislators' Collaborative

AD26-7-000 · 2026-07-22

This group should have "jump ball" or direct filing rights to submit proposals to FERC regarding cost allocation and market rules – the same authorities available to states in many other RTOs. PDF p. 2

Pennsylvania Public Utility Commission

AD26-7-000 · 2026-07-22

Numerous critical policy choices that must be made to sustain a state’s electric grid as well as ratepayer citizens’ lives and livelihoods should not all be made by an RTO operating in an administrative ex parte stakeholder process that is not designed to balance public interests in the way that state commissioners bound to a public interest standard can. PDF p. 2

PJM LEGISLATORS' COLLABORATIVE

AD26-7-000 · 2026-07-23

This group should have "jump ball" or direct filing rights to submit proposals to FERC regarding cost allocation and market rules – the same authorities available to states in many other RTOs. PDF p. 2

Individual No Affiliation

AD26-7-000 · 2026-08-05

RATEPAYER PROTECTION DOES NOT PROTECT LANDOWNERS President Trump’s Ratepayer Protection Pledge establishes an important principle: companies creating extraordinary new electric demand should build, bring or buy the power they require and pay for the delivery infrastructure needed to serve them. Source text

Individual No Affiliation

AD26-7-000 · 2026-08-10

A governance process that explicitly records the difference between forecast, commitment, executability, and realized performance would improve the Commission's and states' ability to understand when a change in large-load conditions should affect planning, cost causation, or implementation sequencing. PDF p. 4

Individual No Affiliation

AD26-7-000 · 2026-08-17

Board 205 Rights: The PJM Board of Managers should have Federal Power Act (FPA) Section 205 filing rights across all major business functions, including transmission planning, cost allocation, the RTEP, as well as the energy and ancillary services markets. Source text

Individual No Affiliation

AD26-7-000 · 2026-08-19

Poor communication increases the likelihood that the states and the PJM Board will be at odds on proposals, especially those that would increase costs substantially for ratepayers. PDF p. 2

Illinois Commerce Commission

AD26-7-000 · 2026-08-19

14) Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal? PDF p. 11

Chesapeake Climate Action Network

AD26-7-000 · 2026-08-20

Poor communication increases the likelihood that the states and the PJM Board will be at odds on proposals, especially those that would increase costs substantially for ratepayers. PDF p. 2

Indiana Municipal Power Agency

AD26-7-000 · 2026-08-20

14) Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal? PDF p. 4

Ceres

AD26-7-000 · 2026-08-20

Poor communication increases the likelihood that the states and the PJM Board will be at odds on proposals, especially those that would increase costs substantially for ratepayers. PDF p. 1

Citizens Utility Board of Illinois

AD26-7-000 · 2026-08-21

The Board expertise requirements should be updated to include 1) a former state regulator and 2) an individual with experience representing ratepayer interests. PDF p. 11

North Carolina Electric Membership Corporation

AD26-7-000 · 2026-08-21

14) Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal? PDF p. 5

PJM Interconnection, L.L.C.

AD26-7-000 · 2026-08-21

14 | Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal? PDF p. 10

R Street Institute

AD26-7-000 · 2026-08-21

Compensation should not be tied to outcomes in contested domains, such as auction price levels or cost allocation shares, where a financial stake would give management an interest in distributive results. Source text

Evergreen Action

AD26-7-000 · 2026-08-21

​ Prioritize the Public Interest in PJM’s Core Identity ●​ Reflect affordability and the public interest in PJM’s governing charter: PJM Board members and staff should have an explicit and binding responsibility to serve the broader public interest, and to prioritize affordable rates for ratepayers. PDF p. 1

PJM Power Providers Group

AD26-7-000 · 2026-08-21

14 Should OPSI have 'jump ball' rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees? PDF p. 5

Vitol Inc.

AD26-7-000 · 2026-08-21

19) Should state representatives have a formal voting role in the stakeholder process (limited to certain topics, such as resource adequacy and regional transmission cost allocation) in addition to the consumer advocate votes? PDF p. 5

Illinois Municipal Electric Agency

AD26-7-000 · 2026-08-21

14) Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal? PDF p. 4

East Kentucky Power Cooperative, Inc.

AD26-7-000 · 2026-08-21

14) Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal? PDF p. 8

Tenaska Power Services Co.

AD26-7-000 · 2026-08-21

X 14) Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal? PDF p. 3

Duquesne Light Company

AD26-7-000 · 2026-08-21

14) Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal? PDF p. 11

Shell Energy North America (US), L.P.

AD26-7-000 · 2026-08-21

Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal? PDF p. 9

Financial Marketers CoalitionDC Energy, LLC

AD26-7-000 · 2026-08-21

Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal? PDF p. 7

PPL Electric Utilities Corporation

AD26-7-000 · 2026-08-21

16 14) Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal? PDF p. 16

FirstEnergy Service Company

AD26-7-000 · 2026-08-21

Under longstanding cost causation principles, the cost of meeting that demand should be borne by the new large loads, not existing customers. PDF p. 6

Rockland Electric Company

AD26-7-000 · 2026-08-21

X Comments: None 14) Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal? PDF p. 4

Advanced Energy United

AD26-7-000 · 2026-08-21

14) Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal? PDF p. 9

Office of the Ohio Consumers' Counsel

AD26-7-000 · 2026-08-21

PJM should also be required to consult formally with OPSI before any major section 205 filings, including significant resource- adequacy and transmission planning and cost allocation filings. PDF p. 13

American Municipal Power, Inc.

AD26-7-000 · 2026-08-21

”20 14) Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal? PDF p. 13

Individual No Affiliation

AD26-7-000 · 2026-08-21

We would, however, like to turn some attention to the effects of this conflict of interest, and in particular to the unreasonableness of the billions of dollars that are being unjustly extracted from ratepayers subject to PJM’s jurisdiction. Source text

American Electric Power Service Corporation

AD26-7-000 · 2026-08-21

14) Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal? PDF p. 29

Southern Maryland Electric Cooperative, Inc.

AD26-7-000 · 2026-08-21

14) Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal? PDF p. 4

Dominion Energy Services, Inc.

AD26-7-000 · 2026-08-21

Should state representatives have a formal voting role in the stakeholder process (limited to certain topics, such as resource adequacy and regional transmission cost allocation) in addition to the consumer advocate votes? PDF p. 12

PJM Industrial Customer Coalition

AD26-7-000 · 2026-08-21

X Comments: 14) Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal? PDF p. 13

NRG Energy, Inc.

AD26-7-000 · 2026-08-21

14 Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal? PDF p. 5

Dayton Power and Light Company, The

AD26-7-000 · 2026-08-21

14) Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal? PDF p. 3

ENGIE North America Inc.

AD26-7-000 · 2026-08-21

14) Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal? PDF p. 7

Capital Power Corporation

AD26-7-000 · 2026-08-21

Capital Power therefore supports requiring PJM to consult with OPSI before making section 205 filings related to resource adequacy, regional transmission cost allocation, and other matters that materially affect state responsibilities. PDF p. 10

National Grid Plc

AD26-7-000 · 2026-08-21

14) Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal? PDF p. 4

Exelon Corporation

AD26-7-000 · 2026-08-21

Question 14 – Jump Ball Rights for OPSI Yes No Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal? PDF p. 22

Buckeye Power, Inc.

AD26-7-000 · 2026-08-21

Y Comments: 14) Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal? PDF p. 5

Energy Artisans, LLC

AD26-7-000 · 2026-08-21

X 19 Should state representatives have a formal voting role in the stakeholder process (limited to certain topics, such as resource adequacy and regional transmission cost allocation) in addition to the consumer advocate votes? PDF p. 3

Talen Energy Corporation

AD26-7-000 · 2026-08-21

X 14) Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal? PDF p. 13

LS Power Development, LLC

AD26-7-000 · 2026-08-21

14 Should OPSI have 'jump ball' rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees? PDF p. 8

GERONIMO POWER, LLC

AD26-7-000 · 2026-08-21

14) Should OPSI have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal? PDF p. 20

PJM Cities and Communities Coalition

AD26-7-000 · 2026-08-21

14) Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal? Source text

Old Dominion Electric Cooperative

AD26-7-000 · 2026-08-21

14) Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal? PDF p. 12

Google LLC

AD26-7-000 · 2026-08-24

This is critical to ensure grid rules accommodate the integration of large loads and support state energy policies while protecting residential ratepayers from stranded asset risks or cost-shifting. PDF p. 6

Monitoring Analytics, LLC

AD26-7-000 · 2026-08-26

Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal? PDF p. 10

Filing procedure

Organization of PJM States, Inc.

AD26-7-000 · 2026-07-21

12 Building for the Future Through Electric Regional Transmission Planning and Cost Allocation, Unopposed Motion for Extension of Time and Request for Expedited Consideration of PARSEC and PJM Transmission Owners, Docket No. PDF p. 4

Registry access

PJM Cities and Communities Coalition

AD26-7-000 · 2026-07-22

PJM’s board selection process should include input from states, consumer advocates, and other stakeholders so as to deliver a board that is representative not only of PJM member utilities but of the region’s many other stakeholder sectors as well. PDF p. 6

PJM Legislators' Collaborative

AD26-7-000 · 2026-07-22

In addition, PJM should provide formal governance roles, as well as technical assistance and other resources to state representatives and consumer advocates. PDF p. 2

PJM LEGISLATORS' COLLABORATIVE

AD26-7-000 · 2026-07-23

In addition, PJM should provide formal governance roles, as well as technical assistance and other resources to state representatives and consumer advocates. PDF p. 2

Individual No Affiliation

AD26-7-000 · 2026-08-05

EARLY STATE AND COMMUNITY PARTICIPATION States, consumer advocates, local governments and representatives of affected communities should enter while meaningful alternatives remain available—not only after the broad electrical solution has been selected and routing has begun. Source text

Individual No Affiliation

AD26-7-000 · 2026-08-19

While granting OPSI 205 filing rights provides a backstop, increased consultation between the PJM Board, representatives of its member states and consumer advocates – such as getting feedback on draft filings – would foster trust, build credibility, and avoid litigation. PDF p. 2

Illinois Commerce Commission

AD26-7-000 · 2026-08-19

19) Should state representatives have a formal voting role in the stakeholder process (limited to certain topics, such as resource adequacy and regional transmission cost allocation) in addition to the consumer advocate votes? PDF p. 12

Chesapeake Climate Action Network

AD26-7-000 · 2026-08-20

Along with reserving a permanent seat for a consumer advocate, the Nominating Committee should also allow for one appointee from OPSI and another from a governors’/legislators’ organization - as recommended by the Governors’ Collaborative. PDF p. 2

League of Conservation Voters

AD26-7-000 · 2026-08-20

The decisions that the Board makes should be accountable to serving those ratepayers and transparent votes will ensure stakeholders, including consumer advocates, are more informed and capable of being informed participants throughout PJM’s decision-making process. PDF p. 2

Indiana Municipal Power Agency

AD26-7-000 · 2026-08-20

19) Should state representatives have a formal voting role in the stakeholder process (limited to certain topics, such as resource adequacy and regional transmission cost allocation) in addition to the consumer advocate votes? PDF p. 5

Ceres

AD26-7-000 · 2026-08-20

Along with reserving a permanent seat for a consumer advocate, the Nominating Committee should also allow for one appointee from OPSI and another from a governors’/legislators’ organization - as recommended by the Governors’ Collaborative. PDF p. 2

Citizens Utility Board of Illinois

AD26-7-000 · 2026-08-21

2 Any governance reforms proposed at PJM should strengthen not only the state voice, but also the voice of the 67 million customers that PJM serves, who are represented solely by statutory consumer advocates. PDF p. 2

North Carolina Electric Membership Corporation

AD26-7-000 · 2026-08-21

” 19) Should state representatives have a formal voting role in the stakeholder process (limited to certain topics, such as resource adequacy and regional transmission cost allocation) in addition to the consumer advocate votes? PDF p. 6

PJM Interconnection, L.L.C.

AD26-7-000 · 2026-08-21

19 | Should state representatives have a formal voting role in the stakeholder process (limited to certain topics, such as resource adequacy and regional transmission cost allocation) in addition to the consumer advocate votes? PDF p. 11

R Street Institute

AD26-7-000 · 2026-08-21

19) Should state representatives have a formal voting role in the stakeholder process (limited to certain topics, such as resource adequacy and regional transmission cost allocation) in addition to the consumer advocate votes? Source text

Evergreen Action

AD26-7-000 · 2026-08-21

This could include the development of a separate sector that is geared toward the needs of small end use customers and would include the consumer advocate members of PJM. PDF p. 2

PJM Power Providers Group

AD26-7-000 · 2026-08-21

19 Should state representatives have a formal voting role in the stakeholder process (limited to certain topics) in addition to consumer advocate votes? PDF p. 6

Vitol Inc.

AD26-7-000 · 2026-08-21

19) Should state representatives have a formal voting role in the stakeholder process (limited to certain topics, such as resource adequacy and regional transmission cost allocation) in addition to the consumer advocate votes? PDF p. 5

Duke Energy Ohio, Inc. and Duke Energy Kentucky, Inc.

AD26-7-000 · 2026-08-21

Should state representatives have a formal voting role in the stakeholder process (limited to certain topics, such as resource adequacy and regional transmission cost allocation) in addition to the consumer advocate votes? PDF p. 7

Illinois Municipal Electric Agency

AD26-7-000 · 2026-08-21

19) Should state representatives have a formal voting role in the stakeholder process (limited to certain topics, such as resource adequacy and regional transmission cost allocation) in addition to the consumer advocate votes? PDF p. 5

East Kentucky Power Cooperative, Inc.

AD26-7-000 · 2026-08-21

10 Questions/Comments Yes No 19) Should state representatives have a formal voting role in the stakeholder process (limited to certain topics, such as resource adequacy and regional transmission cost allocation) in addition to the consumer advocate votes? PDF p. 10

Tenaska Power Services Co.

AD26-7-000 · 2026-08-21

19) Should state representatives have a formal voting role in the stakeholder process (limited to certain topics, such as resource adequacy and regional transmission cost allocation) in addition to the consumer advocate votes? PDF p. 4

Duquesne Light Company

AD26-7-000 · 2026-08-21

19) Should state representatives have a formal voting role in the stakeholder process (limited to certain topics, such as resource adequacy and regional transmission cost allocation) in addition to the consumer advocate votes? PDF p. 13

Shell Energy North America (US), L.P.

AD26-7-000 · 2026-08-21

Should state representatives have a formal voting role in the stakeholder process (limited to certain topics, such as resource adequacy and regional transmission cost allocation) in addition to the consumer advocate votes? PDF p. 11

Financial Marketers CoalitionDC Energy, LLC

AD26-7-000 · 2026-08-21

Should state representatives have a formal voting role in the stakeholder process (limited to certain topics, such as resource adequacy and regional transmission cost allocation) in addition to the consumer advocate votes? PDF p. 9

PPL Electric Utilities Corporation

AD26-7-000 · 2026-08-21

If the PJM Board is supposed to act in the public interest, but in its independent judgment decides that standard calls for a different action than a gover- nor’s representative or consumer advocate urges (when they are also acting in the public inter- est), how should it resolve the matter? PDF p. 12

FirstEnergy Service Company

AD26-7-000 · 2026-08-21

X Comments: 19) Should state representatives have a formal voting role in the stakeholder process (limited to certain topics, such as resource adequacy and regional transmission cost allocation) in addition to the consumer advocate votes? PDF p. 14

Rockland Electric Company

AD26-7-000 · 2026-08-21

X Comments: None 19) Should state representatives have a formal voting role in the stakeholder process (limited to certain topics, such as resource adequacy and regional transmission cost allocation) in addition to the consumer advocate votes? PDF p. 5

Advanced Energy United

AD26-7-000 · 2026-08-21

19) Should state representatives have a formal voting role in the stakeholder process (limited to certain topics, such as resource adequacy and regional transmission cost allocation) in addition to the consumer advocate votes? PDF p. 12

Office of the Ohio Consumers' Counsel

AD26-7-000 · 2026-08-21

It would provide FERC, states, consumer advocates, and stakeholders with an independent source of information needed to determine whether billions of dollars in transmission investment are prudent, efficient, and beneficial to consumers. PDF p. 8

American Municipal Power, Inc.

AD26-7-000 · 2026-08-21

 Comments: Other than meetings or sessions specifically convened to discuss confidential information, as would occur in executive session, Board meetings should be open to and available for the public. PDF p. 10

American Electric Power Service Corporation

AD26-7-000 · 2026-08-21

19) Should state representatives have a formal voting role in the stakeholder process (limited to certain topics, such as resource adequacy and regional transmission cost allocation) in addition to the consumer advocate votes? PDF p. 31

Southern Maryland Electric Cooperative, Inc.

AD26-7-000 · 2026-08-21

X Comments: None 19) Should state representatives have a formal voting role in the stakeholder process (limited to certain topics, such as resource adequacy and regional transmission cost allocation) in addition to the consumer advocate votes? PDF p. 5

Dominion Energy Services, Inc.

AD26-7-000 · 2026-08-21

Should state representatives have a formal voting role in the stakeholder process (limited to certain topics, such as resource adequacy and regional transmission cost allocation) in addition to the consumer advocate votes? PDF p. 12

PJM Industrial Customer Coalition

AD26-7-000 · 2026-08-21

19) Should state representatives have a formal voting role in the stakeholder process (limited to certain topics, such as resource adequacy and regional transmission cost allocation) in addition to the consumer advocate votes? PDF p. 14

NRG Energy, Inc.

AD26-7-000 · 2026-08-21

19 Should state representatives have a formal voting role in the stakeholder process (limited to certain topics, such as resource adequacy and regional transmission cost allocation) in addition to the consumer advocate votes? PDF p. 5

Dayton Power and Light Company, The

AD26-7-000 · 2026-08-21

19) Should state representatives have a formal voting role in the stakeholder process (limited to certain topics, such as resource adequacy and regional transmission cost allocation) in addition to the consumer advocate votes? PDF p. 5

ENGIE North America Inc.

AD26-7-000 · 2026-08-21

AD26-07-000 Page 10 Questions/Comments Yes No 19) Should state representatives have a formal voting role in the stakeholder process (limited to certain topics, such as resource adequacy and regional transmission cost allocation) in addition to the consumer advocate votes? PDF p. 10

Capital Power Corporation

AD26-7-000 · 2026-08-21

Board sessions should remain closed where necessary to address personnel matters, cybersecurity, physical security, enforcement, litigation, privileged legal advice, commercially sensitive information, Critical Energy/Electric Infrastructure Information, or other confidential information protected by applicable law or Commission policy. PDF p. 7

National Grid Plc

AD26-7-000 · 2026-08-21

19) Should state representatives have a formal voting role in the stakeholder process (limited to certain topics, such as resource adequacy and regional transmission cost allocation) in addition to the consumer advocate votes? PDF p. 5

Exelon Corporation

AD26-7-000 · 2026-08-21

This reform would have the added benefit of addressing concerns, that have been expressed by the Commission and states regarding the need to prevent special interest groups, incumbent transmission and generation utilities, financial marketers, industrial customers and consumer advocates from capturing the regulatory process and vetoing market reforms that threaten their parochial business interests. PDF p. 18

Buckeye Power, Inc.

AD26-7-000 · 2026-08-21

19) Should state representatives have a formal voting role in the stakeholder process (limited to certain topics, such as resource adequacy and regional transmission cost allocation) in addition to the consumer advocate votes? PDF p. 6

Energy Artisans, LLC

AD26-7-000 · 2026-08-21

X 19 Should state representatives have a formal voting role in the stakeholder process (limited to certain topics, such as resource adequacy and regional transmission cost allocation) in addition to the consumer advocate votes? PDF p. 3

Talen Energy Corporation

AD26-7-000 · 2026-08-21

X 19) Should state representatives have a formal voting role in the stakeholder process (limited to certain topics, such as resource adequacy and regional transmission cost allocation) in addition to the consumer advocate votes? PDF p. 13

LS Power Development, LLC

AD26-7-000 · 2026-08-21

19 Should state representatives have a formal voting role in the stakeholder process (limited to certain topics) in addition to consumer advocate votes? PDF p. 9

GERONIMO POWER, LLC

AD26-7-000 · 2026-08-21

19) Should state representatives have a formal voting role in the stakeholder process (limited to certain topics, such as resource adequacy and regional transmission cost allocation) in addition to the consumer advocate votes? PDF p. 22

Old Dominion Electric Cooperative

AD26-7-000 · 2026-08-21

Specifically, there should be a requirement that at least two Board members have experience that would qualify for the Electric Distributor (end-use customer) sector and/or at least one Board position for a State PUC or consumer advocate. PDF p. 5

Google LLC

AD26-7-000 · 2026-08-24

19) Should state representatives have a formal voting role in the stakeholder process (limited to certain topics, such as resource adequacy and regional transmission cost allocation) in addition to the consumer advocate votes? PDF p. 8

Monitoring Analytics, LLC

AD26-7-000 · 2026-08-26

Should state representatives have a formal voting role in the stakeholder process (limited to certain topics, such as resource adequacy and regional transmission cost allocation) in addition to the consumer advocate votes? PDF p. 12

Reliability and curtailment

PERSISTENCE ANALYTICS GROUP LLC

AD26-7-000 · 2026-07-16

States should be able to review the underlying assumptions driving: - large-load forecasts; - data-center demand; - transmission need; - capacity-market exposure; - cost-causation findings; - resource adequacy risk; and - ratepayer impacts. PDF p. 3

Organization of PJM States, Inc.

AD26-7-000 · 2026-07-21

Second, should OPSI agree on resource adequacy or transmission cost allocation reforms, PJM or the Transmission Owners (“TOs”) should provide that solution to FERC in a way that FERC can accept it. PDF p. 1

PPL Electric Utilities Corporation

AD26-7-000 · 2026-07-22

However, a note of caution is war- ranted: The Commission and the participants in this docket should be sober about the limited ability of governance reform to address resource adequacy and should embark on this process with eyes open toward the real risk that things can get worse. PDF p. 2

PJM Legislators' Collaborative

AD26-7-000 · 2026-07-22

At the same time, states argue they are systematically excluded from meaningful governance despite bearing primary responsibility for energy policy, resource adequacy, and consumer protection. PDF p. 3

Pennsylvania Public Utility Commission

AD26-7-000 · 2026-07-22

When states collectively develop a consensus resource adequacy reform, they should have a clear pathway to put that proposal before FERC under Section 205 of the Federal Power Act. PDF p. 1

PJM LEGISLATORS' COLLABORATIVE

AD26-7-000 · 2026-07-23

At the same time, states argue they are systematically excluded from meaningful governance despite bearing primary responsibility for energy policy, resource adequacy, and consumer protection. PDF p. 3

Energy Artisans, LLC

AD26-7-000 · 2026-07-23

Create Expedited Procedures Certain issues—including reliability, resource adequacy, cybersecurity, and significant market integrity concerns—should be eligible for accelerated stakeholder review with clearly defined timelines. PDF p. 4

RTO Governance Research Network

AD26-7-000 · 2026-07-23

To that end, the RTO and the public interest would be helped if the Board were to have (at least shared) filing rights over all major aspects of PJM’s functions – including regional transmission planning and resource adequacy compliance. PDF p. 4

Illinois Commerce Commission

AD26-7-000 · 2026-08-19

14) Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal? PDF p. 11

League of Conservation Voters

AD26-7-000 · 2026-08-20

Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal? PDF p. 3

Indiana Municipal Power Agency

AD26-7-000 · 2026-08-20

14) Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal? PDF p. 4

Citizens Utility Board of Illinois

AD26-7-000 · 2026-08-21

PJM states should have this same capability across all issues—not only resource adequacy, which is jurisdictionally a state responsibility, but also transmission planning, which Order 1920 recognizes requires a robust state role. PDF p. 7

North Carolina Electric Membership Corporation

AD26-7-000 · 2026-08-21

14) Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal? PDF p. 5

PJM Interconnection, L.L.C.

AD26-7-000 · 2026-08-21

14 | Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal? PDF p. 10

R Street Institute

AD26-7-000 · 2026-08-21

14) Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal? Source text

PJM Power Providers Group

AD26-7-000 · 2026-08-21

14 Should OPSI have 'jump ball' rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees? PDF p. 5

Vitol Inc.

AD26-7-000 · 2026-08-21

19) Should state representatives have a formal voting role in the stakeholder process (limited to certain topics, such as resource adequacy and regional transmission cost allocation) in addition to the consumer advocate votes? PDF p. 5

Illinois Municipal Electric Agency

AD26-7-000 · 2026-08-21

14) Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal? PDF p. 4

East Kentucky Power Cooperative, Inc.

AD26-7-000 · 2026-08-21

A key theme in written and oral comments arising from the Technical Conference was that there should be a clear delineation of responsibilities between PJM and the “states” to achieve resource adequacy and ensure it will persist into the future. PDF p. 3

Tenaska Power Services Co.

AD26-7-000 · 2026-08-21

X 14) Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal? PDF p. 3

PSEG CompaniesPSEG Energy Resources & Trade LLCPSEG Power LLC ,Public Service Electric and Gas Company ,

AD26-7-000 · 2026-08-21

” In this regard, not all changes are created equal; for example, whether all or only certain PJM Board meetings are open to the public is not as significant from a governance reform perspective as deciding who should have filing rights or how votes should be taken or how to establish clear and workable rules around the future role of the states in resource adequacy decision-making. PDF p. 1

Duquesne Light Company

AD26-7-000 · 2026-08-21

14) Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal? PDF p. 11

Shell Energy North America (US), L.P.

AD26-7-000 · 2026-08-21

Equally important, they should maintain the checks and 3 See Meeting the Challenge of Resource Adequacy in Regional Transmission Organization and Independent System Operator Regions, Docket No. PDF p. 2

Financial Marketers CoalitionDC Energy, LLC

AD26-7-000 · 2026-08-21

Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal? PDF p. 7

FirstEnergy Service Company

AD26-7-000 · 2026-08-21

10 While PJM has limited tools to support resource adequacy, including administering markets to produce price signals and curtailment mechanisms, under the cooperative federalism framework, ultimate direct authority over resource adequacy rests with the states. PDF p. 3

Rockland Electric Company

AD26-7-000 · 2026-08-21

The intended result of longer Board terms should be to empower the Board to make decisions that improve reliability and resource adequacy within the PJM footprint. PDF p. 2

Advanced Energy United

AD26-7-000 · 2026-08-21

14) Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal? PDF p. 9

Office of the Ohio Consumers' Counsel

AD26-7-000 · 2026-08-21

14) Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal? PDF p. 25

CTC Global Corporation

AD26-7-000 · 2026-08-21

Governance Reform Should Be Evaluated by Whether It Enables PJM to Address Urgent Reliability, Affordability, and Transmission Needs Many of the challenges currently confronting PJM—resource adequacy, generation interconnection, large-load integration, affordability, and reliability—are closely linked to the availability of sufficient transmission capability. PDF p. 2

Southern Maryland Electric Cooperative, Inc.

AD26-7-000 · 2026-08-21

14) Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal? PDF p. 4

Dominion Energy Services, Inc.

AD26-7-000 · 2026-08-21

Yes, we support a Members Committee with jump ball filing rights over defined resource adequacy and energy and ancillary services reforms when a supermajority supports an alternative. PDF p. 11

PJM Industrial Customer Coalition

AD26-7-000 · 2026-08-21

X Comments: 14) Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal? PDF p. 13

NRG Energy, Inc.

AD26-7-000 · 2026-08-21

14 Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal? PDF p. 5

Dayton Power and Light Company, The

AD26-7-000 · 2026-08-21

14) Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal? PDF p. 3

ENGIE North America Inc.

AD26-7-000 · 2026-08-21

14) Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal? PDF p. 7

Capital Power Corporation

AD26-7-000 · 2026-08-21

In addition, to further enhance visibility of the Board’s decision-making processes, Capital Power also supports requiring PJM to provide public explanations when the Board acts on significant market-design, resource adequacy, transmission planning, interconnection, or governance matters. PDF p. 7

National Grid Plc

AD26-7-000 · 2026-08-21

14) Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal? PDF p. 4

Exelon Corporation

AD26-7-000 · 2026-08-21

Question 14 – Jump Ball Rights for OPSI Yes No Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal? PDF p. 22

Buckeye Power, Inc.

AD26-7-000 · 2026-08-21

Y Comments: 14) Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal? PDF p. 5

Energy Artisans, LLC

AD26-7-000 · 2026-08-21

X 19 Should state representatives have a formal voting role in the stakeholder process (limited to certain topics, such as resource adequacy and regional transmission cost allocation) in addition to the consumer advocate votes? PDF p. 3

Talen Energy Corporation

AD26-7-000 · 2026-08-21

X 14) Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal? PDF p. 13

LS Power Development, LLC

AD26-7-000 · 2026-08-21

14 Should OPSI have 'jump ball' rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees? PDF p. 8

GERONIMO POWER, LLC

AD26-7-000 · 2026-08-21

14) Should OPSI have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal? PDF p. 20

PJM Cities and Communities Coalition

AD26-7-000 · 2026-08-21

14) Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal? Source text

Old Dominion Electric Cooperative

AD26-7-000 · 2026-08-21

14) Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal? PDF p. 12

Google LLC

AD26-7-000 · 2026-08-24

Questions/Comments Yes No Neutral Comments: Same as 12 14) Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal? PDF p. 7

Monitoring Analytics, LLC

AD26-7-000 · 2026-08-26

Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal? PDF p. 10

Retail and wholesale authority

PJM Legislators' Collaborative

AD26-7-000 · 2026-07-22

The state authority should also include formal input mechanisms over regional planning assumptions, PJM’s load forecasting models, congestion analyses, and long-term transmission planning assumptions, transmission cost allocation, and resource adequacy metrics, requiring a formal administrative reconciliation process before major filings are submitted to FERC. PDF p. 24

PJM LEGISLATORS' COLLABORATIVE

AD26-7-000 · 2026-07-23

The state authority should also include formal input mechanisms over regional planning assumptions, PJM’s load forecasting models, congestion analyses, and long-term transmission planning assumptions, transmission cost allocation, and resource adequacy metrics, requiring a formal administrative reconciliation process before major filings are submitted to FERC. PDF p. 24

Evergreen Action

AD26-7-000 · 2026-08-21

●​ Respect state authority: PJM must adhere to and actively support state clean-energy laws and engage constructively in state resource planning. PDF p. 2

American Electric Power Service Corporation

AD26-7-000 · 2026-08-21

AEP supports a formal consultation right for the states with respect to Section 205 filings on matters within state jurisdiction, with the exception of certain transmission cost allocation issues. PDF p. 31