AD26-7-000 · 2026-08-21 · Duquesne Light Company

Post-Conference Comments of Duquesne Light Company re PJM Governance and Stakeholder Reforms

PDF page 1

1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Governance and Stakeholder Reforms

)
Docket No. AD26-7-000

POST-CONFERENCE COMMENTS OF DUQUESNE LIGHT COMPANY
I. INTRODUCTION

Duquesne Light Company (“Duquesne Light”) respectfully submits the following comments in response to the Notice Requesting Post-Conference Comment issued by the Federal Energy Regulatory Commission (“FERC” or “Commission”) on July 30, 2026, following the July 23, 2026 Technical Conference on PJM Governance and Stakeholder Reforms.1 The Technical Conference discussed important issues around how PJM governance works and the ability of the PJM stakeholders to work within that process to development consensus solutions for the betterment of the PJM region. Duquesne Light commends the Commission for holding the technical conference.

II. Duquesne Light Company’s Interest in the Proceeding

Duquesne Light is a FERC-jurisdictional Transmission and Distribution only utility that serves over 600,000 customers and operates in parts of Allegheny and Beaver Counties, located in Western Pennsylvania, including the city of Pittsburgh. Duquesne

1 Exploring The Current State of PJM Governance, Docket Number AD26-7-000 (FERC).

PDF page 2

2

Light operates over 670 miles of high-voltage transmission lines and over 7,200 miles of distribution lines. Duquesne Light has transferred operational control of its electric transmission facilities to the PJM Interconnection, L.L.C. (“PJM”), a Regional Transmission Operator (“RTO”). As a member of PJM, Duquesne Light is a Participating Transmission Owner (“PTO”) that operates in the PJM market and participates in the PJM Stakeholder process. As a PJM stakeholder and a PTO in the PJM region, Duquesne Light has unique interests that may be affected by the outcome of this proceeding and that cannot be fully represented by any other participant.

III. COMMENTS
A. PJM Governance Reform is Needed

The PJM stakeholder process was developed over 20 years ago during a time of excess supply, flat load growth and with far fewer stakeholders. In 2006, the PJM stakeholder process had fewer than 400 members.2 To meet the needs of the members and the environment at the time, a stakeholder process was built for slow, deliberate changes. The stakeholder process was not built to make quick changes or to be able to respond to an environment that is rapidly changing. It was built to allow significant time for all parties to consider issues, engage in lengthy discussion, conduct significant analysis and to ultimately reach consensus. One example is that it typically takes four months to hold the votes necessary to pass a typical proposal. Any proposal must go through a first read, before an

2 PJM Interconnection, L.L.C., PJM Summer 2006 Outlook at 2 (June 2006).

PDF page 3

3

endorsement vote can be held, and this occurs at both the standing and senior standing committees. For example, if a proposal comes through the Planning Committee, in month one there would be a first read at the Planning Committee. In month two, there would be an endorsement vote at the Planning Committee. If passed at the Planning Committee, in month three, there would be a first read at the Markets and Reliability Committee. In month four, there would be an endorsement vote at the Markets and Reliability Committee. A Members Committee vote is also typically required and could happen in parallel with, staggered with or after a successful endorsement vote at the Markets and Reliability Committee. Therefore, if the Members Committee vote were to happen following the Markets and Reliability Committee, the process could take six months, with the Members Committee first read happening in month five and the endorsement vote in month six. This process, while extremely effective at ensuring there is sufficient review and opportunity for feedback, is not built to be nimble. By design the stakeholder process is slow and methodical, built for deliberate consideration and consensus building. That design is at conflict with the challenges PJM is facing today.

Today, PJM membership includes over 1,100 members.3 Membership has more than doubled in the last 20 years. In addition, the landscape is drastically different from when the stakeholder process was designed. The explosive growth

3 PJM Interconnection, L.L.C., PJM Members Committee, Draft Minutes of the 285th Meeting (July 28, 2026).

PDF page 4

4

of data centers and the retirement of significant portions of the generation fleet has created a capacity shortfall. The PJM region is at a crossroads and the ability to provide customers with reliable and affordable service hangs in the balance. The PJM stakeholder process raises concerns regarding accountability and control. Vince Duane and Tony Clark aptly described the problem well in their 2021 whitepaper, “Who Owns the RTO?”

“RTOs are organized such that their customers, in the broadest sense imaginable, are also their owners, with ownership rights varying in practical degree and in all cases ambiguously stated legally. These customers exercise shared control over RTO

decisions and RTO management – notwithstanding the supposed
independence of RTOs. The peculiar RTO corporate structure is akin to the organization of a cooperative corporation, to the extent that each member typically exercises the same voting control, without regard to the member’s respective financial commitment and interest in the RTO. The structures have always been

bureaucratic, but they also dissipate any locus of control, blur ultimate accountability and not surprisingly, often fail to reach consensus, leaving important questions of market design and

operational protocol to be resolved by FERC through
administrative litigation.”4

This lack of accountability is a key flaw in PJM's governance. PJM’s stakeholder process constrains PJM’s ability to effectuate change, leaving outcomes largely dependent on stakeholders who “lack a shared purpose and vision when it comes to the RTO’s”5 and whose individual interests are far from aligned. Expecting this stakeholder body to compromise and reach consensus

4 Vincent Duane & Tony Clark, Who Owns the RTO? Why RTO Governance is an Achilles Heel in the Clean Grid Transition at 1 (Nov. 2021). 5 Id. at 2 (Nov. 2021).

PDF page 5

5

today, when the stakes are high, when action is needed expeditiously, and when doing so could materially affect members' business interests, is unrealistic. Accordingly, it is irresponsible to continue to allow this stakeholder body to serve as the final decision-maker on matters central to PJM's operation as an RTO.

B. PJM as the RTO Should be the Entity Held Accountable. The
Stakeholder Process Should be Advisory.

Stakeholders play an important role in PJM's governance by contributing their expertise and helping inform solutions across a range of interests. However, stakeholders should not have the ability to prevent PJM from fulfilling its responsibilities as the RTO, including submitting filings pursuant to Section 205 of the Federal Power Act (“Section 205” or “205”).

As the RTO PJM should be the entity accountable to FERC and the region for fulfilling RTO responsibilities, including making Section 205 filings related to its markets and regional planning processes. Currently, the stakeholder process inhibits PJM’s ability to make Section 205 filings at FERC to address issues or update its core functions, thereby limiting its ability to act and fulfill its role as an RTO.

All stakeholders and states have the ability to make filings pursuant to Section 206 of the Federal Power Act (“Section 206” or “206”) at the Commission or to protest any filing made by PJM, providing an appropriate balance. As the RTO, PJM should be the entity submitting proposals and defending them before

PDF page 6

6

the Commission. Those proposals should consider and incorporate feedback from PJM stakeholders through the stakeholder process. If consensus is not reached or stakeholders disagree with the decision of the RTO, they can take their arguments to FERC, either in response to a filing by PJM or by initiating a 206 filing. FERC is then able to make an informed decision based on the record and is the appropriate entity to do so.

Given this, PJM’s stakeholder process should become advisory. PJM should have the Section 205 filing rights over the Tariff and Operating Agreement. PJM should continue to maintain its stakeholder process, but the ultimate conclusion of it would be advisory.

Transitioning to an advisory stakeholder process would also enable PJM to move more expeditiously to address emerging reliability, market, and planning needs when necessary. While there are many options for how this could work, PJM would be able to define a process that meets a moment, allowing it to move quickly to address emergent issues without being hamstrung by a lengthy stakeholder process, or vulnerable to rejection by stakeholders based on a procedural issue.

C. States Should Have an Increased Role in the PJM Stakeholder Process

State input is critical to the success of the RTO; therefore Duquesne Light supports providing states a larger role at PJM, including a seat on the Nominating Committee and the ability to cast advisory votes.

PDF page 7

7

Allowing one collective seat for all PJM state entities on the Nominating Committee is appropriate. The Nominating Committee consists of “one representative elected annually from each sector of the Members Committee established under Operating Agreement, section 8.1 and three voting Board Members (provided that one such Board Member shall serve only as a non-voting member of the Nominating Committee).”6 Each sector has a single representative and only the PJM Board has an additional voting representative. Therefore, it is appropriate for the states to have a single representative collectively representing all state interests. The PJM Board would continue to be the only entity with more than one voting representative on the committee, which is appropriate because it bears ultimate responsibility and accountability for PJM's performance and governance and is therefore best positioned to identify the skills, expertise, and experience needed in future Board candidates.

States having the ability to cast advisory votes in the stakeholder process is also appropriate. In line with the recommendation above that the stakeholder process should become advisory; state votes should also be advisory and should be considered by the PJM Board to inform their decision making. States’ input is critical and should be allowed to inform the PJM Board for its ultimate decisions. Duquesne Light encourages an approach to increase state participation in PJM in a coordinated fashion, including using the existing Organization of PJM

6 PJM Interconnection, L.L.C., Operating Agreement, Section 7.1

PDF page 8

8

States, Inc (“OPSI”) as the body to represent all state entities at PJM. OPSI could be expanded and structured to have separate internal groups, including individual groups for governors’ offices, legislators, utility commissions, etc. Through OPSI, meetings could be facilitated for each group individually and/or cross-functionally. The groups would all roll up under OPSI and it would allow a single organization to house and represent the views of the PJM states. PJM’s 13 state jurisdictions with disparate views is one of its biggest challenges. This should be considered as the structure for increased state participation is developed. The more states are able to speak with a single voice, the more impactful they will be and the more valuable their input for PJM’s consideration.

D. Responses to the Commission’s Polling Questions

1. PJM Board Independence

Questions/Comments
Yes No
1) Should Board members’ terms be extended to five or more years? X

Comments: PJM Board members should serve five-year terms and be eligible for one additional term, ensuring continuity while limiting service to a maximum of 10 years. Individual terms longer than 5 years are too long. It could create a barrier to finding new board members who may not be willing to commit to almost a decade. Duquesne agrees Board members need more certainty and terms longer than 3 years are needed for Board members to maintain their independence. Five year terms with eligibility for one extension achieves an appropriate balance

2) Should there be a maximum number of years that a Board member
may serve (e.g., 10 years)?
X

PDF page 9

9

Comments: PJM Board members should be limited to a maximum of 10 years. Ten years is the appropriate balance to meet the need for PJM to have experienced and knowledgeable board members and not provide unduly burdensome years. The average board member serves a term of 9 years, so a 10- year maximum is appropriate to allow board members to develop deep industry and organizational expertise while maintaining a healthy balance between continuity and board refreshment.7

3) Should the Board member qualification rules be revised to provide a preference for some Board members that reside in the PJM region? X

Comments: A preference, but not a requirement, for a Board member to reside in PJM should be included. A potential Board member should not be disqualified for not residing in PJM. PJM board members require a significant amount of knowledge about the PJM region and are expected to attend a variety of in- person events. Therefore, residing in PJM could be a benefit and should be considered as one of the many factors the Nominating Committee reviews for potential Board members.

4) Should the conflict-of-interest rules be revised to reduce the cooling off period for Board members from two years to one year?

X

Comments: A reduction of the cooling off period from two years to one year is appropriate to widen the candidate pool and identify qualified candidates to serve on the PJM Board.

5) Should restrictions on Board communications be relaxed to enable more communication between the Board and stakeholders?

X

Comments: Board communications could be relaxed to allow Board members to get more feedback from stakeholders. This relaxation should be balanced with additional transparency to ensure all members are receiving the same opportunities with the PJM Board.

6) In order to increase transparency, should Board votes be made public or the Board be required to explain its reasoning?

X

Comments: The PJM Board should provide reasoning behind votes, especially those directing a 205 filing at the Commission. The PJM Board typically provides this reasoning and should continue to do so. If the PJM Board’s filing

7 Board Tenure Statistics: Average, Distribution, and What It Means for Open Seats (FindABoardSeat Research, May 28, 2026).

PDF page 10

10

rights are expanded or the stakeholder process becomes advisory, then the requirement should become mandatory to ensure transparency and balance PJM’s broader authority.

7) In order to increase transparency, should some Board meetings be open or available to the public?

X

Comments: The PJM Board should continue to engage in the stakeholder process and be transparent about its decisions but should continue to be able to conduct their business privately to maintain its independence.

8) Should PJM’s governing documents be revised to explicitly state that the responsibility of PJM and its Board is to serve the public interest? X

Comments: The safety, reliability and security of the bulk electric system and the functioning of wholesale power markets is at the core of the nation's economic prosperity, national security, and public welfare and it is appropriate for PJM, to consider the public interest in its decisions to manage and operate these critical systems and markets. If this is implemented, Duquesne recommends public interest be well defined to manage the varied definitions of public interest throughout the 13 jurisdictions PJM serves and is rooted in authority from FERC and the Federal Power Act.

9) Should state representatives have at least one voting member on the Nominating Committee?

X

Comments: All PJM states and their respective representatives, including utility commissions, governors' offices, and legislatures, should collectively hold one seat and one vote on the Nominating Committee. Each sector has one member and one vote, and it is appropriate for the states to have an equal role in the Nominating Committee.

10) Should PJM adopt public performance metrics and tie management compensation to their achievement?

X

Comments: PJM should remain accountable to its stakeholders and continue to provide transparency regarding its performance, but management compensation should not be tied to public performance metrics.

PDF page 11

11

2. Section 205 Filing Rights

Questions/Comments
Yes No
11) Should the stakeholder process be advisory, i.e., stakeholder votes only inform the Board?

X

Comments: Yes, PJM as the RTO should be the entity accountable for PJM executing and delivering on its mission as the RTO. Therefore, PJM should have the authority and filing rights to execute and implement changes necessary to fulfill its responsibilities and ensure the reliable operation of the bulk electric system and wholesale electricity markets.

12) Should PJM have section 205 filing rights over the energy market and ancillary services unencumbered by the requirement to obtain

approval of two-thirds of the Members Committee?
X

Comments: PJM needs to have the ability to make 205 filings to improve or modify all aspects it oversees, including the energy markets and ancillary services. Running these markets is one of PJM’s core duties and it should not be barred from seeking approval for improvements or changes to those markets it sees fit under a section 205 filing. Any 205 filing will have a record that all stakeholders are able to participate in and that the Commission to consider.

13) Should PJM have section 205 filing rights over Regional
Transmission Expansion Planning (RTEP) unencumbered by the
requirement to obtain approval of two-thirds of the Members
Committee?
X

Comments: PJM needs to have the ability to make 205 filings to improve or modify all aspects it oversees, including the RTEP. Conducting the RTEP is one of PJM’s core duties and stakeholders should not be able to bar PJM from seeking approval from the Commission for improvements or other changes it sees fit under a section 205 filing. Any 205 filing will have a record that all stakeholders are able to participate in and that the Commission to consider.

14) Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal?

X

Comments:
Resource Adequacy: PJM as the RTO should maintain all the 205 rights for the Tariff, OA and all of its core responsibilities. States should provide input that

PDF page 12

12

Questions/Comments
Yes No
should be considered and are able to participate in any 205 proceeding initiated by PJM.

Transmission Cost Allocation: PJM does not have the 205 filing rights for transmission cost allocation. Therefore, PJM would not make such a filing and there would be no need for OPSI to have “jump ball” filing rights.

15) Should the Members Committee have “jump ball” filing rights over the portions of the tariff where PJM has 205 filing rights when a supermajority of stakeholders approves an alternative proposal?

X

Comments: PJM as the RTO should be the entity with the 205 filing rights. Stakeholders should provide input and are able to participate in any 205 proceeding or to make section 206 filings to address any concerns they may have with a PJM proposal.

3. Stakeholder Process

Questions/Comments
Yes No
16) Should the approval threshold in the Members Committee be lowered from two-thirds sector-weighted voting?

X

Comments: The two-thirds sector-weighted vote threshold remains appropriate and should not be lowered. The threshold requires agreement from 3.33 of the 5 sectors. Lowering it to allow less than three sectors to agree would no longer represent a consensus solution.

17) Should the voting rules barring affiliate votes, which apply to senior standing committees, also apply to lower-level committees?

X

Comments: The current voting paradigm with affiliate voting in lower committees is appropriate. The committee structure was set up to allow technical experts from the member companies with vested interest in PJM to express that expertise to be considered by the senior standing committee and remains appropriate.

4. State Participation

PDF page 13

13

Questions/Comments
Yes No
18) In addition to OPSI, should there be a second state representative group consisting of governors’ representatives and/or state legislators’ representatives?

X

Comments: Ideally the different state entities are able to coordinate and work through an expanded Organization of PJM States, Inc. (OPSI). Duquesne Light is supportive of OPSI being expanded. OPSI could be structured in a variety of ways for the governors, legislators and utility commission representatives to work separately or as collectively as they deem appropriate. Duquesne is supportive of the states engaging more fully in the PJM process and looks forward to that engagement and dialogue.

19) Should state representatives have a formal voting role in the stakeholder process (limited to certain topics, such as resource adequacy and regional transmission cost allocation) in addition to the consumer advocate votes?

X

Comments: Duquesne supports moving to an advisory stakeholder process and under that paradigm a state vote, one per state, would be an important informational item for the PJM Board. If the outcome is not to move to an advisory process, then the states should be afforded a vote, one per state, that would be informational to the PJM Board and would not be counted in the sector- weighted vote outcome.

20) Should PJM be required to consult with OPSI prior to making a section 205 filing related to resource adequacy and transmission cost allocation?

X

Comments:
Resource Adequacy: PJM and the states have complementary authority around PJM markets. PJM runs the markets that incentivize resource entry and exit, but PJM has no authority to require a resource to enter or exit the market. The states have the authority to direct a resource to be built or to retire but have no authority over the operation of PJM markets. Given these complementary authorities it is important for PJM and the states to be in regular communication. A consultation before making any 205 filing on resource adequacy is appropriate, but ideally states have been engaged in the development of any proposal through the stakeholder process.

Transmission Cost Allocation: PJM does not have the 205 filing rights for transmission cost allocation. Therefore, PJM would not make such a filing and

PDF page 14

14

Questions/Comments
Yes No
there would be no need for a consultation.

IV. CONCLUSION
While the structure and governance of PJM met the needs of the time of its creation, the complexity of issues faced, expanded membership, and need for expeditious action requires revision to its stakeholder and governance structure. Duquesne Light appreciates the opportunity to provide input and respectfully submits these comments for the Commission’s consideration.

Respectfully Submitted,
/s/David Fisfis
David Fisfis
Special Council
Duquesne Light Company
Nova Place
100 South Commons Suite 118
Mail Drop OGC-L1
Pittsburgh, PA 15212
Telephone: (412) 393-6924
Email: dfisfis@duqlight.com

PDF page 15

15

/s/ C. James Davis

/s/Christin Domian
C. James Davis

Christin Domian
Director, Rates, Energy Procurement and

Sr Manager, FERC/RTO Affairs
Federal/RTO Affairs

Duquesne Light Company
Duquesne Light Company

Nova Place
Nova Place

100 South Commons, Suite 118
100 South Commons, Suite 118

Mail Drop OGC-L1
Mail Drop OGC-L1

Pittsburgh, PA 15212
Pittsburgh, PA 15212

Telephone: (412) 393-6316
Telephone: (412) 393-6402

Email: cdomian@duqlight.com
Email: jdavis4@duqlight.com

Dated: August 21, 2026