AD26-7-000 · 2026-08-21 · Duquesne Light Company

Post-Conference Comments of Duquesne Light Company re PJM Governance and Stakeholder Reforms

Text extracted from the eLibrary original (SHA-256 42be38a3bd092fac…). Download the original from the official source.

Contents · 9 sections
  1. I. INTRODUCTION p. 1
  2. II. Duquesne Light Company’s Interest in the Proceeding p. 1
  3. III. COMMENTS p. 2
  4. A. PJM Governance Reform is Needed p. 2
  5. B. PJM as the RTO Should be the Entity Held Accountable. The p. 5
  6. C. States Should Have an Increased Role in the PJM Stakeholder Process p. 6
  7. D. Responses to the Commission’s Polling Questions p. 8
  8. IV. CONCLUSION p. 14
  9. C. James Davis p. 15

Read topic-matched comments in AD26-7

Topics in the text: Cost allocation · Reliability and curtailment · Registry access

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

1 UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Governance and Stakeholder Reforms ) Docket No.
Read this passage

I. INTRODUCTION

printed heading

INTRODUCTION Duquesne Light Company (“Duquesne Light”) respectfully submits the following comments in response to the Notice Requesting Post-Conference Comment issued by the Federal Energy Regulatory Commission (“FERC” or “Commission”) on July 30, 2026, following the July 23, 2026 Technical…
Read this passage

II. Duquesne Light Company’s Interest in the Proceeding

printed heading

Duquesne Light Company’s Interest in the Proceeding Duquesne Light is a FERC-jurisdictional Transmission and Distribution only utility that serves over 600,000 customers and operates in parts of Allegheny and Beaver Counties, located in Western Pennsylvania, including the city of Pittsburgh.
Read this passage

III. COMMENTS

printed heading

III.
Read this passage

A. PJM Governance Reform is Needed

printed heading

Any proposal must go through a first read, before an 2 PJM Interconnection, L.L.C., PJM Summer 2006 Outlook at 2 (June 2006). 3 endorsement vote can be held, and this occurs at both the standing and senior standing committees.
Read this passage

B. PJM as the RTO Should be the Entity Held Accountable. The

printed heading

PJM as the RTO Should be the Entity Held Accountable.
Read this passage

C. States Should Have an Increased Role in the PJM Stakeholder Process

printed heading

The Nominating Committee consists of “one representative elected annually from each sector of the Members Committee established under Operating Agreement, section 8.1 and three voting Board Members (provided that one such Board Member shall serve only as a non-voting member of the Nominating…
Read this passage

D. Responses to the Commission’s Polling Questions

printed heading · Topic match: Cost allocation

Transmission Cost Allocation: PJM does not have the 205 filing rights for transmission cost allocation.
Read this passage Filed comments: Cost allocation

IV. CONCLUSION

printed heading

CONCLUSION While the structure and governance of PJM met the needs of the time of its creation, the complexity of issues faced, expanded membership, and need for expeditious action requires revision to its stakeholder and governance structure.
Read this passage

C. James Davis

printed heading

James Davis Christin Domian Director, Rates, Energy Procurement and Sr Manager, FERC/RTO Affairs Federal/RTO Affairs Duquesne Light Company Duquesne Light Company Nova Place Nova Place 100 South Commons, Suite 118 100 South Commons, Suite 118 Mail Drop OGC-L1 Mail Drop OGC-L1 Pittsburgh, PA 15212…