AD26-7-000 · 2026-08-21 · Citizens Utility Board of Illinois

Post-Conference Comments of the Delaware Division of the Public Advocate, et al. re PJM Governance and Stakeholder Reforms

PDF page 1

1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Governance and Stakeholder Reforms )

Docket No. AD26-7-000

POST-CONFERENCE COMMENTS OF THE DELAWARE DIVISION OF THE
PUBLIC ADVOCATE, ILLINOIS CITIZENS UTILITY BOARD, MARYLAND OFFICE
OF PEOPLE’S COUNSEL, AND VIRGINIA OFFICE OF THE ATTORNEY GENERAL
DIVISION OF CONSUMER COUNSEL

The Commission’s consideration of PJM governance reform is timely and
welcome. The Commission is responsible for ensuring just and reasonable rates. However, PJM’s structure is a major impediment to achieving those rates. PJM’s voting membership is overwhelmingly market participants who have an interest in higher revenues. The 67 million customers–who pay the bills and use the electricity–are PJM’s raison d'être, but are woefully underrepresented in the stakeholder process. These 67 million customers in PJM’s footprint are represented solely by 14 consumer advocate votes – one for each jurisdiction. These 14 votes translate to 1.3% of potential voters at the Standing Committee and Senior Task Force level, where the details of rules and plans are designed. At the Senior Standing Committee levels, the Markets and Reliability Committee (MRC) and Members Committee (MC), the 14 consumer advocates make up approximately 7% of the vote.1 The lack of ratepayer representation in the PJM stakeholder process has led to an untenable status quo, where moneyed interests design and vote on the rules that benefit them, without regard to public cost.

1 Consumer Advocates of the PJM States (CAPS) Presentation, PJM Annual Meeting, May 13, 2026. https://www.pjm.com/-/media/DotCom/committees-groups/user-groups/pieoug/2026/20260513/20260513-item-03-- -consumer-advocates-of-the-pjm-states-presentation---updated.pdf

PDF page 2

2

Any governance reforms proposed at PJM should strengthen not only the state voice, but also the voice of the 67 million customers that PJM serves, who are represented solely by statutory consumer advocates. Our consumer advocate offices have longstanding technical expertise at PJM and are members of the End-Use Customer sector. Our offices have deeply engaged at PJM long before the RTO became front page news, and we will continue to do so after PJM fades back to the obscurity of the public utility world. Consumer advocates have perspectives that are unique and distinct from other state entities. We are independent bodies charged with protecting ratepayers from unreasonable costs on their utility bills. We represent ratepayers before our state commissions, who consider issues beyond cost to ratepayers. At times we agree with our state commissions and at times we disagree. Similarly, state policy entities, like governors or legislators, balance a number of competing priorities, such as economic development and environmental protection, of which ratepayer affordability is simply one. Unlike state Commissions or other policymakers, we are in the position of singularly advocating for positive outcomes for consumers in PJM. Our positions do not originate from a “balance” between the investor-owned interests and PJM ratepayers. Governance reforms must thus have an eye to both state and ratepayer representation. At minimum, this must include revising PJM’s mission and Operating Agreement to serve the public interest by balancing affordability alongside reliability.2

The following recommendations for governance reform at PJM seek to incorporate a focus on affordability, strengthen the role of the states, and improve PJM’s decision-

2 On August 19, 2026 the Affordability and Reliability for Residential Customers (ARRC) User Group presented proposed modifications to O.A. Section 7.7 to reflect the principle of affordability. https://www.pjm.com/- /media/DotCom/committees-groups/committees/mc/2026/20260819/20260819-item-01---arrc-user-group- affordability-consideration---presentation.pdf

PDF page 3

3

making process. One of the challenges of reforming governance at PJM is that many
changes require a supportive vote of PJM Members, who are overwhelmingly the corporate
entities who benefit from the status quo. In devising solutions, FERC must also consider
how to implement them given the self-interest of PJM's controlling Members.

I. EXPANDED 205 RIGHTS FOR THE PJM BOARD SHOULD ONLY BE PURSUED
ALONGSIDE REVISIONS TO THE GOVERNING DOCUMENTS AND JUMP BALL FILING
RIGHTS FOR THE STATES AND MEMBERS COMMITTEE … 4
A. The Board has not used its existing filing rights effectively … 4
B. The need to reflect affordability and the public interest in PJM’s mission … 5
C. States must have 205 jump ball filing rights … 6
II. THE “CREDIBILITY TRAP” IS RESOLVABLE WITH MEANINGFUL COST OVERSIGHT

8
A. Require cost impact information and ongoing cost impact dialogue … 8
B. Appoint an Independent Transmission Monitor … 9
III. IMPROVEMENTS TO PJM’S BOARD ARE NECESSARY TO ACHIEVE POSITIVE
GOVERNANCE REFORM … 10
A. Expand the Nominating Committee to include state representatives … 10
B. Expand the Board expertise requirements to include state and ratepayer experience … 11
C. Open Board meetings and publish Board votes … 11
IV. CONSENSUS-BUILDING IN THE STAKEHOLDER PROCESS CAN BE IMPROVED BY
MODIFICATIONS TO VOTING AND TRANSPARENCY RULES … 12
A. Expand sector-weighted voting to all Standing Committees and Senior Task Forces … 12
B. Require transparency of individual firm votes across all committee levels … 13
C. Record and publicly share stakeholder meetings … 14
V. CONCLUSION … 15 Appendix … 17

PDF page 4

4

I. EXPANDED 205 RIGHTS FOR THE PJM BOARD SHOULD ONLY BE
PURSUED ALONGSIDE REVISIONS TO THE GOVERNING DOCUMENTS AND JUMP
BALL FILING RIGHTS FOR THE STATES AND MEMBERS COMMITTEE
Much of the Technical Conference focused on whether the PJM Board should be granted expanded 205 rights. The PJM Board must not be granted expanded 205 rights unless and until the LLC’s mission and governing documents are reformed to account for affordability and the public interest, and the states and Members Committee have 205 jump ball filing rights on all topics. Regardless of whether 205 rights get expanded or not, these checks and balances on PJM would support the principles of accountability, transparency, and Board independence.

A. The Board has not used its existing filing rights effectively
Any proposed changes to PJM’s governance should be evaluated on their ability to solve the current problems that PJM is facing. This includes the question of whether or not PJM should have expanded 205 rights. If the Board is granted expanded 205 rights and all else remains equal, the regional situation will not improve.

The Board has 205 rights for the capacity market, which has been in a state of disarray for years. Instead of acting decisively after the first Critical Issues Fast Path (CIFP) on Large Load Adjustments concluded, the PJM Board started yet another CIFP. While it is critical to get stakeholder feedback, the Board has not used the existing 205 rights to demonstrate leadership. In contrast, the PJM Board does utilize its existing 206 rights when it deems an issue important, so the lack of 205 rights is not necessarily an impediment. When the Board disagreed with the vast majority of stakeholders on proposed changes to

PDF page 5

5

the Consolidated Transmission Owners Agreement, it overrode Member objections3 and filed a 206 at FERC. In short, there is seemingly no rhyme or reason to when the Board finds stakeholder opposition to be meaningful or not: the Board has 205 rights for the capacity market, yet has pursued a multitude of CIFPs; yet being limited to 206 rights in other areas has not prevented the PJM Board from taking action.

Nevertheless, it is true that the PJM Board is fairly unique among RTOs in lacking 205 rights over transmission planning and energy markets, and the Commission may choose to resolve that discrepancy. Should the Commission grant the PJM Board expanded 205 filing rights, it must only do so once the PJM mission and governing documents are revised to include affordability and the public interest, and the states and Members Committee have jump ball filing rights. Both reforms are essential independently, but together, they would help to ensure that the Board’s enhanced power leads to positive outcomes.

B. The need to reflect affordability and the public interest in PJM’s mission As the grid operator managing electricity for 14 jurisdictions and 67 million customers, PJM’s success or failure is intertwined with the public interest. Electricity is a public good necessary to modern life. Reliable electricity is critical and it must also be affordable. The PJM mission statement and governing documents should be revised to reflect that the Board must act in the public interest by balancing reliability and affordability. The Federal Power Act requires that rates be just and reasonable.4 To do so,

3 Leith-Yessian, Devin. “Members Vote against Granting PJM Filing Rights over Planning.” RTO Insider, 7 May 2024, www.rtoinsider.com/78031-members-committee-against-granting-pjm-filing-rights/.

416 U.S.C. §§ 824–824w

PDF page 6

6

the Commission must ensure that RTOs provide reliability at least cost. Several RTOs recognize that serving the public interest is at the core of their functions: CAISO is a nonprofit public benefit corporation and MISO is a 501(c)(4) or social welfare organization.

However, the principle of least cost is not reflected in PJM’s mission or governing documents. Not having any mention of affordability or the public interest contributes to the PJM Board being laser-focused on reliability, and the approach in PJM can be better described as “reliability at any cost.” Without a clear responsibility for affordability, the Board will continue to lack accountability to the 67 million customers it serves. The absence of affordability from PJM’s mission and governing documents has more than a symbolic impact: the vast majority of proposals are unaccompanied by cost impact analysis, and even where costs are tracked, PJM’s reporting is inconsistent and riddled with errors.5 There is no way to confirm whether PJM is achieving just and reasonable rates without cost impact analysis and data.

C. States must have 205 jump ball filing rights
The status quo of the states having merely an informal advisory role to PJM through the Organization of the PJM States (OPSI) is not working. States have the least formalized input into PJM than any of the other multistate RTOs. This creates difficulty when state laws rely on PJM’s cooperation for implementation, or when PJM makes rules or undertakes planning processes that undercut state goals. States have responsibilities and

5 Consumer Advocates of the PJM States (CAPS) Presentation, PJM Annual Meeting, May 13, 2026. https://www.pjm.com/-/media/DotCom/committees-groups/user-groups/pieoug/2026/20260513/20260513-item-03-- -consumer-advocates-of-the-pjm-states-presentation---updated.pdf

PDF page 7

7

jurisdictional rights that PJM does not possess, and vice versa. It is common sense that a functional RTO will have a collaborative relationship with its participatory states. The minimal advisory role of OPSI to PJM is not fit for that purpose; more substantial and more formalized representation for state entities at PJM is overdue. In many multi-state RTOs, Regional State Committees have 205 “jump ball” filing rights. PJM states should have this same capability across all issues—not only resource adequacy, which is jurisdictionally a state responsibility, but also transmission planning, which Order 1920 recognizes requires a robust state role. Placing states on an even footing with the Members Committee, which is dominated by market interests, requires extending the states’ jump ball filing rights over the energy and ancillary services markets as well. Granting states 205 jump ball filing rights will also provide an incentive for the diverse states of PJM to come to consensus on key issues.6

Improvements to PJM coordination with the states go beyond the allocation of 205 rights. Ideally, states would feel confident in their relationship with PJM leadership so that those rights need never be exercised. Prior to making major filings at FERC, the PJM Board should consult with OPSI. This could entail the Board sharing draft filings with OPSI for feedback prior to formal filing at FERC. Allowing OPSI to review filings in advance would head off key concerns by the states and could lead to less litigation. For the purposes of formal OPSI consultation, major filings could be filings resulting in a certain threshold of cost impact, or at minimum, any policy decided through a CIFP.

6 Comments by panelist at 19:32, Dan Scripps, Michigan Public Service Commission, Summit on the State of PJM Interconnection, RTO Governance: Lessons Learned from Other Regions, PJM Governors Meeting, September 2025. https://www.dropbox.com/scl/fi/1pj9mceyan3tvo53ymfv3/9.-RTO-Governance-Lessons-Learned-From- Other-Regions.MP4?rlkey=2d5b8pmndl9e0g1lt2w9ujf7p&st=d6gibwh1&e=1&dl=0

PDF page 8

8

II. THE “CREDIBILITY TRAP”7 IS RESOLVABLE WITH MEANINGFUL COST
OVERSIGHT

A. Require cost impact information and ongoing cost impact dialogue
The lack of cost impact analysis at PJM should be considered unacceptable. PJM- managed markets and planning account for more than half of the cost of residential ratepayer bills across the states in the region.8 There is no way to evaluate whether PJM has achieved just and reasonable rates without cost impact information. As consumer advocates, we work at both the RTO and the state level, representing ratepayers in front of our commissions. The difference between the quality of cost information we can access at the state level versus at PJM is staggering. At PJM, we rarely receive any cost impact analysis prior to voting on proposals. A proposal that PJM or a Member advances may promote reliability, but it is also possible that there are alternatives that could achieve the same reliability results at lower cost; there is no way to know, because currently there is no standardized method for evaluating proposals for cost. It should be standard practice for PJM to evaluate the cost impact of any proposal as part of the First Read at the MRC/MC. Such analysis may not provide perfect information, but just as PJM is expected to evaluate proposals for reliability, they should also do so for cost. This way, stakeholders and states

7 Powering Reliability Through Market Design: Addressing Rising Demand and Constrained Supply, and Stimulating Investment To Support Durable Reliability, PJM Interconnection, 2026. See “credibility trap” discussion on p.5. https://www.pjm.com/-/media/DotCom/library/reports-notices/special-reports/2026/20260506-powering- reliability-through-market-design.pdf
8 Consumer Advocates of the PJM States (CAPS) Presentation, PJM Annual Meeting, May 13, 2026. https://www.pjm.com/-/media/DotCom/committees-groups/user-groups/pieoug/2026/20260513/20260513-item-03-- -consumer-advocates-of-the-pjm-states-presentation---updated.pdf

PDF page 9

9

would be more informed as they consider the trade-offs between proposals. Cost impact analyses are needed to determine whether PJM rates are just and reasonable. A regular quarterly meeting between consumer advocates, state regulators, the Independent Market Monitor, and the PJM Board could facilitate better understanding of the PJM Board’s responsibility for wholesale costs. The PJM Board and staff would benefit from learning how wholesale costs translate to retail bills, and a regular meeting would facilitate dialogue and feedback on how the PJM Board is achieving reliability at least cost.

B. Appoint an Independent Transmission Monitor
PJM’s Independent Market Monitor plays an invaluable role, not only mitigating market power, but also often providing cost information that PJM does not. However, there is no such equivalent accountability for transmission costs. Even when reported, transmission costs are often incomplete or inaccurate.9 Even worse, many transmission projects, namely supplemental projects, receive no cost oversight at all, as detailed by the Ohio Consumers Counsel.10 The result is that Transmission Owners have an incentive to overbuild less efficient transmission projects that escape oversight, while underbuilding more thoroughly scrutinized, but also likely more regionally beneficial, projects. An Independent Transmission Monitor would provide impartial and independent cost analysis, increasing the transparency and accountability of PJM’s transmission planning. By improving transmission oversight, planning would be improved, costs would be better

9 Consumer Advocates of the PJM States (CAPS) Presentation, PJM Annual Meeting, May 13, 2026. https://www.pjm.com/-/media/DotCom/committees-groups/user-groups/pieoug/2026/20260513/20260513-item-03-- -consumer-advocates-of-the-pjm-states-presentation---updated.pdf
10 The Office of the Ohio Consumers’ Counsel v. PJM Interconnection, L.L.C., et al., FERC Docket No. EL23-105

PDF page 10

10

justified and potentially reduced, and individual transmission lines could prove to be less contentious.

III. IMPROVEMENTS TO PJM’S BOARD ARE NECESSARY TO ACHIEVE
POSITIVE GOVERNANCE REFORM
The lack of a public interest mandate has allowed the PJM Board to largely ignore the cost impacts of PJM decisions on the 67 million customers it serves. In addition to reforming PJM’s mission to include affordability and the public interest, there are several ways the PJM Board can be more effective.

A. Expand the Nominating Committee to include state representatives
We agree with Jacob Finkel’s suggestion, on behalf of the Governors Collaborative, to expand the Nominating Committee to include 3 designees of the states.11 A potential model would be a seat for an OPSI designee, a seat for an appointee of a separate governors/legislators organization, and a statutory consumer advocate. Consumer advocates, as Members of the End-Use Customer sector, alternate with representatives of industrial energy users on the Nominating Committee, but do not have a permanent seat. As the only voice of the 67 million customers, there should always be meaningful consumer advocate input when Board members are selected.

11 Pre-Technical Conference Statement Jacob Finkel, Office of Governor Josh Shapiro, Deputy Secretary of Policy, FERC Docket No. AD26-7-000.

PDF page 11

11

B. Expand the Board expertise requirements to include state and ratepayer experience

The PJM Board has a number of expertise requirements. For example, there must always be a Board member with transmission planning experience. Other areas of expertise include cybersecurity, law, and accounting. The Board expertise requirements should be updated to include 1) a former state regulator and 2) an individual with experience representing ratepayer interests. These expertise requirements are necessary in part to facilitate understanding of how wholesale costs are translated onto retail bills. Having a former state regulator on the PJM Board will also support a better understanding among Board members of state processes and jurisdiction.

C. Open Board meetings and publish Board votes
Board meetings are currently conducted in private. Recorded minutes are minimal. The unfortunate result is that Members, and the public, have no way to evaluate individual Board performance, which can lead to unfavorable election votes when the Board makes decisions contrary to Member perspectives. The lack of transparency also prevents Members and the public from knowing the depth of the Board’s knowledge. It is difficult to understand Board perspectives when their deliberations are shrouded in secrecy. Making Board meetings and individual votes public will greatly enhance accountability for, and understanding of, the Board.

Some commentators have suggested that ex parte rules be revised to allow private contact between PJM Members and individual Board members. We disagree. Ex parte

PDF page 12

12

rules are important for maintaining Board independence. Making Board meetings transparent will foster accountability while maintaining independence.

IV. CONSENSUS-BUILDING IN THE STAKEHOLDER PROCESS CAN BE
IMPROVED BY MODIFICATIONS TO VOTING AND TRANSPARENCY RULES

A. Expand sector-weighted voting to all Standing Committees and Senior Task Forces

Sector-weighted voting should be expanded throughout all PJM committees. Under current affiliate voting practices, proposals in Standing Committees and Senior Task Forces are biased towards PJM members representing supply interests. For example, West Deptford Energy (also known as LS Power) has 25 affiliate votes at the Standing Committee and Senior Task Force level. This is more votes than every consumer advocate combined, since consumer advocate votes are capped at one for each of the 14 jurisdictions.12 The barrier to consensus emerges once proposals are advanced to the Senior Standing Committees of the MRC and MC. Because supply-side interests can advance a proposal out of the standing committees without load support, proposals at the MRC or MC may then face a higher risk of rejection by load interests. There is a difference between being able to veto a solution and shape a solution. PJM’s current structure creates a dynamic where load interests are often painted as naysayers over-exercising veto power, but any naysaying might be reduced if load interests had more meaningful input at the

12 Consumer Advocates of the PJM States (CAPS) Presentation, PJM Annual Meeting, May 13, 2026. https://www.pjm.com/-/media/DotCom/committees-groups/user-groups/pieoug/2026/20260513/20260513-item-03-- -consumer-advocates-of-the-pjm-states-presentation---updated.pdf

PDF page 13

13

Standing Committee level, where proposals are negotiated and designed in detail. Applying sector-weighted voting to the standing committees will allow affiliates to continue voting, but would prevent their ability to dominate the outcomes. Then, proposals that are advanced to the MRC and MC are more likely to be balanced and pass. Even supply-side commentators have noted that affiliate voting in the standing committees stifles consensus and recommended applying sector-weighted voting across all levels.13 We concur.

B. Require transparency of individual firm votes across all committee levels Votes are only reported in full at the MC. At the MRC, vote results are reported by sector, but not broken down by individual firm. At the Standing Committee and Senior Task Force level, votes are only reported in aggregate, with the number and percentage of yeas, nays, and abstentions. Not only does this limit transparency — which should be a core value of any entity making decisions affecting rates and reliability – but it also scuppers consensus building.

For example, a recent vote at the Deactivation Enhancements Senior Task Force (DESTF) resulted in no proposal reaching the 50% threshold to advance. However, PJM’s proposal was close to advancing – 44% of stakeholders preferred it over the status quo.14 In any legislative process, knowing who voted how would then lead to conversations about why they took the position they did, what their concerns were, and what changes might result in getting a proposal across the finish line. Knowing full vote results facilitates

13 Comments by panelist at 4:22, J. Arnold Quinn, Vistra Corporation, Panel 2, Group 1, FERC Technical Summit on PJM Stakeholder Governance, July 23, 2026. https://www.ferc.gov/news-events/events/PJM-Governance- Stakeholder-Reforms.
14 Voting Results - Scope Area 4 /5, Deactivation Enhancements Senior Task Force, June 17, 2026. https://www.pjm.com/-/media/DotCom/committees-groups/task-forces/destf/2026/20260617/20260617-item-04--- voting-results---scope-area-4-5.pdf

PDF page 14

14

further conversation, which facilitates consensus. However, because there is no such vote transparency at all levels of the PJM stakeholder process, and individual firms were not forthcoming with their concerns, the DESTF process could not produce a result. Requiring voting transparency will also facilitate fairness among PJM Members. In Delaware,15 Maryland,16 New Jersey,17 and Virginia,18 utilities are required to report the votes they take at PJM. Most state-appointed consumer advocates are subject to public record laws (and in Delaware, they are subject to the same PJM voting transparency law as the utilities). The result is a patchwork of disclosure that largely impacts two types of Members. Full and comprehensive voting disclosure by PJM would eliminate this disparate treatment.

PJM Members are not acting as individual voters—they are deciding on policies that impact the reliability and affordability of electricity for 67 million customers. Just as elected officials must vote in public, PJM Members should as well.

C. Record and publicly share stakeholder meetings
There are more PJM meetings than days in the year, and many meetings run as long as 8 hours. No human can possibly attend them all. Even for those who do attend as many meetings as feasible, the subject matter is highly technical and can be difficult to fully digest in the moment. The transparency of the PJM process and quality of the technical solutions will be greatly enhanced by recording meetings and posting those recordings, with transcripts, publicly.

15 10 Del. C. sec. 1021.
16 Md. Code Ann., Pub. Util. (“PUA”) §7-108 (2028).
17 NJ. Code P.L. 2025, c.129 (A5463 1R)
18 Va. Code Ann. § 56-579.1 (2026).

PDF page 15

15

V. CONCLUSION
PJM governance is broken and leads to unjust and unreasonable outcomes. We recommend the following changes:

1) Reflect affordability and the public interest in PJM’s mission and governing documents

2) Grant OPSI 205 jump ball filing rights
3) Formalize Board consultation with OPSI
4) Require cost impact information
5) Appoint an Independent Transmission Monitor
6) Expand the Nominating Committee to include state representatives
7) Expand the Board expertise requirements to include state and ratepayer experience

8) Open Board meetings and publish Board votes
9) Expand sector-weighted voting to all Standing Committees and Senior Task Forces

10) Require transparency of individual firm votes across all committee levels
11) Record and publicly share stakeholder meetings

PDF page 16

16

Respectfully submitted,
ILLINOIS CITIZENS UTILITY
BOARD
Sarah Moskowitz
Executive Director
/s/ Clara Summers
Clara Summers
Consumers for a Better Grid Campaign
Director
Illinois Citizens Utility Board
309 West Washington Street
Suite 800
Chicago, IL 60606
csummers@citizensutilityboard.org
DAVID S. LAPP
PEOPLE’S COUNSEL

/electronic signature/
William F. Fields
Deputy People’s Counsel
Philip L. Sussler
Senior Assistant People’s Counsel

Maryland Office of People’s
Counsel
6 Saint Paul Street, Suite 2102
Baltimore, Maryland 21202
(410)767-8150
William.fields@maryland.gov
Philip.sussler@maryland.gov

DELAWARE DIVISION OF THE
PUBLIC ADVOCATE
JAMESON TWEEDIE, PUBLIC
ADVOCATE

/s/ David T. Crumplar
David T. Crumplar (#5876)
Deputy Attorney General
820 N. French Street
Wilmington, DE 19801
Telephone: 302-577-8400
David.crumplar@delaware.gov
Counsel to the Delaware Division of
the Public Advocate
VIRGINIA OFFICE OF THE
ATTORNEY GENERAL
DIVISION OF CONSUMER
COUNSEL

/s/ John E. Farmer, Jr.
John E. Farmer, Jr.
Senior Assistant Attorney General
202 North Ninth Street
Richmond, Virginia 23219
(804) 786-2071
jfarmer@oag.state.va.us

DATED: August 20, 2026

PDF page 17

17

Appendix

Questions/Comments
Yes
No
1) Should Board members’ terms be extended to five or more years?
X

Comments: Due to the technical nature of the position, a term of up to 5 years may be appropriate. However, longer than 5 years is excessive and could lead to a loss of accountability. Every other RTO has a 3-year term.

2) Should there be a maximum number of years that a Board member may serve
(e.g., 10 years)?
X

Comments: If a Board member is effective, they should have the opportunity to be re-elected. Reasonable term lengths and more transparency of Board meetings, including making the voting records of individual Board members public, will provide the level of accountability necessary to evaluate whether a Board member deserves additional terms.

3) Should the Board member qualification rules be revised to provide a preference
for some Board members that reside in the PJM region?
X

Comments: It is useful for Board members to live in the region and have the perspective of being impacted by their own decisions. However, it is more important to have knowledgeable Board members and stringent conflict-of-interest rules. A preference for Board members living in the region is reasonable but should not supersede other qualifications.

4) Should the conflict-of-interest rules be revised to reduce the cooling off period for Board members from two years to one year?

X

Comments: Market power is endemic to the PJM region. Reducing the conflict-of-interest rules runs the risk of the further entrenchment of market power.

5) Should restrictions on Board communications be relaxed to enable more
communication between the Board and stakeholders?

X

Comments:  Ex parte rules are important for maintaining Board independence. Making Board meetings transparent will foster accountability while maintaining independence.

6) In order to increase transparency, should Board votes be made public or the Board be required to explain its reasoning?

X

Comments: It is difficult to understand Board perspectives when their
deliberations are shrouded in secrecy. Making Board meetings and individual
votes public will greatly enhance accountability for, and understanding of, the
Board.

PDF page 18

18

Questions/Comments
Yes
No
7) In order to increase transparency, should some Board meetings be open or
available to the public?
X

Comments: It is difficult to understand Board perspectives when their deliberations are shrouded in secrecy. Making Board meetings and individual votes public will greatly enhance accountability for, and understanding of, the Board.

8) Should PJM’s governing documents be revised to explicitly state that the
responsibility of PJM and its Board is to serve the public interest?
X

Comments: As the grid operator managing electricity for 14 jurisdictions and 67 million customers, PJM’s success or failure is intertwined with the public interest. Electricity is a public good necessary to modern life. Reliable electricity is critical and it must also be affordable. PJM governing documents should be revised to reflect that the Board must act in the public interest by balancing reliability and affordability.

9) Should state representatives have at least one voting member on the
Nominating Committee?
X

Comments: Yes, and ideally 3: one designated by OPSI, one designated by a governors/legislators group, and one statutory consumer advocate.

10) Should PJM adopt public performance metrics and tie management
compensation to their achievement?
X

Comments: none

11) Should the stakeholder process be advisory, i.e., stakeholder votes only inform
the Board?

X

Comments: No, the PJM Board has not exercised its existing 205 rights effectively. The stakeholder process should only become advisory if PJM’s governing documents are reformed to incorporate affordability and the public interest, and states and the Members Committee have 205 jump ball filing rights. The vast majority of the time, PJM Members are able to come to consensus, and FERC should not so easily disregard a proposal brought by a two-thirds majority of Members by making the stakeholder process advisory-only. Instead of automatically privileging PJM staff’s perspective, FERC should be able to also consider proposals supported by either a two-thirds majority of OPSI or a two-thirds majority of PJM Members. Having the potential for several options would facilitate FERC selecting solutions that best achieve reliability at least cost.

PDF page 19

19

Questions/Comments
Yes
No
12) Should PJM have section 205 filing rights over the energy market and ancillary services unencumbered by the requirement to obtain approval of two-thirds of the Members Committee?

X

Comments: PJM should only receive expanded 205 rights if the mission is revised to incorporate affordability and the public interest and the states and Members Committee have jump ball filing rights.

13) Should PJM have section 205 filing rights over Regional Transmission Expansion Planning (RTEP) unencumbered by the requirement to obtain approval of two-thirds of the Members Committee?

X

Comments: PJM should only receive expanded 205 rights if the mission is revised to incorporate affordability and the public interest and the states and Members Committee have jump ball filing rights.

14) Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal?

X

Comments: none
15) Should the Members Committee have “jump ball” filing rights over the portions of the tariff where PJM has 205 filing rights when a supermajority of stakeholders approves an alternative proposal?

X

Comments: none

16) Should the approval threshold in the Members Committee be lowered from two- thirds sector-weighted voting?

X

Comments: none
17) Should the voting rules barring affiliate votes, which apply to senior standing committees, also apply to lower-level committees?

X

Comments: none

PDF page 20

20

Questions/Comments
Yes
No
18) In addition to OPSI, should there be a second state representative group
consisting of governors’ representatives and/or state legislators’
representatives?
X

Comments: none.
19) Should state representatives have a formal voting role in the stakeholder
process (limited to certain topics, such as resource adequacy and regional
transmission cost allocation) in addition to the consumer advocate votes?
X
Comments: If the states want a vote, then that is appropriate. However, the states should have powers that are distinct from (and not beholden to) the stakeholder process.

20) Should PJM be required to consult with OPSI prior to making a section 205
filing related to resource adequacy and transmission cost allocation?
X
Comments: Prior to making major filings at FERC, the PJM Board should consult with OPSI. This could entail the Board sharing draft filings with OPSI for feedback prior to formal filing at FERC. Allowing OPSI to review filings in advance would head off key concerns by the states and could lead to less litigation. For the purposes of formal OPSI consultation, major filings could be filings resulting in a certain threshold of cost impact, or at minimum, any policy decided through a CIFP. States input should extend to transmission planning and the energy and ancillary services markets, not just resource adequacy and transmission cost allocation.