Post-Conference Comments of the Delaware Division of the Public Advocate, et al. re PJM Governance and Stakeholder Reforms
Text extracted from the eLibrary original (SHA-256 34b54a5f93b42dfa…). Download the original from the official source.
Contents · 20 sections
- I. EXPANDED 205 RIGHTS FOR THE PJM BOARD SHOULD ONLY BE PURSUED
- II. THE “CREDIBILITY TRAP” IS RESOLVABLE WITH MEANINGFUL COST OVERSIGHT
- III. IMPROVEMENTS TO PJM’S BOARD ARE NECESSARY TO ACHIEVE POSITIVE
- IV. CONSENSUS-BUILDING IN THE STAKEHOLDER PROCESS CAN BE IMPROVED BY
- I. EXPANDED 205 RIGHTS FOR THE PJM BOARD SHOULD ONLY BE
- A. The Board has not used its existing filing rights effectively
- B. The need to reflect affordability and the public interest in PJM’s mission
- C. States must have 205 jump ball filing rights
- II. THE “CREDIBILITY TRAP”7 IS RESOLVABLE WITH MEANINGFUL COST
- A. Require cost impact information and ongoing cost impact dialogue
- B. Appoint an Independent Transmission Monitor
- III. IMPROVEMENTS TO PJM’S BOARD ARE NECESSARY TO ACHIEVE
- A. Expand the Nominating Committee to include state representatives
- B. Expand the Board expertise requirements to include state and ratepayer
- C. Open Board meetings and publish Board votes
- IV. CONSENSUS-BUILDING IN THE STAKEHOLDER PROCESS CAN BE
- A. Expand sector-weighted voting to all Standing Committees and Senior Task
- B. Require transparency of individual firm votes across all committee levels
- C. Record and publicly share stakeholder meetings
- V. CONCLUSION
Read topic-matched comments in AD26-7
Topics in the text: Cost allocation · Registry access · Reliability and curtailment
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Cost allocation
Governance reforms must thus have an eye to both state and ratepayer representation.Read this passage Filed comments: Cost allocation
I. EXPANDED 205 RIGHTS FOR THE PJM BOARD SHOULD ONLY BE PURSUED
printed heading
States must have 205 jump ball filing rights ....................................................................... 6Read this passage
II. THE “CREDIBILITY TRAP” IS RESOLVABLE WITH MEANINGFUL COST OVERSIGHT
printed heading
THE “CREDIBILITY TRAP” IS RESOLVABLE WITH MEANINGFUL COST OVERSIGHT 8 A.Read this passage
III. IMPROVEMENTS TO PJM’S BOARD ARE NECESSARY TO ACHIEVE POSITIVE
printed heading · Topic match: Cost allocation
III.Read this passage Filed comments: Cost allocation
IV. CONSENSUS-BUILDING IN THE STAKEHOLDER PROCESS CAN BE IMPROVED BY
printed heading
IV.Read this passage
I. EXPANDED 205 RIGHTS FOR THE PJM BOARD SHOULD ONLY BE
printed heading
The PJM Board must not be granted expanded 205 rights unless and until the LLC’s mission and governing documents are reformed to account for affordability and the public interest, and the states and Members Committee have 205 jump ball filing rights on all topics.Read this passage
A. The Board has not used its existing filing rights effectively
printed heading
Should the Commission grant the PJM Board expanded 205 filing rights, it must only do so once the PJM mission and governing documents are revised to include affordability and the public interest, and the states and Members Committee have jump ball filing rights.Read this passage
B. The need to reflect affordability and the public interest in PJM’s mission
printed heading
Reliable electricity is critical and it must also be affordable.Read this passage
C. States must have 205 jump ball filing rights
printed heading · Topic match: Registry access
States must have 205 jump ball filing rights The status quo of the states having merely an informal advisory role to PJM through the Organization of the PJM States (OPSI) is not working.Read this passage Filed comments: Registry access
II. THE “CREDIBILITY TRAP”7 IS RESOLVABLE WITH MEANINGFUL COST
printed heading
THE “CREDIBILITY TRAP”7 IS RESOLVABLE WITH MEANINGFUL COST OVERSIGHTRead this passage
A. Require cost impact information and ongoing cost impact dialogue
printed heading · Topic match: Cost allocation
PJM- managed markets and planning account for more than half of the cost of residential ratepayer bills across the states in the region.8 There is no way to evaluate whether PJM has achieved just and reasonable rates without cost impact information.Read this passage Filed comments: Cost allocation
B. Appoint an Independent Transmission Monitor
printed heading · Topic match: Registry access
By improving transmission oversight, planning would be improved, costs would be better 9 Consumer Advocates of the PJM States (CAPS) Presentation, PJM Annual Meeting, May 13, 2026. https://www.pjm.com/-/media/DotCom/committees-groups/user-groups/pieoug/2026/20260513/20260513-item-03--…Read this passage Filed comments: Registry access
III. IMPROVEMENTS TO PJM’S BOARD ARE NECESSARY TO ACHIEVE
printed heading
IMPROVEMENTS TO PJM’S BOARD ARE NECESSARY TO ACHIEVE POSITIVE GOVERNANCE REFORM The lack of a public interest mandate has allowed the PJM Board to largely ignore the cost impacts of PJM decisions on the 67 million customers it serves.Read this passage
A. Expand the Nominating Committee to include state representatives
printed heading · Topic match: Registry access
Expand the Nominating Committee to include state representatives We agree with Jacob Finkel’s suggestion, on behalf of the Governors Collaborative, to expand the Nominating Committee to include 3 designees of the states.11 A potential model would be a seat for an OPSI designee, a seat for an…Read this passage Filed comments: Registry access
B. Expand the Board expertise requirements to include state and ratepayer
printed heading · Topic match: Cost allocation
For example, there must always be a Board member with transmission planning experience.Read this passage Filed comments: Cost allocation
C. Open Board meetings and publish Board votes
printed heading
Open Board meetings and publish Board votes Board meetings are currently conducted in private.Read this passage
IV. CONSENSUS-BUILDING IN THE STAKEHOLDER PROCESS CAN BE
printed heading
CONSENSUS-BUILDING IN THE STAKEHOLDER PROCESS CAN BE IMPROVED BY MODIFICATIONS TO VOTING AND TRANSPARENCY RULESRead this passage
A. Expand sector-weighted voting to all Standing Committees and Senior Task
printed heading · Topic match: Registry access
This is more votes than every consumer advocate combined, since consumer advocate votes are capped at one for each of the 14 jurisdictions.12 The barrier to consensus emerges once proposals are advanced to the Senior Standing Committees of the MRC and MC.Read this passage Filed comments: Registry access
B. Require transparency of individual firm votes across all committee levels
printed heading · Topic match: Registry access
Just as elected officials must vote in public, PJM Members should as well.Read this passage Filed comments: Registry access
C. Record and publicly share stakeholder meetings
printed heading
Record and publicly share stakeholder meetings There are more PJM meetings than days in the year, and many meetings run as long as 8 hours.Read this passage
V. CONCLUSION
printed heading · Topic match: Cost allocation
Reliable electricity is critical and it must also be affordable.Read this passage Filed comments: Cost allocation