AD26-7-000 · 2026-08-21 · Old Dominion Electric Cooperative

Comments of Old Dominion Electric Cooperative in response to FERC's 07/30/2026 Notice re PJM Governance and Stakeholder Reforms

Text extracted from the eLibrary original (SHA-256 ce2b2c9b8d15d02b…). Download the original from the official source.

Contents · 9 sections
  1. I. INTRODUCTION p. 1
  2. II. COMMENTS p. 3
  3. A. Overview of ODEC p. 3
  4. B. Board Independence p. 4
  5. C. Section 205 Filing Rights p. 5
  6. D. Stakeholder Process p. 7
  7. E. State Participation p. 8
  8. III. RESPONSE TO THE QUESTIONS IN THE COMMISSION’S JULY 30 NOTICE p. 9
  9. IV. CONCLUSION p. 13

Read topic-matched comments in AD26-7

Topics in the text: Reliability and curtailment · Cost allocation · Registry access

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

1 UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Governance and Stakeholder Reforms ) Docket No.
Read this passage

I. INTRODUCTION

printed heading

INTRODUCTION Old Dominion Electric Cooperative (“ODEC”) appreciates this opportunity to provide comments pursuant to the Notice issued by the Commission in the above-referenced proceeding on July 30, 2026.
Read this passage

II. COMMENTS

printed heading

II.
Read this passage

A. Overview of ODEC

printed heading

Overview of ODEC ODEC is a not-for-profit power supply electric cooperative, organized and operating under the laws of Virginia and subject to FERC jurisdiction.
Read this passage

B. Board Independence

printed heading · Topic match: Registry access

The Board must also possess the expertise, transparency, accountability, and perspective necessary to maintain stakeholder confidence and effectively respond to the increasingly complex reliability, market, and transmission challenges facing the PJM region.
Read this passage Filed comments: Registry access

C. Section 205 Filing Rights

printed heading

Section 205 Filing Rights Section 205 filing rights are among the most consequential authorities within PJM’s governance framework.
Read this passage

D. Stakeholder Process

printed heading

Stakeholder Process PJM’s stakeholder process is one of the organization’s defining characteristics and serves as the primary mechanism for developing changes to PJM’s markets, planning procedures, operations, and governing documents.
Read this passage

E. State Participation

printed heading · Topic match: Reliability and curtailment

As PJM’s decisions increasingly affect reliability, affordability, transmission investment, and resource adequacy, many stakeholders have proposed expanding the role of states within PJM governance.
Read this passage Filed comments: Reliability and curtailment

III. RESPONSE TO THE QUESTIONS IN THE COMMISSION’S JULY 30 NOTICE

printed heading · Topic match: Cost allocation

Specifically, “public interest” for PJM and its Board should be ensuring the discharge of PJM’s duties and responsibilities “in a manner consistent with the safe and reliable operation of the Interconnection, the creation of a robust, competitive, and non-discriminatory electric power market in the…
Read this passage Filed comments: Cost allocation

IV. CONCLUSION

printed heading

CONCLUSION 14 WHEREFORE, for the foregoing reasons, ODEC requests that the Commission consider these comments in its determinations regarding whether and how to reform PJM governance and stakeholder processes.