AD26-7-000 · 2026-08-21 · Old Dominion Electric Cooperative
Comments of Old Dominion Electric Cooperative in response to FERC's 07/30/2026 Notice re PJM Governance and Stakeholder Reforms
PDF page 1
1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Governance and Stakeholder Reforms
)
Docket No. AD26-7-000
COMMENTS OF OLD DOMINION ELECTRIC COOPERATIVE
I. INTRODUCTION
Old Dominion Electric Cooperative (“ODEC”) appreciates this opportunity to provide comments pursuant to the Notice issued by the Commission in the above-referenced proceeding on July 30, 2026. As discussed herein, ODEC generally supports the existing PJM governance and stakeholder process. However, ODEC also understands that the Commission has undertaken a review “with a particular focus on identifying and evaluating actionable reforms to improve PJM’s ability to address system needs in a timely and efficient manner.”1 With this focus in mind, ODEC offers comments on the issues discussed at the Technical Conference held on July 23, 2026. ODEC also provides in this pleading answers to the questions posed in the Commission’s July 30, 2026 Notice.
ODEC believes PJM’s governance model has generally served the region well and should not be fundamentally restructured. The stakeholder process remains one of PJM’s defining strengths and continues to provide valuable technical expertise, stakeholder engagement, and accountability. At the same time, ODEC believes targeted reforms are warranted to improve transparency, strengthen Board accountability, modernize certain governance requirements, and enhance the effectiveness of the stakeholder process. Targeted reforms to PJM’s governance and stakeholder process should also result in improved involvement and coordination with the PJM states.
1 Notice of Commission-Led Technical Conference, issued in this proceeding on May 12, 2026, at page 1.
PDF page 2
2
As discussed below, ODEC generally supports reforms while preserving meaningful stakeholder participation and avoiding unnecessary concentrations of authority. ODEC has considered the governance and stakeholder reforms as an integrated package. To the extent some reforms are not made, they will impact ODEC’s support for other reforms. For example, while ODEC supports granting PJM independent FPA Section 205 filing authority over certain core market and transmission planning matters, ODEC’s support is conditioned on (1) the PJM stakeholder process continuing to require PJM to thoroughly vet changes with stakeholders; (2) stakeholders retaining the ability to advance competing proposals through a Members Committee “jump ball” filing process; and (3) the Commission ensures that such grant of PJM FPA section 205 authority maintains PJM’s independence from control by any market participant or class of market participants, as required by Order No. 2000.2
In summary, ODEC supports a governance reform package that includes the following: Board of Managers
Extend Board member terms from three years to five years.
Eliminate Board term limits.
Reduce the Board cooling-off period from two years to one year.
Increase Board transparency through public voting records.
Increase Board transparency through public Board meetings where practical. Add state representation to the PJM Nominating Committee.
Recognize reliability, affordability, and efficient markets as components of the Board’s public interest responsibilities.
Stakeholder Process
Introduce a sector-weighted approval threshold in lower-level committees thereby eliminating affiliate voting.
Retain lower-level committees and technical forums as part of PJM’s governance structure.
State Participation
Consolidate and better coordinate existing avenues for state participation. 2 Reg’l Transmission Orgs., Order No. 2000, FERC Stats. & Regs. ¶ 31,089 at 31, 061 (1999); 18 C.F.R. § 35.34(j)(1)(ii) (2025).
PDF page 3
3
Permit advisory or informational state voting to communicate state perspectives to stakeholders and the Board.
Continue to explore opportunities for improved state engagement without granting formal voting rights or independent Section 205 filing authority.
Add state representation to the PJM Nominating Committee.
Section 205 Filing Rights
Grant PJM independent Section 205 filing rights over Energy Market, Ancillary Services Market, and RTEP matters.
Preserve meaningful stakeholder participation.
Grant the Members Committee corresponding “jump ball” filing rights that allow stakeholders to submit competing proposals directly to FERC.
Ensure PJM independence from any stakeholder or stakeholder segment.
ODEC recognizes that several proposals currently under discussion, as well as positions that may be advanced during the dispute resolution process, warrant additional evaluation before definitive positions can be adopted. In particular, ODEC expects to have further comment after review of PJM’s proposal for governance and stakeholder reforms, as invited by the Commission.3
II. COMMENTS
A. Overview of ODEC
ODEC is a not-for-profit power supply electric cooperative, organized and operating under the laws of Virginia and subject to FERC jurisdiction. ODEC supplies capacity and energy to its eleven electric distribution cooperative members in Delaware, Maryland and Virginia, all of which are located within the PJM control area. ODEC is a network transmission customer of PJM, as well as a PJM Transmission Owner. ODEC is also a generation owner in PJM. ODEC takes transmission service under the PJM Tariff. ODEC is also a Market Seller of energy and capacity under the PJM Tariff. Thus, ODEC participates in each market operated by PJM and also participates extensively in the PJM stakeholder process as a member of the Electric Distributor (“ED”) sector.
3 July 26th Notice at page 2.
PDF page 4
4
B. Board Independence
ODEC supports maintaining an independent Board of Managers and believes Board independence remains an essential component of effective regional governance. The Board must also possess the expertise, transparency, accountability, and perspective necessary to maintain stakeholder confidence and effectively respond to the increasingly complex reliability, market, and transmission challenges facing the PJM region. Accordingly, ODEC supports consideration of several targeted reforms to strengthen the Board’s effectiveness and legitimacy while preserving its independence and oversight role. Those reforms include the following:
Increasing the term of PJM Board members from three years to five years, and eliminating term limits;
Reducing the “cooling off” period from two years to one year;
Increasing transparency into PJM Board decision-making through the publication of individual Board voting records and expanded use of public Board meetings;
Recognizing the public interest as a responsibility of the PJM Board, provided that the concept of “public interest” is clearly defined and tied to PJM’s core mission, with the addition of affordability; and
Adding state representation on the PJM Nominating Committee.
In addition to these reforms, there are several aspects of PJM’s Board composition and process that ODEC believes should be retained. For example, the existing restrictions against ex parte communication with the PJM Board should not be relaxed. ODEC also does not support imposing a mandatory residency requirement for members of the PJM Board of Managers. Familiarity and/or expertise regarding the PJM region is helpful, but residing in the region is not critical. Instead of a residence requirement, the Board member qualification rules should be revised to
PDF page 5
5
require a breadth of experience that will ensure fair consideration of various perspectives. Specifically, there should be a requirement that at least two Board members have experience that would qualify for the Electric Distributor (end-use customer) sector and/or at least one Board position for a State PUC or consumer advocate.
C. Section 205 Filing Rights
Section 205 filing rights are among the most consequential authorities within PJM’s governance framework. Within PJM, the allocation of Section 205 filing authority is not straightforward. While certain filing rights are expressly granted to PJM, Transmission Owners, or other entities, the ability to propose reforms is often influenced by where the relevant provisions appear in PJM’s governing documents and the approval processes applicable to those documents. As a result, discussions regarding “who holds a Section 205 filing right” frequently refer not only to legal filing authority before FERC but also to which entity’s approval is required for a proposal to be advanced.
Consequently, proposals to move a provision from the Operating Agreement to the Tariff, or to transfer filing authority from one entity to another, are often about more than filing rights alone. Such reforms can alter the role of stakeholders in the development of PJM rules, affect the degree of discretion afforded to PJM or the Board of Managers, and ultimately change the balance of authority within PJM’s governance structure. For this reason, the location of a provision within PJM’s governing documents can be nearly as important as the filing right itself when evaluating governance reform proposals. ODEC generally believes governance reforms should focus less on preserving existing filing-right allocations and more on ensuring that any reallocation of authority maintains appropriate checks and balances among the PJM Board, and stakeholders.
PDF page 6
6
ODEC conditionally supports granting the PJM Board independent Section 205 filing rights over the Energy Market and Ancillary Services Markets, as well as over RTEP matters, provided stakeholders retain the ability to advance competing proposals through a Members Committee “jump ball” filing process. ODEC believes PJM should possess sufficient authority to advance reforms to core Energy Market and Ancillary Services Market constructs when it determines such reforms are necessary to maintain reliability, improve market outcomes, or address emerging challenges facing the region. Similarly, PJM should possess sufficient authority to advance transmission planning reforms when it determines such reforms are necessary to maintain reliability, accommodate load growth, facilitate resource development, and/or improve the efficiency of the transmission planning process. Providing PJM with independent Section 205 filing authority would allow PJM to bring proposals directly to FERC for consideration without first obtaining supermajority stakeholder approval. ODEC does not support further revisions to FPA Section 205 filing rights at this time.
At the same time, ODEC believes meaningful stakeholder participation remains an essential component of PJM governance. The Energy Market and Ancillary Services Markets directly affect generators, load-serving entities, electric distributors, transmission owners, consumers, and other market participants throughout the PJM footprint. Stakeholders provide valuable technical expertise and practical experience that improve market design and help identify unintended consequences associated with proposed reforms.
In addition to the “jump ball” filing process, it will be critical for the Commission to ensure that the PJM stakeholder process continues to require PJM to thoroughly vet changes with stakeholders. Also, as the Commission determined in rejecting PJM and the PJM Transmission Owners’ prior attempts to revise the governing documents regarding PJM FPA section 205 filing
PDF page 7
7
rights, any grant of PJM FPA section 205 authority maintains PJM’s independence from control by any market participant or class of market participants, as required by Order No. 2000.4
D. Stakeholder Process
PJM’s stakeholder process is one of the organization’s defining characteristics and serves as the primary mechanism for developing changes to PJM’s markets, planning procedures, operations, and governing documents. The process brings together representatives from all PJM sectors to provide technical expertise, identify potential impacts, and build consensus around proposed reforms.
While recent governance reform discussions have raised concerns regarding the speed and effectiveness of the stakeholder process, ODEC believes meaningful stakeholder participation remains one of PJM’s greatest strengths and should be preserved. At the same time, ODEC recognizes that certain reforms are warranted to improve efficiency, reduce procedural barriers, and ensure the process remains capable of addressing the increasingly complex challenges facing the PJM region.
One such change that ODEC supports in order to improve efficiency is to introduce a sector-weighted vote to approve proposals in PJM’s lower-level committees and senior task forces. Requiring sector-weighted vote in lower-level committees would help ensure that proposals brought forward to the Members Committee reflect greater consensus and have received meaningful consideration across stakeholder sectors. ODEC also supports eliminating affiliate voting at PJM’s lower-level committees and senior task forces. The purpose of lower-level committees is to develop proposals, identify stakeholder concerns, and build consensus among affected parties. Allowing affiliated entities to exercise multiple votes at this stage can create the 4 PJM Interconnection, L.L.C., 189 FERC ¶ 61,181 (2024); order on reh’g, Duquesne Light Co., et al., 192 FERC ¶ 61,051 (2025); 18 C.F.R. § 35.34(j)(1)(ii) (2025).
PDF page 8
8
perception that certain stakeholder groups possess disproportionate influence over issue development and committee recommendations. This reform would improve stakeholder confidence in the process, promote broader consensus-building, and create a more balanced forum for developing PJM proposals while preserving the existing sector-weighted voting framework at higher levels of the stakeholder process.
E. State Participation
States have an important interest in PJM governance given their responsibility for overseeing retail electric service and protecting consumer interests. As PJM’s decisions increasingly affect reliability, affordability, transmission investment, and resource adequacy, many stakeholders have proposed expanding the role of states within PJM governance. ODEC supports meaningful state engagement in PJM governance. However, any reforms should preserve clear lines of accountability, maintain PJM’s regional character, and recognize that individual states may have different positions on issues. Consistent with these principles, ODEC supports exploring opportunities to better coordinate and consolidate state participation within PJM governance but does not support creating additional state-focused organizations and forums. The existence of multiple state-focused organizations and forums can create uncertainty regarding which entity is speaking on behalf of the states, particularly in instances where different organizations within a single state may not agree. Multiple state-focused organizations will also make it difficult to determine whether a particular position reflects a consensus view or the perspective of a subset of states. ODEC also supports the use of non-binding advisory or informational voting mechanisms for states to communicate their views and the addition of state representation to the Nominating Committee. However, ODEC does not support granting states formal voting rights within PJM’s stakeholder process. As discussed in the response to the
PDF page 9
9
Commission’s questions, below, states initially opted against becoming Members of PJM. Moreover, states have the ability to communicate with and advise the PJM Board freely and would lose that capability as PJM Members. ODEC also notes that states can have a non-voting member on PJM standing committees. ODEC is concerned that granting states formal voting rights could blur the distinction between stakeholder governance and state regulatory oversight while creating uncertainty regarding how state votes would be allocated and exercised.
III. RESPONSE TO THE QUESTIONS IN THE COMMISSION’S JULY 30 NOTICE
PJM Board Independence
Questions/Comments
Yes No
1) Should Board members’ terms be extended to five or more years?
X
Comments: Board members will have an initial period of time where they learn PJM substantive matters and process (e.g., stakeholder, governance processes). Board members should serve some period of time after this “learning curve” period so that their education and experience can benefit the Board. Board terms should also be long enough to provide assurance to Board members that they will have an adequate term and also provide a sense of overall stability and consistency to stakeholders, particularly in this period of growth and associated challenges. However, it is also important that Board terms are of short enough duration that Board members will be willing to commit to service. A term of five years, but no more than five years, strikes a reasonable balance.
2) Should there be a maximum number of years that a Board member may
serve (e.g., 10 years)?
X
Comments: Term limits would result in losing Board members who are highly effective or have gained significant experience.
3) Should the Board member qualification rules be revised to provide a preference for some Board members that reside in the PJM region?
X
Comments: Familiarity and/or expertise regarding the PJM region is helpful, but residing in the region is not critical. Instead of a residence requirement, the Board member qualification rules should be revised to require a breadth of experience that will ensure fair consideration of various perspectives. Specifically, there should be a requirement that at least two Board members have experience that would qualify for the
PDF page 10
10
Questions/Comments
Yes No
Electric Distributor (end-use customer) sector and/or at least one Board position for a State PUC or consumer advocate.
4) Should the conflict-of-interest rules be revised to reduce the cooling off period for Board members from two years to one year?
X
Comments: the current two-year cooling-off period may unnecessarily exclude highly qualified individuals with valuable utility, market, regulatory, or operational experience. Reducing the restriction to one year would continue to provide meaningful conflict-of- interest protection while allowing PJM to recruit from a broader and more experienced pool of candidates.
5) Should restrictions on Board communications be relaxed to enable more communication between the Board and stakeholders?
X
Comments: The restrictions on Board communications protect against individual stakeholders or stakeholder groups exerting undue influence and ensure fair and equal representation of all stakeholder interests.
6) In order to increase transparency, should Board votes be made public or the Board be required to explain its reasoning?
X
Comments: Stakeholders should be able to understand how significant decisions are reached and how individual Board members exercise their responsibilities. Publishing Board voting records would provide appropriate accountability for directors and improve understanding of Board decision-making.
7) In order to increase transparency, should some Board meetings be open or available to the public?
X
Comments: Consistent with the response to question 6 above, meetings and votes should be open and available to the public as listen-only sessions. Alternatively, meeting minutes could be publicly available after Board meetings.
8) Should PJM’s governing documents be revised to explicitly state that the responsibility of PJM and its Board is to serve the public interest?
X
Comments: The responsibility should be to serve the public interest but “public interest” needs to be defined consistent with the PJM Charter. Specifically, “public interest” for PJM and its Board should be ensuring the discharge of PJM’s duties and responsibilities “in a manner consistent with the safe and reliable operation of the Interconnection, the creation of a robust, competitive, and non-discriminatory electric power market in the PJM Region and the principle that a Member or group of Members shall not have undue
PDF page 11
11
Questions/Comments
Yes No
influence over the operation of the Interconnection.”5 ODEC further recommends that affordability should be added to the PJM Charter and Board responsibilities.
9) Should state representatives have at least one voting member on the Nominating Committee?
X
Comments: State representation on the Nominating Committee would improve communication between PJM and the states, enhance confidence in the Board selection process, and help ensure that state perspectives are considered when evaluating potential Board candidates. Importantly, representation on the Nominating Committee would provide states with input into the candidate identification process without compromising Board independence or giving states direct control over Board decisions.
10) Should PJM adopt public performance metrics and tie management
compensation to their achievement?
Comments: ODEC does not currently have a definitive position regarding proposals to tie PJM executive compensation to publicly disclosed performance metrics. Additional evaluation is warranted regarding the appropriate metrics, implementation approach, and potential unintended consequences of such reforms.
Section 205 Filing Rights
Questions/Comments
Yes No
11) Should the stakeholder process be advisory, i.e., stakeholder votes only inform the Board?
X
Comments: ODEC is willing to accept PJM’s having FPA section 205 filing rights over the energy market, ancillary services market, and RTEP matters provided that (1)the advisory stakeholder process provides meaningful input and information to the Board;
(2) continued assurance that PJM will maintain its independence; (3) an active role for states; (4) the Board will act more in the interest of load which will be accomplished by ensuring Board members with experience from the electric distributor sector; and (5) “jump ball” filing procedures where PJM would submit to FERC both the Board proposal as well as proposals from the Members Committee meetings. The “jump ball” rights should be for proposals vetted during the MC as opposed to any particular sector or interests.
5 PJM Board of Managers Master and Committee Charters at page 1, available at board-committees-charter- 2026.pdf (last accessed August 20, 2026).
PDF page 12
12
Questions/Comments
Yes No
12) Should PJM have section 205 filing rights over the energy market and ancillary services unencumbered by the requirement to obtain approval of two-thirds of the Members Committee?
X
Comments: See comments on question 11, above.
13) Should PJM have section 205 filing rights over Regional Transmission Expansion Planning (RTEP) unencumbered by the requirement to obtain approval of two-thirds of the Members Committee?
X
Comments: See comments on question 11, above.
14) Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal?
X
Comments: See comments on question 11, above.
15) Should the Members Committee have “jump ball” filing rights over the portions of the tariff where PJM has 205 filing rights when a supermajority of stakeholders approves an alternative proposal?
X
Comments: See comments on question 11, above.
Stakeholder Process
Questions/Comments
Yes No
16) Should the approval threshold in the Members Committee be lowered from two-thirds sector-weighted voting?
X
Comments: The current supermajority voting requirement is an important feature of PJM’s stakeholder governance framework. The requirement helps ensure that significant changes to PJM’s markets, planning processes, operations, and governance structure receive broad support across multiple stakeholder sectors before moving forward.
17) Should the voting rules barring affiliate votes, which apply to senior standing committees, also apply to lower-level committees? X
PDF page 13
13
Questions/Comments
Yes No
Comments: Eliminating affiliate voting at lower-level committees would help ensure that stakeholder recommendations more accurately reflect the views of distinct market participants rather than corporate families with multiple affiliated entities. State Participation
Questions/Comments
Yes No
18) In addition to OPSI, should there be a second state representative group consisting of governors’ representatives and/or state legislators’
representatives?
X
Comments: States have an important role to play in PJM governance. However, the existence of multiple state-focused organizations and forums can create uncertainty regarding which entity is speaking on behalf of the states, particularly in instances where different organizations within a single state may not agree. Multiple state-focused organizations will also make it difficult to determine whether a particular position reflects a consensus view or the perspective of a subset of states.
19) Should state representatives have a formal voting role in the stakeholder process (limited to certain topics, such as resource adequacy and regional transmission cost allocation) in addition to the consumer advocate votes? X
Comments: During the formation of PJM, the states chose not to be Members of PJM out of concern that they would be in a position of voting on matters that may come before them in their state regulatory roles. (See PJM Comments filed in Docket No. AD26-7, at 10). States have the ability to communicate with and advise the PJM Board freely and would lose that capability as PJM Members. ODEC also notes that states can have a non-voting member on PJM standing committees. ODEC is concerned that granting states formal voting rights could blur the distinction between stakeholder governance and state regulatory oversight while creating uncertainty regarding how state votes would be allocated and exercised.
20) Should PJM be required to consult with OPSI prior to making a section 205 filing related to resource adequacy and transmission cost allocation? Comments: ODEC does not currently have a definitive position on whether PJM should be required to consult with states before exercising its Section 205 filing rights.
IV. CONCLUSION
PDF page 14
14
WHEREFORE, for the foregoing reasons, ODEC requests that the Commission consider these comments in its determinations regarding whether and how to reform PJM governance and stakeholder processes.
Respectfully submitted,
/s/ Adrienne E. Clair
Adrienne E. Clair
Thompson Coburn LLP
1909 K Street, N.W., Suite 600
Washington, D.C. 20006-1167
(202) 585-6900
(202) 585-6969 (fax)
aclair@thompsoncoburn.com
Attorney for Old Dominion Electric
Cooperative
Dated: August 21, 2026
PDF page 15
CERTIFICATE OF SERVICE
I hereby certify that on this 21st day of August 2026, I have caused a copy of the foregoing to be served upon each party designated on the Commission’s Official Service List for this proceeding.
/s/Adrienne E. Clair