AD26-7-000 · 2026-08-21 · PJM Industrial Customer Coalition

Post-Technical Conference Comments of The PJM Industrial Customer Coalition in response to FERC's 07/30/2026 supplemental notice re PJM Governance and…

Text extracted from the eLibrary original (SHA-256 a86ed864faf1f943…). Download the original from the official source.

Contents · 6 sections
  1. I. Background p. 3
  2. II. Areas of Common Ground p. 4
  3. III. Areas of Divergence p. 4
  4. IV. Accountability Considerations p. 6
  5. V. Proposed Accountability Safeguards p. 7
  6. VI. Conclusion p. 10

Read topic-matched comments in AD26-7

Topics in the text: Reliability and curtailment · Cost allocation · Registry access

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

1 UNITED STATES OF AMERICA FEDERAL ENERGY REGULATORY COMMISSION PJM Governance and Stakeholder Reforms : Docket No.
Read this passage

I. Background

printed heading · Topic match: Reliability and curtailment

Subsequently, PJM circulated its mediation term sheet proposing eight reform measures, including proposing to assume from PJM Members additional Section 205 filing authority, making the Members Committee advisory to the RTO on all matters, extending Board terms to nine years, and creating state…
Read this passage Filed comments: Reliability and curtailment

II. Areas of Common Ground

printed heading

Areas of Common Ground PJMICC supports PJM’s willingness to streamline committee structures and create expedited processes, provided that the process continues to solicit and consider diverse viewpoints.
Read this passage

III. Areas of Divergence

printed heading · Topic match: Reliability and curtailment

Of particular importance is the relationship between PJM’s proposed Section 205 filing rights and the stakeholder checks that currently govern those rights. 5 PJM’s mediation term sheet proposes removing PJM Members’ Section 205 filing authority over the energy and ancillary services markets, as…
Read this passage Filed comments: Reliability and curtailment

IV. Accountability Considerations

printed heading

Accountability Considerations A central concern animating these comments is what may be viewed as an “accountability gap” in PJM’s reform proposals.
Read this passage

V. Proposed Accountability Safeguards

printed heading

Proposed Accountability Safeguards To address the considerations identified above, PJMICC respectfully proposes the following measures to complement any governance reform package.
Read this passage

VI. Conclusion

printed heading · Topic match: Reliability and curtailment

X Comments: On resource adequacy, where PJM already has Section 205 rights, and PJM Members are advisory, a formal vote to signal states’ position would help to advise the PJM Board. 20) Should PJM be required to consult with OPSI prior to making a section 205 filing related to resource adequacy…
Read this passage Filed comments: Reliability and curtailment

CERTIFICATE OF SERVICE

printed heading

Bruce McNees Wallace & Nurick LLC 100 Pine Street Harrisburg, PA 17101 Tel: 717-232-8000 Fax: 717-237-5300 E-mail: sbruce@mcneeslaw.com
Read this passage