AD26-7-000 · 2026-08-21 · Vitol Inc.

Comments of Vitol Inc. offering perspectives on PJM governance arising from the Commissioner-led Technical Conference on 07/23/2026

Text extracted from the eLibrary original (SHA-256 0605f4ee43233279…). Download the original from the official source.

Contents · 6 sections
  1. I. PJM Board Independence p. 2
  2. II. State Participation p. 4
  3. III. Section 205 Filing Rights p. 6
  4. IV. Stakeholder Process p. 8
  5. V. Conclusion p. 9
  6. VI. Communications and Correspondence p. 10

Read topic-matched comments in AD26-7

Topics in the text: Cost allocation · Registry access · Reliability and curtailment

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

1 UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Governance and Stakeholder Reforms ) Docket No.
Read this passage

I. PJM Board Independence

printed heading · Topic match: Reliability and curtailment

Specifically, if OPSI or a state governors’ organization provides a resource adequacy proposal backed by a supermajority of its members, PJM could be obligated within its FERC transmittal to explain its rationale for rejection of such proposal. 7) In order to increase transparency, should some…
Read this passage Filed comments: Reliability and curtailment

II. State Participation

printed heading · Topic match: Cost allocation

Any such reforms must be constructed to ensure state concerns are presented in a timely and actionable structure. 18) In addition to OPSI, should there be a second state representative group consisting of governors’ representatives and/or state legislators’ representatives?
Read this passage Filed comments: Cost allocation

III. Section 205 Filing Rights

printed heading · Topic match: Cost allocation

FERC, the court sustained FERC’s rejection of a utility filing compelled by a state regulator because Section 205 governs changes the utility itself proposes, not changes a state requires it to propose.3 OPSI may submit advisory alternatives, intervene, protest, or seek relief under Section 206,…
Read this passage Filed comments: Cost allocation

IV. Stakeholder Process

printed heading

Stakeholder Process There are many potential improvements that could be made to speed the stakeholder process, but these are secondary in importance to the questions posed above.
Read this passage

V. Conclusion

printed heading

Conclusion Vitol respectfully offers the responses above to the Commission’s Post Technical Conference queries.
Read this passage

VI. Communications and Correspondence

printed heading

Communications and Correspondence All communications and correspondence regarding this filing should be directed to:4 Vijay D’Cruz Seth Cochran* Vitol Inc. 3425 West Alabama St, Houston TX 77027 Houston, TX 77027 Phone: (713) 230-1000 vad@vitol.com sco@vitol.com.
Read this passage

CERTIFICATE OF SERVICE

printed heading

Dated at Houston, TX, this 21st day of August, 2026. /s/ Edwin Cambero Edwin Cambero Vitol Inc. 3425 West Alabama St.