AD26-7-000 · 2026-08-21 · ENGIE North America Inc.
Post-Conference Comments of ENGIE North America, Inc. re FERC's technical discussion of Governance and Stakeholder Reforms in the PJM Interconnection LLC…
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
)
PJM Governance and Stakeholder Reforms )
Docket No. AD26-7-000
)
POST-CONFERENCE COMMENTS OF ENGIE NORTH AMERICA, INC.
(August 21, 2026)
ENGIE North America, Inc.,1 (“ENGIE”) appreciates the opportunity to provide post-conference comments following the Federal Energy Regulatory Commission’s (“FERC” or “Commission”) technical discussion of Governance and Stakeholder Reforms in the PJM Interconnection LLC (“PJM”) region on July 23, 2026. We commend the Commission for its leadership in facilitating the candid and enlightening discussion. ENGIE submitted pre-technical conference comments and has registered to participate in the upcoming Alternative Dispute Resolution process.
ENGIE encourages reforms that strengthen confidence in PJM’s governance and stakeholder processes but that also preserve the critical role that PJM’s competitive wholesale markets play in maintaining reliability across the region..
I. COMMENTS
ENGIE’s pre-technical conference comments address several of the questions issued by the Commission in the Appendix to its Notice Requesting Post-Conference Comment (“Notice”) issued on July 30, 2026. One important matter is the critical need to modify the role of the PJM Board. We continue to believe that the role of the PJM Board is not to over involve itself in the detailed matrix of
1 ENGIE North America (“ENGIE”) is a subsidiary of ENGIE SA, a global energy company and one of the world’s largest producers of energy. With roots that trace back 180 years, we own and operate 110 GW of power generation, including 46 GW of natural gas generation, 6 GW of nuclear generation, and 57 GW of renewable generation – with 11 GW in North America. ENGIE operates the largest natural gas distribution network in Europe, owns 2,485 miles of transmission lines, is a global leading energy supplier to commercial and industrial customers, and is a significant supplier of U.S. produced LNG to Europe.
PDF page 2
ENGIE CommentsDocket No. AD26-07-000Page 2
decisions in the PJM stakeholder process. Instead the Board should be focused on matters of Board-level relevance such as providing strategic oversight, ensuring accountability, managing risk, and promoting PJM’s long-term success. This should both increase the efficiency of the stakeholder process but, importantly, provide leadership and vision for PJM and its leadership. We invite you to review our pre- technical conference comments for further detail.2
ENGIE is pleased to offer the following comments in response to the Commission’s specific questions on PJM Board independence, Section 205 filing rights, the stakeholder process, and state participation.
A. PJM Board Independence
Questions/Comments
Yes
No
1) Should Board members’ terms be extended to five or more years?
X
Comments:
Board members term lengths should be five years. However, because there is a significant learning curve for Board members, it takes time to implement strategic vision, and board members are more able to engage meaningfully with increased experience, board members should be allowed to serve two five-year terms for a total of ten years. Board members must stand for re-election following the conclusion of the initial five-year term.
2) Should there be a maximum number of years that a Board member may
serve (e.g., 10 years)?
X
Comments:
Ten years. Two terms of five years.
3) Should the Board member qualification rules be revised to provide a
preference for some Board members that reside in the PJM region?
X
Comments:
The rules should not be revised to mandate a preference for Board members from the PJM
2 Comments of ENGIE North America, Docket No. AD26-7-000 (filed July 22, 2026) at pp. 2-3.
PDF page 3
ENGIE CommentsDocket No. AD26-07-000Page 3
region. Because it is already a challenge to identify qualified candidates due to business and other conflicts, we advise against placing further restrictions on Board member selection. However, as a matter of procedure, the nominating committee could give preference to candidates that are in the PJM region as is the practice in ISO New England. Further, perspectives from outside of the PJM operating area are beneficial t the region. If a preference for Board members from the PJM region is mandated, the mandate should be limited to three members.
4) Should the conflict-of-interest rules be revised to reduce the cooling off period for Board members from two years to one year?
X
Comments:
Stringent conflict of interest rules make it challenging to identify qualified candidates. Relaxing the rules appropriately should help to expand the pool of eligible candidates.
5) Should restrictions on Board communications be relaxed to enable more communication between the Board and stakeholders?
X
Comments:
Increased communication between Board members and market participants and other stakeholders should tend to increase trust and understanding between all parties. However, communication opportunities must be meaningful in terms of venue and content and with opportunities for direct dialogue. PJM stakeholders should have regular, formal and informal opportunities to meet with the Board to discuss items of interest. For example, market participants in New England meet with the ISO-NE Board twice a year in meetings with their New England Power Pool (“NEPOOL”) sectors. The Board also engages through other regional opportunities such as with the ISO-NE Consumer Liaison Group and the New England Conference of Public Utilities Commissioners and are generally responsive to individual market participant outreach.
6) In order to increase transparency, should Board votes be made public or the Board be required to explain its reasoning?
X
PDF page 4
ENGIE CommentsDocket No. AD26-07-000Page 4
Questions/Comments
Yes
No
Comments:
ENGIE’s pre-Technical Conference comments urge PJM to refocus its board’s role on appropriate board-level activities. In this context, the Board would not vote on market rule changes and therefore, Board reasoning and votes may not need to be made public. Importantly, the PJM Board should focus on the traditional and essential matters of governance: providing strategic oversight, ensuring accountability, managing risk, and promoting PJM’s long-term success. The Board should not be excessively involved in the tactical stakeholder process. It is an inefficient use of time and resources for the Board to participate directly in stakeholder decision-making exercises, such as evaluating a matrix of many complex and competing choices. The Board should instead be advised of and consulted on major reforms so that Board members are appropriately informed, remain accountable and, in turn, can hold the PJM organization responsible for implementation of market design and other changes.
7) In order to increase transparency, should some Board meetings be open or available to the public?
X
Comments:
Some level of openness of the Board meetings would provide stakeholders with a better understanding of how the Board functions and is likely to engender trust. As importantly as open board meetings are opportunities for stakeholders to interact with Board members and a generally openness of Board members to meet with stakeholders. Increased transparency should not interfere with the work of the Board to the extent that the work cannot be done efficiently.
8) Should PJM’s governing documents be revised to explicitly state that the responsibility of PJM and its Board is to serve the public interest?
Comments:
Much of the language in the governing documents that is used to describe the duties and responsibilities of the PJM Board and the formation of market prices signify the organization’s intent to serve the public interest. Embracing the meaning of terms like competitive, non-discriminatory, transparent, efficient, just, and reasonable should drive market results that are sustainable for buyers and sellers. Sustained market success does not mean preferrable results to either buyers or sellers but at least acceptable or tolerable to both. Importantly, PJM is already subject to a public interest framework through FERC oversight since it operates under FERC-approved tariffs and governing documents. FERC itself is charged under the Federal Power Act with ensuring that rates and practices are just, reasonable, and not unduly discriminatory.
Further, the term “public interest” could mean reliability, affordability, competition, environmental goals, consumer protection, competition, economic development, and state policy objectives. There is something for every perspective. Implementing such a mandate
PDF page 5
ENGIE CommentsDocket No. AD26-07-000Page 5
would be subject to the interpretation of the PJM leadership of the time and require careful balancing to ensure unfettered operation of the competitive wholesale electricity markets.
9) Should state representatives have at least one voting member on the Nominating Committee?
X
Comments:
It is important that states share the opportunity and burden of identifying and electing PJM Board members. However, the Nominating Committee process must not become a political process. So, assuming rational actors behave reasonably and considering the existing slate of five Sector voting members and two Board of Directors voting members, ENGIE recommends the addition of onevoting slot for the PJM states. This would allow the states to have a meaningful impact on the process. However, adding one member to the Nominating Committee results in an even number of voting members and the potential for a vote with no majority. In order to address this possible outcome, ENGIE supports the addition of one “tie-break” member to the Nominating Committee jointly elected by the five Sectors. This ninth voting member could participate in the Nominating Committee process but only vote if needed to create a majority choice.
10) Should PJM adopt public performance metrics and tie management
compensation to their achievement?
X
Comments:
Adopting public performance metrics may be counterproductive and could lead to unintended consequences. We have observed that there is already an environment of heightened and unproductive scrutiny. Metrics may tend to promote near-term thinking and action, particularly at the Board level, while a professional Board should be thinking about long term strategy and organizational health.
Any metrics adopted must be clearly defined and support the organization’s strategy and priorities whenever these items are clearly defined by leadership.
B. Section 205 Filing Rights
Questions/Comments
Yes
No
11) Should the stakeholder process be advisory, i.e., stakeholder votes only inform the Board?
X
Comments:
While we believe that PJM leadership, not the Board, should be the ultimate decision- maker, ENGIE is wary of moving to an advisory stakeholder process unless there are alternative recourses available for stakeholders.
ENGIE has experience in ISO-NE were advisory stakeholder processes provide a
PDF page 6
ENGIE CommentsDocket No. AD26-07-000Page 6
reasonable opportunity for market participants and regional stakeholders to engage meaningfully with ISO/RTO staff and leadership during multiple stakeholder processes including market rule changes and work prioritization without presenting insurmountable roadblocks to needed reforms. If stakeholders believe there has been sufficient engagement and that their questions and comments have been answered and acknowledged then it should be left to PJM leadership to make and informed decision based on the information they have learned from the stakeholder process and what they believe to be the best path forward for the region.
However, in an advisory voting process stakeholders should be granted a “jump ball” right to provide them with meaningful recourse at those times when a supermajority of stakeholders agree on an alternative path forward.
12) Should PJM have section 205 filing rights over the energy market and ancillary services unencumbered by the requirement to obtain approval of two-thirds of the Members Committee?
X
Comments:
We support permitting PJM to make section 205 filing rights without the need to obtain two-thirds approval by the Members Committee. However, if approval is not needed, PJM must still bring the filing through the stakeholder process for discussion, review and an advisory vote. Further, in an advisory voting process stakeholders should be granted a “jump ball” right to provide them with meaningful recourse at those times when a supermajority of stakeholders agree on an alternative path forward.
13) Should PJM have section 205 filing rights over Regional Transmission Expansion Planning (RTEP) unencumbered by the requirement to obtain
approval of two-thirds of the Members Committee?
X
PDF page 7
ENGIE CommentsDocket No. AD26-07-000Page 7
Questions/Comments
Yes
No
Comments:
We support permitting PJM to make section 205 filings over RTEP without the need to obtain two-thirds approval by the Members Committee. However, if approval is not needed, PJM must still bring the filing through the stakeholder process for discussion, review and an advisory vote.
14) Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a
supermajority of OPSI agrees on an alternative proposal?
X
Comments:
State participation in the PJM stakeholder process through an organization such as OPSI is vital to capturing the full scope of stakeholder interests. However, it is not necessary for states to have their own jump ball rights if the PJM stakeholders, generally have their own right. Creating a single jump ball right for all stakeholders improves the chances for a communicative and efficient stakeholder process. If states have a proposal that they would like to bring to PJM and the stakeholders it should be brought through the designated stakeholder process. It should be voted the same way as any other stakeholder proposal and put forward as a jump ball alternative to a PJM proposal upon obtaining the necessary share of stakeholder votes.
In the New England Power Pool (NEPOOL) stakeholder process, the states effectively have a jump ball right through their collaboration through the New England States Committee on Electricity (NESCOE), because NESCOE may bring a proposal through the NEPOOL stakeholder process and if it receives a sufficient percentage of votes may become a jump ball filing.
15) Should the Members Committee have “jump ball” filing rights over the portions of the tariff where PJM has 205 filing rights when a supermajority of stakeholders approves an alternative proposal?
X
Comments:
Jump ball filing rights would provide stakeholders not only with a right to have the Commission review the stakeholders’ proposal on par with PJM approval but also an effective preventative measure that would encourage increased engagement between PJM and its stakeholders.
ENGIE has experience in ISO-NE, where the ability to pursue a jump ball filing incentivizes ISO-NE to work with stakeholders to resolve their concerns with its
PDF page 8
ENGIE CommentsDocket No. AD26-07-000Page 8
proposals, and encourages stakeholders to work together to build consensus around solutions to the concerns with the ISO proposal.
Jump ball filings increase uncertainty for an ISO and encourage the ISO to strive for a stronger and more predictable negotiated outcome.
For example, although the jump ball right has been available to NEPOOL members since the creation of ISO-NE, it has been used very rarely. Instead, it has provided NEPOOL members with a useful backstop in its discussions amongst members and with ISO-NE which has led to better negotiated outcomes and increased joint proposals at FERC.
PDF page 9
ENGIE CommentsDocket No. AD26-07-000Page 9
C. Stakeholder Process
Questions/Comments
Yes
No
16) Should the approval threshold in the Members Committee be lowered from two-thirds sector-weighted voting?
X
Comments:
Two-thirds remains a reasonable threshold.
17) Should the voting rules barring affiliate votes, which apply to senior standing committees, also apply to lower-level committees?
X
Comments:
Affiliate voting should be strictly prohibited. It provides an unwarranted advantage to a disproportionately small percentage of the PJM member population. Affiliate voting may lead to increased gaming opportunities and is inherently unfair.
D. State Participation
Questions/Comments
Yes
No
18) In addition to OPSI, should there be a second state representative group consisting of governors’ representatives and/or state legislators’
representatives?
X
Comments:
As we discussed in our Pre-Technical Conference Comments, an organization to represent the governors and/or their representatives would benefit the PJM stakeholder process through organized and informed executive engagement. This organization should have the budget to hire technical and legal staff as well as outside technical and legal staff. New England’s NESCOE is an excellent example of an effective organization that engages extensively in the NEPOOL stakeholder process.
PDF page 10
ENGIE CommentsDocket No. AD26-07-000Page 10
Questions/Comments
Yes
No
19) Should state representatives have a formal voting role in the stakeholder process (limited to certain topics, such as resource adequacy and regional transmission cost allocation) in addition to the consumer advocate votes? X
Comments:
ENGIE believes that a State within the PJM footprint could coordinate its energy policy interests across its Consumer Advocate, Public Utility Commission and Governor’s Energy Policy Office to vote as part of its existing rights as a PJM Member in the End-Use Customers sector. Allowing the different departments within a State’s energy policy making apparatus to have enhanced Stakeholder input such as OPSI or a new model similar to NESCOE is addressed in Question 18.
20) Should PJM be required to consult with OPSI prior to making a section 205 filing related to resource adequacy and transmission cost allocation?
X
Comments:
Whether or not this consultation is mandated, PJM should be consulting with all of its stakeholders prior to making any section 205 filing, regardless of subject matter. While the level and frequency of engagement will depend on the complexity and impact of the filing, early and meaningful engagement with OPSI and all stakeholders is key to a successful filing at FERC.
PDF page 11
II. CONCLUSION
ENGIE appreciates the opportunity to engage with the Commission, PJM, the PJM states, and other PJM stakeholders to consider region pursues improvements to governance and the stakeholder process. We appreciate the Commission’s bias toward action, and remain optimistic that governance reforms will contribute to a more affordable, reliable, fair, and competitive PJM.
Respectfully submitted,
/s/ Sarah Bresolin Silver
Sarah Bresolin Silver
Vice President, Government and Regulatory
Affairs
Jeffrey Levine
Vice President, Government and Regulatory
Affairs
1360 Post Oak Blvd.
Houston, TX 77056
(617) 717-4535
sarah.bresolin@engie.com
jeffrey.levine@engie.com
PDF page 12
ENGIE CommentsDocket No. AD26-07-000Page 12
CERTIFICATE OF SERVICE
The undersigned certifies that a copy of this pleading has been served this day upon each person designated on the official service list compiled by the Secretary in this proceeding.
Dated at Boston, MA this 21st day of August, 2026.
/s/ Sarah Bresolin Silver
Sarah Bresolin Silver
Vice President
Government & Regulatory Affairs
ENGIE North America, Inc.
1360 Post Oak Blvd.
Houston, TX 77056
(617) 717-4535
sarah.bresolin@gmail.com