AD26-7-000 · 2026-07-02 · Persistence Analytics Group LLC
Supplemental Comments of Persistence Analytics Group LLC re PJM Governance and Stakeholder Reforms
PDF page 1
Persistence Analytics Group LLC | Supplemental Comments | FERC Docket No. AD26-7-000Public FilingNeil P. Osnato | neil@persistenceanalyticsgroup.com | 609-464-9055Page 1
UNITED STATES OF AMERICA
FEDERAL ENERGY REGULATORY COMMISSION
PJM Governance and Stakeholder Reforms
Docket No. AD26-7-000
SUPPLEMENTAL COMMENTS OF
PERSISTENCE ANALYTICS GROUP LLC
Regarding PJM Governance, Large-Load Validation, and Pre-NTP Assumption Verification These comments are submitted as public, non-confidential comments in response to the Commission-led technical conference on PJM governance and stakeholder reforms. They are intended to support concrete, actionable reforms that improve timely decision-making, transparency, accountability, and verification of operational and market assumptions before obligations harden. Submitted by:
Neil P. Osnato
Founder
Persistence Analytics Group LLC | United Grid
National Security & Infrastructure Risk Analytics
Demand Durability | Grid Stress | Load Integrity
neil@persistenceanalyticsgroup.com
609-464-9055
https://persistenceanalyticsgroup.com/
SAM.gov Registered Vendor
UEI: D3VYU39H6DX9 | CAGE: 19T34
D-U-N-S: 142849930
July 2, 2026
PDF page 2
Persistence Analytics Group LLC | Supplemental Comments | FERC Docket No. AD26-7-000Public FilingNeil P. Osnato | neil@persistenceanalyticsgroup.com | 609-464-9055Page 2
I. Introduction
Persistence Analytics Group LLC (PAG) respectfully submits these supplemental comments in Docket No. AD26-7-000 regarding PJM governance and stakeholder reforms. PAG supports the Commission's focus on concrete, actionable reforms that improve PJM's ability to address operational and market needs in a timely and efficient manner.
PAG's work focuses on national security and infrastructure risk analytics, including demand durability, grid stress, load integrity, public-cost exposure, and implementation-risk verification. The central issue addressed in these comments is whether PJM's governance and stakeholder processes can distinguish durable, decision-relevant infrastructure needs from incomplete, speculative, weakly supported, or insufficiently verified assumptions before costs, procurement, transmission planning, interconnection activity, or public obligations harden.
PJM governance reform should not be treated only as a process-design exercise. Governance determines what evidence is required, who can require it, when decisions must move, when delay becomes harmful, and who bears the downside if assumptions fail. For large loads, AI and data center development, transmission expansion, onsite generation, interconnection timing, resource adequacy, and cost allocation, the governance question is also an assumption-verification question.
II. Summary of Recommendations
1. Adopt a pre-NTP assumption-verification screen for high-impact load and infrastructure commitments. Before Notice to Proceed (NTP), PJM and relevant stakeholders should have a structured way to evaluate whether demand, power deliverability, interconnection timing, contractual support, cost allocation, and execution readiness are sufficiently verified.
2. Establish minimum evidence standards for large-load and project-readiness signals. PJM governance should identify what counts as a legitimate, actionable signal for planning and market purposes, and what remains staged, conditional, speculative, or insufficiently supported.
3. Create fast-path or time-bound review procedures for critical operational and market issues. Where delay increases reliability risk, public-cost exposure, or market uncertainty, PJM should have defined procedures to escalate, review, and resolve issues within an identified timeframe.
4. Improve transparency around assumptions, dependencies, and downside ownership. Stakeholders, states, and the public should be able to understand which assumptions drive decisions, which dependencies must hold, what evidence supports them, and who bears consequences if they fail.
5. Develop a durable-load and public-cost exposure framework. PJM should distinguish between announced load, contracted load, financially supported load, interconnection-ready load, and load that is durable enough to justify infrastructure obligations.
III. Why Pre-NTP Verification Matters
The phrase 'prior to NTP' is critical. Once a project reaches NTP, the capital stack, EPC schedule, procurement chain, utility planning assumptions, onsite generation commitments, transmission expectations, and public-cost exposure may already be moving. At that stage, decision-makers may be managing consequences rather than preventing avoidable risk.
For large-load and data center-related infrastructure, the following questions should be answered before commitments harden:
PDF page 3
Persistence Analytics Group LLC | Supplemental Comments | FERC Docket No. AD26-7-000Public FilingNeil P. Osnato | neil@persistenceanalyticsgroup.com | 609-464-9055Page 3
• Is the projected load real, staged, contingent, or speculative?
• Is the load durable enough to support the life of the infrastructure being planned or financed?
• Is the power solution a temporary bridge, a permanent requirement, or a stranded-asset risk if grid conditions change?
• What happens if grid supply catches up, interconnection constraints ease, or onsite generation loses its scarcity premium?
• Who owns downside exposure if the customer, site, revenue case, supply chain, contract, or AI/data center use case changes?
• What evidence should be required before the project counts as a legitimate planning or market signal? A governance system that cannot answer those questions before NTP risks converting uncertainty into obligations. That can expose utilities, developers, lenders, generators, suppliers, states, ratepayers, and customers to avoidable cost and reliability risk.
IV. Application to the Conference Agenda
PAG's recommendations map directly to the agenda questions for Panel 1 and Panel 2. Agenda Area
PAG Recommendation
Panel 1, Question 3: governance
reforms to improve accountability and
responsiveness
Accountability should include a named assumption owner, a
defined evidence threshold, and a documented decision path
for high-impact operational and market issues.
Panel 1, Question 6: lessons from
other RTO/ISO governance structures
Recognizing regional differences, the Commission should
encourage minimum cross-RTO evidence standards for
legitimate project and load-readiness signals, especially where
large loads affect reliability, transmission, interconnection, and
public costs.
Panel 2, Question 2: transparency
reforms
Transparency should show not only stakeholder positions, but
also the assumptions being relied upon, evidence gaps,
dependencies, timelines, and downside allocation.
Panel 2, Question 5: reforms to
ensure PJM can meet regional
challenges
PJM should adopt a structured Large-Load and Infrastructure
Assumption Verification Track for issues with material
operational, reliability, cost, or market consequences.
Panel 2, Question 8: fast-path or
time-bound review procedures
High-importance topics should have time-bound review, clear
escalation triggers, written evidence maps, and defined
outcomes that prevent endless process delay while preserving
appropriate stakeholder input.
V. Proposed Large-Load and Infrastructure Assumption Verification Track
PAG recommends that PJM adopt, or that the Commission encourage PJM to develop, a Large-Load and Infrastructure Assumption Verification Track. The purpose would be to test whether material operational and market assumptions are sufficiently supported before they trigger or influence major planning,
PDF page 4
Persistence Analytics Group LLC | Supplemental Comments | FERC Docket No. AD26-7-000Public FilingNeil P. Osnato | neil@persistenceanalyticsgroup.com | 609-464-9055Page 4
procurement, interconnection, cost-allocation, or market-design consequences. Such a track should not be anti-growth, anti-data center, anti-manufacturing, anti-generation, or anti-transmission. It should be pro-evidence. It should help good projects move with more confidence and identify weak assumptions before they create avoidable harm.
Verification Element
Core Question
Demand durability
Is the load persistent, financeable, and supported by credible
customer, contract, and use-case evidence?
Power deliverability
Can the required power be delivered on the schedule assumed, and
what constraints remain unresolved?
Interconnection and
transmission readiness
What queue, study, upgrade, permitting, equipment, or construction
dependencies must hold?
Contract and cost-allocation
strength
Who pays, who benefits, who absorbs delay, and who bears downside
if assumptions fail?
Bridge versus permanent
infrastructure
Is onsite or dedicated generation solving a temporary scarcity problem
or creating a long-lived asset exposure?
Public-cost and ratepayer
exposure
Could unverified assumptions shift costs to customers, ratepayers,
states, or other market participants?
Exit and failure scenario
If the project stalls, changes, or fails, what obligations remain and who
controls the unwind?
VI. Governance Reform Should Identify Assumption Ownership
A recurring governance failure in infrastructure decision-making is not merely that assumptions are wrong. It is that no one is clearly responsible for naming, testing, updating, or retiring them before they become embedded in planning and cost recovery. PJM reform should therefore include assumption ownership. For each high-impact operational or market decision, PJM should identify:
• the assumption being relied upon;
• the source and quality of evidence supporting it;
• the decision that depends on it;
• the timeline on which the assumption must remain true;
• the party or process responsible for updating the record if facts change;
• the consequences if the assumption proves inaccurate; and
• the trigger for reconsideration, escalation, or fast-path review.
This is particularly important where large loads, generation additions, transmission needs, and interconnection constraints are moving faster than traditional stakeholder processes can comfortably absorb.
PDF page 5
Persistence Analytics Group LLC | Supplemental Comments | FERC Docket No. AD26-7-000Public FilingNeil P. Osnato | neil@persistenceanalyticsgroup.com | 609-464-9055Page 5
VII. Transparency Should Include Evidence Quality, Not Merely Process
Participation
Transparency reforms should go beyond who voted, who objected, and what committee considered the issue. Those elements are important, but they do not reveal whether the underlying assumptions were decision-grade.
For high-impact issues, transparency should include a public or appropriately summarized evidence map that identifies: the claimed need, the supporting evidence, unresolved dependencies, cost exposure, timing risk, public impact, and the consequence of inaction or delay. Where sensitive information cannot be public, PJM should still provide a non-confidential summary sufficient to support governance accountability.
VIII. Fast-Path Review Should Be Triggered by Risk, Not Stakeholder
Convenience
The Commission's agenda asks whether PJM should increase the use of fast-path or time-bound review procedures for high-importance topics. PAG supports such reforms. Fast-path review should be available where delay itself creates material operational, reliability, market, or public-cost risk. Potential triggers include: material reliability exposure, significant public-cost or ratepayer exposure, large-load uncertainty affecting transmission or capacity planning, interconnection or equipment bottlenecks with regional consequences, major fuel or power-delivery dependencies, or evidence that stakeholder process delay is preventing timely action on an urgent operational or market issue. Fast-path review should not eliminate stakeholder input. It should structure that input around evidence, defined timelines, written assumptions, and decision accountability.
IX. Conclusion
PJM's governance challenge is not only whether its stakeholder process is inclusive or whether its Board has sufficient formal authority. It is whether the regional decision system can verify material assumptions quickly enough to prevent avoidable reliability, market, infrastructure, and public-cost consequences. The Commission should encourage reforms that make PJM faster, more accountable, and more evidence-driven. A pre-NTP assumption-verification screen, minimum evidence standards for large-load signals, transparent assumption ownership, and fast-path review for high-risk issues would improve PJM's ability to meet immediate and future challenges while preserving appropriate stakeholder participation. Markets price the headline. Infrastructure proves whether it can hold. PJM governance reform should help ensure that the assumptions behind infrastructure decisions are verified before obligations harden. Respectfully submitted,
Neil P. Osnato