Supplemental Comments of Persistence Analytics Group LLC re PJM Governance and Stakeholder Reforms
Text extracted from the eLibrary original (SHA-256 0066973e7c140703…). Download the original from the official source.
Contents · 9 sections
- I. Introduction
- II. Summary of Recommendations
- III. Why Pre-NTP Verification Matters
- IV. Application to the Conference Agenda
- V. Proposed Large-Load and Infrastructure Assumption Verification Track
- VI. Governance Reform Should Identify Assumption Ownership
- VII. Transparency Should Include Evidence Quality, Not Merely Process
- VIII. Fast-Path Review Should Be Triggered by Risk, Not Stakeholder
- IX. Conclusion
Read topic-matched comments in AD26-7
Topics in the text: Cost allocation · Reliability and curtailment
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
Persistence Analytics Group LLC | Supplemental Comments | FERC Docket No.Read this passage
I. Introduction
printed heading · Topic match: Reliability and curtailment
Governance determines what evidence is required, who can require it, when decisions must move, when delay becomes harmful, and who bears the downside if assumptions fail.Read this passage Filed comments: Reliability and curtailment
II. Summary of Recommendations
printed heading
Stakeholders, states, and the public should be able to understand which assumptions drive decisions, which dependencies must hold, what evidence supports them, and who bears consequences if they fail. 5.Read this passage
III. Why Pre-NTP Verification Matters
printed heading · Topic match: Cost allocation
That can expose utilities, developers, lenders, generators, suppliers, states, ratepayers, and customers to avoidable cost and reliability risk.Read this passage Filed comments: Cost allocation
IV. Application to the Conference Agenda
printed heading
Application to the Conference Agenda PAG's recommendations map directly to the agenda questions for Panel 1 and Panel 2.Read this passage
V. Proposed Large-Load and Infrastructure Assumption Verification Track
printed heading · Topic match: Cost allocation
Interconnection and transmission readiness What queue, study, upgrade, permitting, equipment, or construction dependencies must hold?Read this passage Filed comments: Cost allocation
VI. Governance Reform Should Identify Assumption Ownership
printed heading
For each high-impact operational or market decision, PJM should identify: • the assumption being relied upon; • the source and quality of evidence supporting it; • the decision that depends on it; • the timeline on which the assumption must remain true; • the party or process responsible for…Read this passage
VII. Transparency Should Include Evidence Quality, Not Merely Process
printed heading
Transparency Should Include Evidence Quality, Not Merely Process Participation Transparency reforms should go beyond who voted, who objected, and what committee considered the issue.Read this passage
VIII. Fast-Path Review Should Be Triggered by Risk, Not Stakeholder
printed heading · Topic match: Cost allocation
Fast-Path Review Should Be Triggered by Risk, Not Stakeholder Convenience The Commission's agenda asks whether PJM should increase the use of fast-path or time-bound review procedures for high-importance topics.Read this passage Filed comments: Cost allocation
IX. Conclusion
printed heading
Conclusion PJM's governance challenge is not only whether its stakeholder process is inclusive or whether its Board has sufficient formal authority.Read this passage