Post-Technical Conference Comments of American Electric Power Company, Inc. re the Commission’s technical conference on governance and stakeholder reforms…
Text extracted from the eLibrary original (SHA-256 e9fdd0f1eca471fa…). Download the original from the official source.
Contents · 16 sections
- I. PJM Must Swiftly Implement Solutions to Help Address Its Most Significant
- II. The Technical Conference Record Demonstrates the Need for Reform
- A. Stakeholders Agree PJM Must Act More Quickly and Decisively
- B. The Record Reflects a Need to Carefully Calibrate the Board’s and
- C. Governance Changes Must Emphasize Concrete Reforms, Not Process for
- III. PJM’s Board and Management Must Have Clear Authority to Address Reliability,
- A. PJM Must Reexamine Section 205 Filing Rights for Core Functional Matters
- B. PJM Must Convert the Stakeholder Process Into a True Advisory Model
- C. PJM Must Limit Its Ex Parte Restrictions to Improve Board Transparency,
- D. PJM Must Implement Additional Targeted Board Reforms to Improve
- E. The Commission Should Not Impose a Novel “Public Interest” Requirement
- IV. PJM Must Implement Reforms that Allow Greater State Input
- A. General Principles: Filing Rights Must Align with Legal Responsibility and
- B. PJM Should Adopt a Limited, Collective State Filing Mechanism for
- C. PJM Should Consider a “Jump-Ball” Section 205 Filing Framework
- CONCLUSION
Read topic-matched comments in AD26-7
Topics in the text: Reliability and curtailment · Cost allocation · Retail and wholesale authority
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Reliability and curtailment
As Deputy Secretary of Energy James Danly put it, the “number one priority” in governance reform must be “fix[ing] the problems that are inhibiting . . . getting as much supply online as quickly as possible, and doing so while protecting ratepayers.”5 Confronting these reliability, affordability,…Read this passage Filed comments: Reliability and curtailment
I. PJM Must Swiftly Implement Solutions to Help Address Its Most Significant
printed heading · Topic match: Reliability and curtailment
PJM Must Swiftly Implement Solutions to Help Address Its Most Significant Challenge: Getting Generation Online in Time to Meet New Load PJM’s most urgent challenge is getting needed generation online quickly enough to meet rapidly growing load.Read this passage Filed comments: Reliability and curtailment
II. The Technical Conference Record Demonstrates the Need for Reform
printed heading
Second, governance reform must navigate the genuine tension between Board independence and stakeholder participation.Read this passage
A. Stakeholders Agree PJM Must Act More Quickly and Decisively
printed heading · Topic match: Reliability and curtailment
Stakeholders Agree PJM Must Act More Quickly and Decisively Everyone, including PJM, agrees that PJM’s current governance system is not delivering fast and decisive decision-making.Read this passage Filed comments: Reliability and curtailment
B. The Record Reflects a Need to Carefully Calibrate the Board’s and
printed heading
The Record Reflects a Need to Carefully Calibrate the Board’s and Stakeholders’ Roles The technical conference confirmed that governance reform must balance two key interests: Ensuring PJM is truly independent to achieve its important objectives as an RTO while providing a meaningful opportunity…Read this passage
C. Governance Changes Must Emphasize Concrete Reforms, Not Process for
printed heading
Governance Changes Must Emphasize Concrete Reforms, Not Process for Process’s Sake The record supports focusing on reforms that solve identifiable problems: delay, lack of accountability, insufficient state involvement, unclear Board decision-making, and inadequate prioritization of urgent issues.Read this passage
III. PJM’s Board and Management Must Have Clear Authority to Address Reliability,
printed heading · Topic match: Reliability and curtailment
PJM’s Board and Management Must Have Clear Authority to Address Reliability, Affordability, Resource Adequacy, and Infrastructure Challenges; Stakeholders Must Have a Meaningful and Effective Role in Promoting the Best Outcomes PJM’s Board and management must be empowered to address the…Read this passage Filed comments: Reliability and curtailment
A. PJM Must Reexamine Section 205 Filing Rights for Core Functional Matters
printed heading · Topic match: Reliability and curtailment
PJM Must Reexamine Section 205 Filing Rights for Core Functional Matters PJM’s current division of Section 205 filing rights can impede timely action, particularly where an integrated reform requires changes to more than one governing document.Read this passage Filed comments: Reliability and curtailment
B. PJM Must Convert the Stakeholder Process Into a True Advisory Model
printed heading
PJM Must Convert the Stakeholder Process Into a True Advisory Model PJM should create an advisory stakeholder structure that provides meaningful, actionable advice to PJM management and the Board while eliminating the procedural features that too often allow stakeholders to block needed reforms.Read this passage
C. PJM Must Limit Its Ex Parte Restrictions to Improve Board Transparency,
printed heading · Topic match: Reliability and curtailment
PJM Must Limit Its Ex Parte Restrictions to Improve Board Transparency, Accessibility, and Stakeholder Engagement PJM’s broad-ranging challenges—including accelerating load growth, resource adequacy concerns, transmission expansion, interconnection reform, and rising expectations from states,…Read this passage Filed comments: Reliability and curtailment
D. PJM Must Implement Additional Targeted Board Reforms to Improve
printed heading · Topic match: Reliability and curtailment
PJM Must Implement Additional Targeted Board Reforms to Improve Expertise, Engagement, and Accountability As detailed in AEP’s pre-conference statement, PJM should adopt several additional, targeted Board reforms drawn from the practices of other RTOs and ISOs.49 Without repeating its prior…Read this passage Filed comments: Reliability and curtailment
E. The Commission Should Not Impose a Novel “Public Interest” Requirement
printed heading
Meanwhile, the public interest is already protected— 53 See id. at 11 (citing PJM Operating Agreement § 7.2; Midcontinent Indep.Read this passage
IV. PJM Must Implement Reforms that Allow Greater State Input
printed heading · Topic match: Reliability and curtailment
PJM Must Implement Reforms that Allow Greater State Input AEP supports targeted reforms to PJM’s governance framework that improve the ability of responsible entities to bring concrete, actionable proposals to the Commission under Section 205.Read this passage Filed comments: Reliability and curtailment
A. General Principles: Filing Rights Must Align with Legal Responsibility and
printed heading · Topic match: Reliability and curtailment
General Principles: Filing Rights Must Align with Legal Responsibility and Reforms Must Enable Timely Action While Preserving FERC’s Role Section 205 filing rights should rest with, or be made available to, entities that have direct responsibility for serving customers, maintaining reliability,…Read this passage Filed comments: Reliability and curtailment
B. PJM Should Adopt a Limited, Collective State Filing Mechanism for
printed heading · Topic match: Reliability and curtailment
However, any such collective state filing mechanism must be limited to proposals related to resource adequacy issues that are appropriately within states’ collective authority, and must not displace or dilute transmission owner filing rights 59 OPSI Comments at 1. 60 Silverman Statement at 2-3. 24…Read this passage Filed comments: Reliability and curtailment
C. PJM Should Consider a “Jump-Ball” Section 205 Filing Framework
printed heading · Topic match: Retail and wholesale authority
State officials specifically endorsed such a mechanism for matters within state jurisdiction.64 Any jump-ball mechanism must include clear eligibility standards, voting thresholds, issue limitations, and safeguards to avoid duplicative or strategic filings.Read this passage Filed comments: Retail and wholesale authority
CONCLUSION
printed heading · Topic match: Cost allocation
Also, each group must have accountability alongside their defined responsibility. 19) Should state representatives have a formal voting role in the stakeholder process (limited to certain topics, such as resource adequacy and regional transmission cost allocation) in addition to the consumer…Read this passage Filed comments: Cost allocation
CERTIFICATE OF SERVICE
printed heading
CERTIFICATE OF SERVICE I hereby certify that on this 21st day of August, 2026, I have served a copy of the foregoing document on the official service list compiled by the Office of the Secretary for the above-referenced proceeding. /s/ LaChon Turner LaChon Turner Paralegal American Electric Power…Read this passage