AD26-7-000 · 2026-08-21 · American Electric Power Service Corporation

Post-Technical Conference Comments of American Electric Power Company, Inc. re the Commission’s technical conference on governance and stakeholder reforms…

PDF page 1

#5144811v2
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Governance and Stakeholder Reforms
Docket No. AD26-7-000

POST-TECHNICAL CONFERENCE COMMENTS OF
AMERICAN ELECTRIC POWER COMPANY, INC.
American Electric Power Company, Inc. (“AEP”) appreciates the opportunity to provide these comments to the Federal Energy Regulatory Commission (“Commission” or “FERC”) following the Commission’s technical conference on governance and stakeholder reforms for PJM Interconnection, L.L.C. (“PJM”). These comments build on AEP’s statement filed in advance of the technical conference.1

INTRODUCTION AND SUMMARY
The Commission’s technical conference confirmed Chairman Swett’s conclusion that PJM’s “status quo is unacceptable.”2 Commissioner See framed the problem at the outset: “PJM’s unique stakeholder process and system of voting” has produced “stalemates”—not “results”—on “some of the most consequential questions PJM is grappling with,” causing everyone to “los[e] confidence[.]”3 Stakeholders echoed those observations throughout the technical conference and in pre-conference filings.

1 PJM Governance and Stakeholder Reforms, Docket No. AD26-7-000, Statement of Stacey Burbure, American Electric Power Company, Inc., Panel 1 (filed July 15, 2026) (“AEP Statement”). Unless otherwise noted, all materials cited in these comments were submitted in FERC Docket No. AD26-7-000.
2 FERC, Chairman Laura Swett’s Comments at PJM’s Annual Meeting in Baltimore, MD (May 12, 2026), https://www.ferc.gov/news-events/news/chairman-laura-swetts-comments-pjms-annual-meeting- baltimore-md-0. 3 FERC, Commission-Led Technical Conference on PJM Governance and Stakeholder Reforms at 21:16– 21:38, YOUTUBE (July 23, 2026) (“Technical Conference”) (statement of Comm’r Lindsay See), https://www.youtube.com/watch?v=OAGH1c-KENM.

PDF page 2

2
Participants broadly shared AEP’s diagnosis of PJM’s ills. There is broad recognition that PJM must act more quickly and decisively. PJM’s governance and stakeholder processes must be modernized so that responsibility, authority, and accountability are aligned to produce timely, technically sound decisions that maintain reliability, support affordability, and accelerate infrastructure development. The PJM governance process must enable economic growth, and most importantly, bring new generation online quickly to meet the generational opportunity before us.4 There is also a near-universal understanding that reform must reconcile the genuine tension between Board independence and meaningful stakeholder and state participation. And there is widespread agreement that PJM and the Commission should pursue concrete reforms that solve identifiable problems rather than focusing on process for process’s sake.

AEP’s overarching position is results-driven: Ensuring PJM customers are served reliably and affordably; developing generation and transmission according to customer-driven timelines; and supporting PJM’s ability to evaluate integrated solutions without procedural paralysis. As Deputy Secretary of Energy James Danly put it, the “number one priority” in governance reform must be “fix[ing] the problems that are inhibiting . . . getting as much supply online as quickly as possible, and doing so while protecting ratepayers.”5 Confronting these reliability, affordability, resource adequacy, and infrastructure-development challenges requires faster and more integrated decision-making. The current governance model was not designed for the speed, complexity, or scale of today’s load growth, generation and transmission development needs, and market-design challenges.

4 See, e.g., AEP Statement at 3-4.
5 Technical Conference at 46:09–46:26 (statement of Dep. Sec’y of Energy James Danly).

PDF page 3

3
The record also strongly supports AEP’s proposed solutions. First, the stakeholder process must be realigned to an advisory model that has the right people at the table, including the states, and can provide actionable support to the Board in fulfilling its role. Second, the Board must be functionally independent and capable of leading nimbly on the most difficult issues facing the region.

These comments proceed in four parts:
Part I explains why these governance reforms are inseparable from PJM’s most urgent substantive challenge: getting generation online in time to serve new load.

Part II highlights how the record from the July 23, 2026, technical conference confirms the need for governance reform in PJM.

Part III discusses how to provide PJM’s Board and management clear authority and accountability through a true advisory stakeholder model and a reexamination of Federal Power Act (“FPA”) Section 205 filing rights over core functional matters.

Part IV addresses reforms to allow greater state involvement, highlighting the need to align filing rights with legal responsibilities while preserving FERC’s role and the rights of transmission owners. AEP specifically recommends that PJM adopt a limited, collective state filing mechanism for resource adequacy issues and consider a “jump-ball” framework.

Finally, the appendix to these comments responds to the specific questions the Commission posed in its July 30, 2026, notice requesting post-conference comments.

Taken together, the AEP recommendations will modernize PJM’s governance so that responsibility, authority, and accountability are aligned to produce timely, technically sound decisions that allow PJM to address this century’s most critical challenges.

PDF page 4

4
COMMENTS
I. PJM Must Swiftly Implement Solutions to Help Address Its Most Significant
Challenge: Getting Generation Online in Time to Meet New Load
PJM’s most urgent challenge is getting needed generation online quickly enough to meet rapidly growing load. But PJM cannot solve that problem if integrated solutions are forced through a governance structure that divides responsibility across fragmented committees and distinct filing authorities. The same governance defects that prevent PJM from evaluating integrated proposals like AEP’s Accelerated Load, Infrastructure, Generation and Network Planning (“ALIGN”) concept also prevent PJM from implementing solutions to get generation online promptly. Indeed, the persistent governance problems in PJM directly contribute to its current resource adequacy challenges: while the region has long seen the current problems coming, potential solutions languished for years in deadlocked stakeholder processes. Governance reform thus is not separate from generator interconnection or resource adequacy concerns; it is the mechanism needed to move necessary reforms from concept to implemented solution.

The relevant measure of reform should be whether it helps new resources reach commercial operation in time to serve customer demand—not whether PJM has merely improved on certain governance, queue administration, or study throughput metrics. PJM’s current committee structure can take an integrated generation solution and divide it into separate pieces—separating out generator interconnection, load interconnection, transmission planning, market design, deliverability, and cost allocation—before PJM, stakeholders, or the Board can evaluate whether the package solves the underlying reliability problem. That fragmentation does not align with the integrated nature of the challenge: generation cannot meet new load unless the project, the network upgrades, deliverability, and load-service arrangements are synchronized. A committee-by-

PDF page 5

5
committee process can delay, narrow, or defeat a proposal before the merits of the integrated solution are ever considered.

Commissioner Rosner captured the interdependent nature of the region’s challenges, observing that “transmission is needed to interconnect new resources. We can have the fastest queue in the world, but if there’s not a grid to plug it in, there’s nothing we can do fast.”6 Divided Section 205 filing rights compound the problem. Even if a solution survives stakeholder review, implementation may require coordinated changes to the Tariff, Operating Agreement, Reliability Assurance Agreement, manuals, and transmission-planning protocols—creating multiple procedural gates controlled by different actors with different incentives. The practical consequence is delayed generation: when each component of an integrated proposal is subject to separate committee review and separate filing authority, PJM cannot reliably move from identifying a need to implementing a solution on the timeline necessitated by customers, states, and the system. This problem ties directly to AEP’s governance recommendations in these Comments:  An advisory stakeholder model would preserve technical input without allowing the stakeholder process to become a veto point;

 Reexamined Section 205 rights would allow reforms related to core functional matters to be brought to the Commission efficiently;

 A more meaningful role for states—with appropriate protections for transmission owners’ Section 205 rights—would ensure that decision-making authority within PJM aligns with the entities responsible for reliability, affordability, and economic development; and

6 Technical Conference at 18:43–18:54 (statement of Comm’r David Rosner).

PDF page 6

6
 A more engaged, qualified, and accountable Board would be better situated to provide dynamic leadership and ensure timely action.

Together, these reforms would give PJM the tools to act on the region’s most pressing needs. PJM should adopt a near-term action framework that coordinates generator

interconnection, transmission planning, and load-service review for projects needed to serve new demand. That framework should include clear eligibility criteria, synchronized study timelines, and Board-level accountability for whether expedited pathways are in fact producing commercial- operation results. The governance reforms AEP recommends will help achieve this objective. Without an advisory process that avoids veto-driven stalemate, clearer filing authority over core functional issues, a meaningful and defined role for states, and an informed and accountable Board—PJM will continue to identify urgent generation needs faster than it can implement the integrated solutions necessary to meet them.

II. The Technical Conference Record Demonstrates the Need for Reform
The record here demonstrates that stakeholders are broadly aligned in three key areas: First, governance reform is necessary to allow PJM to act more efficiently and effectively. Second, governance reform must navigate the genuine tension between Board independence and stakeholder participation. Third, any governance changes should be solutions-oriented, facilitating decisive action to address the region’s most significant challenges rather than focusing on process for its own sake. Although there are outer limits to what governance reform alone can accomplish to address PJM’s current ills, as Commissioner Chang put it, the simple question on the table is: “How can we help PJM make decisions more swiftly?”7

7 Technical Conference at 27:37–32:44 (statement of Comm’r Judy Chang) (“[A]s for solutions, PJM cannot do this alone. . . . I say this because I want to make clear not every problem at PJM will be fixed through changes of the governance structure. And certainly, we will talk about today the stakeholder

PDF page 7

7
A. Stakeholders Agree PJM Must Act More Quickly and Decisively
Everyone, including PJM, agrees that PJM’s current governance system is not delivering fast and decisive decision-making. PJM admitted not only that “matters of significance can stall” in its stakeholder process, but that its most consequential matters often are the ones that do.8 That is in no small part because, as PJM also conceded, the sector-weighted voting structure allows any two of five sectors to block action.9 Critical issues that have fallen victim to PJM’s process impediments range from resource adequacy and the capacity market to large load integration.10 PJM, to its credit, did not shy away from recognizing the severe consequences: In this period of rapid load growth, these governance failures can “degrade[] reliability, increase[] costs, [and reduce] investment certainty in our markets . . . .”11 Preventing such outcomes is PJM’s core responsibility, not an optional undertaking. Therefore, PJM’s conclusion that governance reform must strengthen its ability to act is table stakes.12

PJM’s Critical Issue Fast Path process on large load additions illustrates the point. Although stakeholders participated “active[ly]” and considered numerous competing reform packages, none reached the sector-weighted threshold required for member approval.13 AEP agrees

process, decision-making process . . . but these process related challenges even if we can fix it quickly, we won’t fix some of the technical and market issues. I want to set the stage and make sure that our expectation of change, we set the proper expectations for change.”).

8 Comments from PJM Interconnection, L.L.C. at 3-6 & tbl. 2 (filed July 16, 2026) (“PJM Comments”).
9 Id.
10 Id. at 3-5 & tbl. 2.
11 Id. at 5.
12 Id. at 6-7.
13 Id. at 5-6 & tbl. 4. PJM also highlighted its Reserve Certainty Senior Task Force as another example of “the process’s inability to move through a technically complex, yet important issue,” noting that the task force currently is targeting a Members Committee vote three years after it was formed, after more than forty meetings. Id. at 5.

PDF page 8

8
with PJM that stakeholders receive no trophy for “participation alone,” especially when “timely action on matters of significance” is essential to the 60+ million Americans relying on the RTO.14 State representatives and independent observers reinforced this point. Pat Wood III— former FERC and Public Utility Commission of Texas Chairman and current Executive Chairman of the Hunt Energy Network—called for a “more nimble, transparent process,” recommending that PJM transition its stakeholder process to an advisory role and establish direct channels for states to bring issues to the Board.15 State representatives from across the PJM footprint—including the Organization of PJM States, Inc. (“OPSI”); the Public Utilities Commission of Ohio’s Office of the Federal Energy Advocate; Kelsey Bagot of the Virginia State Corporation Commission; Jacob Finkel of the Office of the Governor of Pennsylvania (on behalf of the PJM Governors’ Collaborative); and Suzanne Jaworowski of the Office of the Governor of Indiana—each highlighted PJM’s failure to take timely action on critical issues and supported reforms to improve state input, strengthen Board accountability, and enhance PJM’s ability to respond to reliability and affordability concerns.16

14 Id. at 6.
15 Recommendations for PJM Governance and Stakeholder Process Reform from Pat Wood III (filed July 16, 2026) (“Wood Statement”).
16 See Pre-Conference Comments of the Organization of PJM States, Inc. at 8 (filed July 21, 2026) (“OPSI Comments”) (“[F]ar too often the PJM stakeholder process becomes a vehicle for repetition and delay . . . .”); Comments of the Public Utilities Commission of Ohio’s Office of the Federal Energy Advocate at 6 (filed July 21, 2026) (“Ohio FEA Comments”) (“[S]omething is not working if PJM’s stakeholder process is not reaching consensus or able to determine a course of action on pressing issues in a timely manner.”); Pre-Conference Comments of Kelsey A. Bagot, Chair, Virginia State Corporation Commission at 1 (filed July 21, 2026) (“Bagot Statement”) (arguing “the PJM stakeholder process has failed to drive meaningful and timely outcomes for the most critical of issues facing PJM”); Pre-Technical Conference Statement of Jacob Finkel, Office of Governor Josh Shapiro, Deputy Secretary of Policy at 10 (filed July 16, 2026) (“Finkel Statement”) (“[D]urable solutions are impossible without better alignment of authority with accountability, which means a more independent Board, a more nimble stakeholder process directed at the right type of engagement, and greater involvement from the states in PJM’s decision-making processes. Such durable solutions are needed, and needed quickly.”); Written Statement of Suzanne Jaworowski, Secretary of Energy and Natural Resources, State of Indiana Office of Governor Mike Braun

PDF page 9

9
Even market participants that resisted major structural change recognized the need for faster and more disciplined execution. For instance, Vistra urged PJM to set timelines and streamline stakeholder processes, American Municipal Power (“AMP”) called for better issue prioritization and workload management, and Constellation identified stronger and more decisive PJM leadership as the single most important reform.17 Large load interests agreed that current processes fall short, with Google criticizing PJM’s lack of visible leadership during the large-load- integration process, and the PJM Industrial Customer Coalition calling for better tools to give the Board actionable information on time-sensitive issues.18

Stakeholders disagree on much, but they reached a broad consensus here: PJM’s current governance structure fails to facilitate the effective, timely action the region needs, and it must change.

at 2 (filed July 15, 2026) (“Jaworowski Statement”) (“Sector-weighted voting has value, but the current design no longer strikes the right balance between consensus and timely action.”).

17 See Pre-Conference Statement of J. Arnold Quinn, Senior Vice President, Regulatory Policy, Vistra Corp. at 10 (filed July 15, 2026) (“Vistra Statement”) (“Significant streamlining and simplification of the PJM stakeholder process would improve both focus and speed. As it stands, the process is needlessly complex, time-consuming, and lacks clear objectives or timelines.”); Pre-Technical Conference Statement of Steven Lieberman on Behalf of American Municipal Power, Inc. at 2 (filed July 15, 2026) (“AMP Statement”) (arguing “the speed of decision-making is largely determined by PJM’s prioritization of issues and meeting schedules”); Pre-Conference Statement of Mason Emnett on Behalf of Constellation Energy Generation, LLC at 2 (filed July 16, 2026) (“Constellation Statement”) (“When PJM has delayed action, it has been because its leadership has decided not to proceed, not because of any lack of authority.”).
18 See Pre-Filed Statement of Brian D. George on Behalf of Google LLC at 3 (filed July 15, 2026) (“Google Statement”) (“It is not unreasonable to posit that with a narrowed and targeted focus, additional efforts to build consensus, including, critically, from PJM leadership, and transparency from the Board regarding their desired outcomes from the stakeholder body, and a little more time, consensus could have been achieved [on large load additions].”); Pre-Filed Statement of Susan Bruce, Counsel to PJM Industrial Customer Coalition at 6 (filed July 15, 2026) (“PJMICC Statement”).

PDF page 10

10
B. The Record Reflects a Need to Carefully Calibrate the Board’s and
Stakeholders’ Roles
The technical conference confirmed that governance reform must balance two key interests: Ensuring PJM is truly independent to achieve its important objectives as an RTO while providing a meaningful opportunity for stakeholders and states to participate in PJM decision- making processes. Several parties—including PJM, OPSI and various other state representatives, the PSEG Companies, and Google—called for greater Board authority and independence. They offered proposals ranging from expanded or unconditioned Section 205 filing rights for PJM and advisory stakeholder voting to revised Board qualifications and reforms to reduce the potential for stakeholder stalemates that can block timely filings.19 Others, meanwhile, cautioned against reforms that could diminish or limit the stakeholder process. For instance, the PJM Power Providers Group, AMP, Constellation, LS Power, Vistra, the Independent Market Monitor, and Kent Chandler—R Street Institute fellow and former Kentucky Public Service Commission Chairman—generally favored more targeted reforms focused on execution, transparency, state engagement, and workflow prioritization rather than wholesale restructuring.20 As described below, fostering functional independence for PJM and providing stakeholders a robust role are not mutually exclusive; they are mutually reinforcing. A well-functioning

19 See, e.g., PJM Comments at 6-9; OPSI Comments at 1-2; Wood Statement; Bagot Statement at 1-2; Finkel Statement at 2-7; Jaworowski Statement at 2-3; Pre-Technical Conference Comments of the PSEG Companies at 4 (filed July 15, 2026) (“PSEG Comments”); Google Statement.
20 See Pre-Conference Comments of the PJM Power Providers Group (P3) (filed July 15, 2026) (“P3 Comments”); AMP Statement; Constellation Statement at 1-2; Pre-Technical Conference Comments of Marjorie Philips, LS Power Development, LLC (filed July 16, 2026); Vistra Statement; Comments of the Independent Market Monitor for PJM at 1-3 (filed July 20, 2026) (“IMM Comments”); Technical Conference at 4:12:10–4:13:19 (American Municipal Power), 5:47:35–5:50:49 (PJM Power Providers Group), 2:07:14–2:08:37 (LS Power), and 4:54:40–4:56:18 (Kent Chandler); Submitted Statement of Kent Chandler, Senior Fellow, Energy and Environmental Policy, R Street Institute (filed July 15, 2026) (“Chandler Statement”).

PDF page 11

11
stakeholder participation model can deliver timely, transparent, and well-developed input to the Board, improving action and outcomes. The stakeholder process, however, cannot endure as a tool for a small minority of interests to block progress. This critical moment requires leadership to calibrate PJM’s governance structure to advance reforms that balance independence and stakeholder participation in a way that promotes engagement and enables solving the pressing problems facing the region.

C. Governance Changes Must Emphasize Concrete Reforms, Not Process for
Process’s Sake
The record supports focusing on reforms that solve identifiable problems: delay, lack of accountability, insufficient state involvement, unclear Board decision-making, and inadequate prioritization of urgent issues. PJM itself proposed concrete process improvements, including an additional expedited process for high-priority reliability, market, and planning issues; enforceable “time gates” for stakeholder processes; conducting more business in writing where appropriate; fewer duplicative meetings; clearer issue prioritization; and better use of technology to improve transparency and reduce repetition.21 Other participants also offered actionable reform proposals. For instance, former FERC Chairman Pat Wood III proposed an advisory stakeholder model, binding consultative authority for OPSI, and a complementary state committee, while the PSEG Companies proposed Section 205 reforms, changing voting structures or moving to an advisory stakeholder process, and Board accountability reviews.22 Other commenters supported enhanced state roles paired with greater Board independence;23 firmer Section 205 authority for the Board,

21 PJM Comments at 9-10.
22 See Wood Statement; PSEG Comments at 6-7.
23 See Finkel Statement; Jaworowski Statement at 1-2.

PDF page 12

12
informed by stakeholder input;24 a funded PJM States Committee modeled on the New England States Committee on Electricity (“NESCOE”);25 “jump-ball” filing rights and a dedicated state sector;26 or requiring the Board to provide written explanations of its decisions and better mechanisms for time-sensitive issues.27

In weighing these and other proposals, PJM and the Commission should distinguish added procedural churn from meaningful governance reform. Additional stakeholder meetings, educational sessions, or informal coordination will not be enough to address the serious shortfalls in PJM governance practices unless they are paired with results-oriented reforms, such as enforceable timelines, clear decision points, defined Board authority, and accountability for outcomes. The reforms AEP recommends are designed to meet that standard.

III. PJM’s Board and Management Must Have Clear Authority to Address Reliability, Affordability, Resource Adequacy, and Infrastructure Challenges; Stakeholders Must Have a Meaningful and Effective Role in Promoting the Best Outcomes

PJM’s Board and management must be empowered to address the reliability, affordability, and resource adequacy challenges confronting the region effectively. To do so, PJM’s governance structure must be calibrated to ensure that the Board can lead decisively and nimbly, while providing stakeholders a structure for their voices to be heard in a manner that assists the Board in achieving the best outcomes. AEP believes that (1) Section 205 filing rights for core functional matters should be reallocated; (2) PJM should shift to a purely advisory stakeholder process; and

24 See Bagot Statement at 2.
25 See Opening Statement of Abraham Silverman at 2-3 (filed July 15, 2026) (“Silverman Statement”).
26 See Overview of Potential Changes to PJM Governance, Delaware Division of the Public Advocate, Jameson Tweedie, Public Advocate for Delaware (filed July 20, 2026) (“Tweedie Comments”).
27 See PJMICC Statement at 5-6.

PDF page 13

13
(3) PJM should adopt other changes that improve the Board’s functionality and its interaction with stakeholders.

A. PJM Must Reexamine Section 205 Filing Rights for Core Functional Matters
PJM’s current division of Section 205 filing rights can impede timely action, particularly where an integrated reform requires changes to more than one governing document. In apportioning Section 205 rights, PJM and the Commission should distinguish between rights over corporate governance of the RTO and rights over core functional matters, such as energy markets, regional transmission planning, resource adequacy, and interconnection reform. The Members Committee’s Section 205 authority over core functional matters too often operates as a barrier to timely and technically sound action.28 Such authority should instead reside with the PJM Board. As PJM explained, it holds unconditioned Section 205 rights in some core areas, principally the capacity market, but its ability to file changes to the energy and ancillary services markets and to the Regional Transmission Expansion Plan process is “conditioned on Members Committee approval,” such that, absent such approval, “PJM may be required to proceed under the more restrictive requirements of section 206.”29 PJM candidly characterized this division as “in many cases[] an accident of history” and noted that its peer RTOs “do not have such conditioning of their 205 rights.”30 PJM therefore asked the Commission to consider whether PJM should have

28 See PJM Comments at 3-6; AEP Statement, App’x at 7-8. 29 PJM Comments at 6.
30 Id. at 7-8. Indeed, it is not clear whether the Commission, in approving PJM’s structure, appreciated the effects of this approach. Cf. Bangor Hydro-Electric Co., 96 FERC ¶ 61,063 at 61,259 (2001) (explaining that an independent RTO “must have the sole authority to make changes to Market Rules and any other changes it deems necessary without being required to seek approval from” a market participant committee); N.Y. Indep. Sys. Operator, Inc., 96 FERC ¶ 61,059 at 61,186-87 (2001) (rejecting NYISO’s proposal for an RTO in which decision-making would be “shared by a non-stakeholder Board of Directors and [a] stakeholder Management Committee,” with the Board having the right to make unilateral Section 205 filings only “in exigent circumstances” because an “RTO must limit the authority of committees of the type NYISO employs to an advisory role”).

PDF page 14

14
“unconditioned section 205 filing rights across all its core operational, market and transmission planning responsibilities, subject to Board oversight and informed by stakeholder engagement.”31 The problem is especially acute for provisions addressed in both the Tariff and the Operating Agreement. Energy market provisions, for example, appear in substantively identical form in both documents, so reform requires approval under both the Board’s and the Members Committee’s filing authorities.32 The practical effect is that an integrated solution like AEP’s ALIGN concept may require changes to multiple governing documents subject to distinct approval requirements33—and too often process defeats substance. AEP therefore supports reforms that allow PJM’s Board and management to advance functional reforms efficiently while preserving stakeholder input through an advisory process. Consistent with the discussion below, transmission owners must retain their appropriate rights and responsibilities under the Consolidated Transmission Owners Agreement and related governing documents.34

B. PJM Must Convert the Stakeholder Process Into a True Advisory Model
PJM should create an advisory stakeholder structure that provides meaningful, actionable advice to PJM management and the Board while eliminating the procedural features that too often allow stakeholders to block needed reforms. Today, the Members Committee approves actions and recommendations by a two-thirds sector-weighted vote.35 Because there are five sectors, any two sectors can combine to veto proposals—even where the Board needs timely advice on reliability,

31 PJM Comments at 8.
32 Compare PJM Open Access Transmission Tariff Attach. K-Appendix with PJM Operating Agreement Sched. 1. 33 AEP Statement at 5-6.
34 See infra Part IV.B.
35 PJM Operating Agreement § 8.4.

PDF page 15

15
planning, or market-design reforms.36 As AEP’s pre-conference statement explained, the two- thirds requirement applies not only to amendments to the Operating Agreement, over which the Members Committee holds Section 205 filing rights, but also to any recommendation to the Board.37 The result is that the Members Committee’s advice “is far too often no advice at all.”38 Stakeholder engagement remains essential, but stakeholder voting should not dictate outcomes when stakeholders are performing an advisory function. Peter Lake, former Senior Director of Power on the White House National Energy Dominance Council, made the point directly at the technical conference: stakeholders “need a voice in the stakeholder process, but it cannot be a veto. We must accelerate gen and load interconnect in PJM.”39 Under a true advisory model, stakeholders would retain robust opportunities to offer proposals, test alternatives, identify consensus, and create a record for Board consideration. PJM management would develop proposals after stakeholder engagement, and the Board would decide whether to proceed— weighing stakeholder input and accepting accountability for the final decision.40 Critically, the advisory structure must be flexible enough to allow subject-matter committees to evaluate discrete technical issues while also enabling integrated proposals—such as AEP’s ALIGN concept—to be considered as a whole rather than being broken up across disconnected committees.41 Moving to a purely advisory model would improve PJM’s effectiveness and speed in decision-making while strengthening—not diminishing—stakeholder

36 See AEP Statement, App’x at 2, 6; see also PJM Comments at 4-5 & tbl. 3.
37 AEP Statement, App’x at 2.
38 Id.
39 Technical Conference at 1:03:14–1:03:24 (statement of Peter Lake, Sr. Dir., White House Nat’l Energy Dominance Council).
40 See AEP Statement, App’x at 6-7.
41 See AEP Statement at 4-6 (describing ALIGN as a concept that would plan committed load, generation, and transmission as a coordinated portfolio, augmenting rather than replacing PJM’s existing processes).

PDF page 16

16
participation, by focusing on surfacing useful advice and insights and avoiding procedural stalemates. This is not a novel construct: The Midcontinent Independent System Operator (“MISO”), the Southwest Power Pool (“SPP”), and ISO New England (“ISO-NE”) each employ advisory stakeholder processes in which final authority rests with an independent board informed by robust stakeholder input.42

C. PJM Must Limit Its Ex Parte Restrictions to Improve Board Transparency,
Accessibility, and Stakeholder Engagement
PJM’s broad-ranging challenges—including accelerating load growth, resource adequacy concerns, transmission expansion, interconnection reform, and rising expectations from states, customers, and federal policymakers—require more frequent and meaningful communication between the PJM Board and affected stakeholders. The current rules restricting informal communications, however, unnecessarily limit the Board’s ability to understand the real-world implications of its governance, market, planning, and reliability decisions. They significantly constrain informal engagement between stakeholders and individual Board members outside of formal stakeholder proceedings.43 Although safeguards against improper influence are important, PJM’s current restrictions are broader than necessary and prevent the Board from hearing directly from those most affected by issues of regional significance—including reliability, transmission planning, and interconnection reform.

PJM’s approach is more restrictive than the governance practices of its peer RTOs, and no other RTO or ISO imposes such severe restrictions on Board-stakeholder communication.44

42 See MISO Transmission Owners Agreement, App’x F (“MISO Bylaws”), Art. VI § 6.1 (Advisory Committee); SPP Bylaws §§ 4.1, 5.1; ISO-NE Participants Agreement § 8.1.
43 See PJM Interconnection, L.L.C., Board of Managers Code of Conduct 3 (rev. Mar. 2026) (“Board Code of Conduct”), https://www.pjm.com/-/media/DotCom/about-pjm/who-we-are/bom-code.ashx.
44 See Christopher A. Parent et al., Governance Structure and Practices in the FERC-Jurisdictional ISOs/RTOs, Exeter Assocs., Inc. (Feb. 2021) (“NESCOE Report”) (discussing PJM’s ex parte restrictions

PDF page 17

17
MISO’s corporate-governance framework expressly contemplates that directors may communicate with stakeholders, requiring only that a director who receives an unsolicited communication on company business report its substance to the CEO and the full Board.45 SPP similarly provides stakeholders with substantial opportunities to engage with its Board through open governance processes, including Board participation in the work of SPP’s organizational groups.46 These examples show that PJM can permit direct stakeholder communication with the Board while maintaining transparency, avoiding improper influence, and preserving the integrity of Board decision-making.

The disconnect between the Board and stakeholders created by PJM’s ex parte restrictions does not fit the Board’s role. PJM is a public utility, not a regulator; its Board should be an active partner in confronting the challenges the region faces, and its policies should not foster the misimpression that the Board is providing another layer of regulator-like oversight. Direct engagement would help ensure that the Board receives a broad range of practical, operational, commercial, and policy perspectives before making decisions that will shape the region’s future. Appropriate safeguards can preserve impartiality without insulating the Board from useful stakeholder input.47

and not identifying any ex parte restrictions for other RTOs or ISOs), https://nescoe.com/wp- content/uploads/2021/02/ISO-RTOGovernanceStructureandPractices_19Feb2021.pdf.

45 See MISO, Principles of Corporate Governance § V.E (May 16, 2025), https://cdn.misoenergy.org/MISO%20Principles%20of%20Corporate%20Governance110859.pdf; NESCOE Report at 4-11 to 4-12 (describing MISO board members’ expected attendance at monthly Advisory Committee meetings and MISO’s encouragement of “additional communication between its Board and stakeholders”).
46 See SPP Bylaws § 4.1(a)-(b); NESCOE Report at ES-7 tbl. ES-5 (reflecting that SPP board meetings, agendas, minutes, and materials are open to the public).
47 AEP Statement at 8 & App’x at 12-13.

PDF page 18

18
Indeed, PJM’s ex parte rules are a product of the Board’s own Code of Conduct, which the Board’s Governance Committee can amend without Members Committee or other stakeholder approval.48 This is a step the Board can and should take immediately. AEP recommends that PJM amend its Board Code of Conduct and related governance practices to allow productive Board- stakeholder engagement, subject to appropriate transparency safeguards. Specifically, PJM should:

(1) permit direct communication between stakeholders and individual Board members, consistent with the practices of peer RTOs; (2) encourage substantive stakeholder discussions in connection with open Board or committee meetings; (3) provide summaries of significant stakeholder outreach where appropriate; (4) revise restrictions on sector meetings so that they are narrowly tailored to prevent improper ex parte influence without unnecessarily limiting productive engagement; and (5) conduct Board meetings in an open and publicly accessible manner whenever practicable, reserving executive sessions for confidential, personnel, litigation, or other legally protected matters.

48 See Board Code of Conduct at 3; PJM Interconnection, L.L.C., Board Managers: Master Charter and Committee Charters 6-7 (rev. May 2026) (explaining that the Board’s Governance Committee “shall . . . [p]eriodically review . . . the PJM Board Code of Conduct” and “[a]pprove revisions to . . . the Board Code of Conduct . . . .”), https://www.pjm.com/-/media/DotCom/about-pjm/who-we-are/board-committees- charter-2026.pdf. Because the Board Code of Conduct is not on file with the Commission, revisions do not require Commission approval. In addition to amending the Board Code of Conduct, the section of PJM Manual 34 on Board Communications also may require revisions. PJM Interconnection, L.L.C., PJM Manual 34: PJM Stakeholder Process § 15.4 (rev. 22, Sept. 25, 2025), https://www.pjm.com/- /media/DotCom/documents/manuals/m34.pdf. Changes to this manual generally require a two-thirds vote of the Members Committee. Id. § 1. However, under the terms of the Operating Agreement, PJM may assert authority to revise the relevant manual directly if stakeholder support cannot be achieved. See id. § 11.15.

PDF page 19

19
D. PJM Must Implement Additional Targeted Board Reforms to Improve
Expertise, Engagement, and Accountability
As detailed in AEP’s pre-conference statement, PJM should adopt several additional, targeted Board reforms drawn from the practices of other RTOs and ISOs.49 Without repeating its prior comments, AEP reiterates its recommendations of the following reforms to strengthen the Board’s ability to address reliability, affordability, resource adequacy, and infrastructure challenges swiftly, while preserving the Board’s independence:

1. PJM should make its President and CEO a voting member of the Board. The President and CEO is responsible for implementing Board decisions and managing PJM’s operations and therefore should be fully involved in Board decision-making. The CEOs of MISO, SPP, and NYISO already serve as voting members of their respective boards, subject to appropriate recusal limits.50

2. PJM Board meetings should be open by default. PJM’s Board meetings are not open to the public or stakeholders, leaving very little transparency into how some of the most consequential decisions are made. For example, following the Critical Issue Fast Path stakeholder process for the reliability backstop procurement, the PJM Board developed its own proposal and submitted it to FERC. Stakeholders do not know how the Board reached its final decision, what tradeoffs it made, and why certain features were selected. AEP strongly supports the Board’s decisive adoption of its own proposal following robust stakeholder input. However, future processes should be more transparent, which in turn will promote better future engagement and enhance the legitimacy of the PJM Board’s decisions. To promote transparency, the Board should provide public access to meetings not involving confidential topics (e.g., personnel, security).51

3. PJM should adopt an in-region preference for Board candidates. Given the importance of regional knowledge to reliability, affordability, and economic- development decisions, AEP recommends a preference for Board candidates who reside within the PJM footprint or have significant professional experience with the region’s electric system. Both ISO-NE and NYISO maintain such preferences.52

49 These reforms—which draw on the governance practices of other RTOs and ISOs—are addressed in detail in the AEP Statement, App’x at 9-13.

50 See AEP Statement, App’x at 9-10 (citing PJM Operating Agreement § 7.1; MISO Bylaws Art. IV § 4.1, Art. V § 5.4; SPP Bylaws § 4.2.1; NYISO Bylaws Art. III § 3(a)).
51 See Chandler Statement at 3-4.
52 See AEP Statement, App’x at 10-11 (citing ISO-NE Participants Agreement § 9.2.2; NYISO Bylaws Art. III § 2).

PDF page 20

20
4. PJM should shorten its cooling-off period for prospective Board members. Reducing the cooling-off period for Board members from two years to one would improve the pool of qualified candidates with current industry experience while maintaining Board independence. This change would be consistent with MISO’s 2017 reform and with the practices of ISO-NE and SPP, which have no cooling-off periods.53

5. PJM should limit incumbent Board control over nominations. Reducing the role incumbent Board members play in the Nominating Committee process would avoid

status-quo bias and improve accountability to PJM members. CAISO and ERCOT
provide no formal role for incumbent directors in their nomination processes.54 These reforms are targeted adjustments, not a wholesale restructuring. Each preserves Board independence while improving the Board’s expertise, information flow, accountability, and responsiveness—qualities the technical conference record shows the region urgently needs.

E. The Commission Should Not Impose a Novel “Public Interest” Requirement
Some participants have suggested that PJM’s governing documents be amended to require the Board to act in the “public interest.” This proposal, however well intentioned, misconceives PJM’s role as an RTO (not a regulator) charged with providing nondiscriminatory open access to the regional transmission system, operating the grid reliably, and administering efficient wholesale markets that serve customers at least cost.55 A generalized “public interest” obligation would run counter to the overriding goal in this proceeding of facilitating nimble and decisive Board action by creating an undefined standard that the Board would have to interpret on the front end and that could create litigation risk on the back end. Meanwhile, the public interest is already protected—

53 See id. at 11 (citing PJM Operating Agreement § 7.2; Midcontinent Indep. Sys. Operator, Inc., Docket No. ER17-686-000, Transmittal Letter at 8-9 (filed Dec. 28, 2016); ISO-NE Participants Agreement § 9.3.1; ISO-NE Code of Conduct § 2.2; SPP Bylaws § 4.2.3).
54 See id. at 12 (citing PJM Operating Agreement § 7.1; CAISO Board Selection Policy § 4.2; Tex. Utils. Code § 39.1513(a), (d)).
55 See 18 C.F.R. § 35.34(j)-(k) (prescribing an RTO’s minimum characteristics and functions); Reg’l Transmission Orgs., Order No. 2000, FERC Stats. & Regs. ¶ 31,089 (1999), order on reh’g, Order No. 2000-A, FERC Stats. & Regs. ¶ 31,092 (2000).

PDF page 21

21
the FPA obliges the Commission to ensure that RTO rates are just, reasonable, and nondiscriminatory.

IV. PJM Must Implement Reforms that Allow Greater State Input
AEP supports targeted reforms to PJM’s governance framework that improve the ability of responsible entities to bring concrete, actionable proposals to the Commission under Section 205. Any expansion of filing rights should be balanced and carefully defined—preserving the existing Section 205 rights of transmission owners while recognizing the central and evolving role of states in resource adequacy, affordability, economic development, and public policy matters. The Commission should encourage governance reforms that promote timely action, transparency, and accountability without undermining the legal responsibilities and investment obligations of transmission owners.

A. General Principles: Filing Rights Must Align with Legal Responsibility and Reforms Must Enable Timely Action While Preserving FERC’s Role

Section 205 filing rights should rest with, or be made available to, entities that have direct responsibility for serving customers, maintaining reliability, making long-term infrastructure investments, and implementing public policy requirements. PJM’s current governance framework—including the allocation of Section 205 rights—was developed in a different operating environment, one characterized by slower load growth, surplus generation, and incremental infrastructure needs.56 As that operating environment has changed, PJM’s governance must be updated to align filing authority with legal responsibility regarding today’s reliability, resource adequacy, transmission-expansion, and affordability challenges.

56 See PJM Comments at 2-3, 7; AEP Statement at 9.

PDF page 22

22
As states bear increasing responsibility for resource adequacy policy, economic development strategy, transmission siting, and customer affordability, they should have a defined mechanism to advance regional tariff reforms within their collective jurisdiction. OPSI explained the point forcefully: state officials “remain accountable for outcomes they have little power to formally shape,” and need “a more formal means of presenting their proposals to the Commission on a level playing field with PJM and the [transmission owners].”57 At the same time, transmission owners must retain meaningful filing rights, because they remain responsible for owning, operating, maintaining, and investing in jurisdictional transmission facilities and for complying with applicable FERC and reliability obligations.

Another important reform principle is that PJM’s governance should not require unanimity or extended stakeholder deadlock before needed reliability, market, or transmission reforms can move forward. Expanding access to Section 205 filing mechanisms can provide a constructive path to facilitate innovative solutions while preserving the Commission’s role as the independent regulator charged with determining whether a proposal is just and reasonable. As PJM emphasized, even where a proposal is filed under Section 205, “stakeholders, of course, may continue to provide feedback or challenge the proposal before the Commission,” which “is ultimately responsible for determining whether a proposed Tariff change is just and reasonable.”58 A reformed filing-rights framework should improve transparency by making disagreements visible to the Commission and allowing proposals to be tested in an open record. The ultimate objective should be a governance

57 OPSI Comments at 1-2; see also Finkel Statement at 1 (describing a “fundamental gap” between those accountable for reliability and affordability—the states and the Board—and the private Members with authority over many of the solutions).

58 PJM Comments at 7.

PDF page 23

23
structure that empowers responsible entities to act, encourages collaboration, and gives the Commission a clear record on which to resolve competing proposals.

B. PJM Should Adopt a Limited, Collective State Filing Mechanism for
Resource Adequacy Issues While Preserving Transmission Owners’ Section
205 Rights
AEP supports providing states with a defined and limited ability to initiate Section 205 filings on matters within their collective jurisdiction—namely, resource adequacy. That authority should be exercised through an established regional process, such as OPSI or another collectively governed state body, rather than through unilateral filings by individual states. A collective mechanism would recognize the important role states play in protecting consumers and advancing policy objectives while reducing the risk of fragmented or conflicting individual state filings. Several participants advanced complementary versions of this idea. For instance, OPSI proposed that, where its members agree on resource adequacy or transmission cost allocation reforms, PJM or the transmission owners should be required to provide that solution to FERC “in a way that FERC can accept it.”59 And Abraham Silverman, research scholar at Johns Hopkins University and principal at SilverGreen Energy Consulting, proposed a funded PJM States Committee, modeled on NESCOE, with co-filing rights over at least the resource adequacy portions of the PJM Tariff.60

AEP believes a collective state filing mechanism could provide significant value as PJM works to address novel resource adequacy challenges. However, any such collective state filing mechanism must be limited to proposals related to resource adequacy issues that are appropriately within states’ collective authority, and must not displace or dilute transmission owner filing rights

59 OPSI Comments at 1.
60 Silverman Statement at 2-3.

PDF page 24

24
over transmission rates, planning responsibilities, cost allocation, or the facilities transmission owners own and operate.

Transmission owners must retain their existing Section 205 rights over matters affecting transmission rates, revenue requirements, cost allocation, planning responsibilities, transmission owner agreements, and the facilities they own and operate.61 These rights are not merely procedural; they are essential to enabling transmission owners to fulfill their obligations to maintain reliability, invest in the transmission system, comply with FERC and NERC requirements, and protect customers. As the Commission made clear in Order No. 2000, “a transmission owner must have independent authority to set the level of its portion of the revenue requirement to be collected by the RTO.”62 Governance reform must not shift authority away from the entities that bear the legal, operational, and financial responsibility for transmission service and system performance. Preserving transmission owner filing rights also ensures that the Commission receives fully developed alternatives when PJM’s stakeholder processes fail to yield timely or adequate reforms.

C. PJM Should Consider a “Jump-Ball” Section 205 Filing Framework
The Commission should encourage PJM and its stakeholders to consider a “jump-ball” filing framework that allows competing Section 205 proposals to be presented to the Commission in appropriate circumstances. Such a framework could apply when PJM, the transmission owners, or a supermajority of states advance competing proposals on issues implicating their respective responsibilities and stakeholder consensus cannot be reached. A jump-ball process follows an

61 See PJM Open Access Transmission Tariff § 9.1 (reserving to Transmission Owners the “exclusive and unilateral” right to file changes relating to the establishment and recovery of their transmission revenue requirements and transmission rate design).
62 Order No. 2000, FERC Stats. & Regs. ¶ 31,089 at 31,076.

PDF page 25

25
established model: ISO-NE’s governing documents already allow a New England Power Pool (“NEPOOL”)-supported alternative to be filed alongside the ISO’s own proposal, with the Commission free to adopt either proposal that it finds just and reasonable.63

A jump-ball approach would allow the Commission to evaluate competing just-and-
reasonable proposals in a single proceeding, rather than forcing stakeholders through a more burdensome Section 206 complaint process. It would promote efficiency—instead of protracted debates at PJM about which specific proposal should be presented to the Commission, multiple competing proposals could be developed in parallel. It also would improve accountability and encourage negotiation, because parties would know that the Commission may evaluate an alternative proposal on the merits. State officials specifically endorsed such a mechanism for matters within state jurisdiction.64 Any jump-ball mechanism must include clear eligibility standards, voting thresholds, issue limitations, and safeguards to avoid duplicative or strategic filings.

CONCLUSION
PJM’s stakeholders—from transmission owners and generators to states and consumer advocates—are committed to serving customers across the region reliably and at just and reasonable rates. But too often, PJM’s governance structure has inhibited, rather than facilitated, that essential work. The technical conference record confirms the need for reform and points the way toward concrete solutions. PJM should adopt the reforms described above: a true advisory

63 See ISO-NE Participants Agreement § 11.1.5 (providing that, where the Participants Committee approves an alternative Market Rule proposal by at least 60% of the aggregate sector voting shares, ISO-NE must describe that alternative in its Section 205 filing and the Commission “may adopt any or all” of either proposal as it finds “just and reasonable and preferable”).
64 See Bagot Statement at 2 (describing longstanding state advocacy for “jump-ball” Section 205 rights over resource adequacy and transmission cost allocation); Tweedie Comments at 1-2 (proposing that, upon supermajority support of a state committee, PJM file the states’ proposal as an alternate “jump-ball” filing).

PDF page 26

26
stakeholder model; a reexamination of Section 205 filing rights over core functional matters; a limited, collective state filing mechanism that preserves transmission owners’ rights; consideration of a “jump-ball” mechanism; and targeted reforms to improve Board transparency, accessibility, expertise, and accountability. These reforms would align legal responsibility, authority, and accountability so that PJM can make the timely, technically sound decisions the region urgently requires and implement a near-term action framework that will bring generation online in time to serve new load.

Respectfully submitted,

/s/ John C. Crespo

John C. Crespo
Senior Legal Counsel
American Electric Power Service Corporation
1 Riverside Plaza
Columbus, OH 43215
Telephone: (614) 716-3727
E-mail: jccrespo@aep.com
August 21, 2026

PDF page 27

27
Appendix
PJM Governance and Stakeholder Reforms – Docket No. AD26-7-000
AEP Responses to Post Technical Conference Questions

PJM Board Independence

Questions/Comments
Yes
No
1) Should Board members’ terms be extended to five or more years?
Yes

Comments: AEP supports a term for Board members up to and including 5 years, with a limit of no more than two consecutive terms.  This term change should be implemented only if the broader reforms also establish clear Board qualification requirements and a residency preference to ensure the Board has the appropriate experience, expertise, and regional representation.

2) Should there be a maximum number of years that a Board member may serve (e.g., 10 years)?

No

Comments: An arbitrary maximum number of years of service is not needed, subject to the limitation that a Board member should serve no more than ten years consecutively (i.e., two consecutive 5-year terms).

3) Should the Board member qualification rules be revised to provide a preference for some Board members that reside in the PJM region?

Yes

Comments: Yes, there should be a preference for Board members to have both permanent residence in the PJM region and meaningful professional experience related to PJM, ensuring that residency reflects substantive knowledge and experience with the region rather than simply maintaining an apartment or other place of residence.

4) Should the conflict-of-interest rules be revised to reduce the cooling off period for Board members from two years to one year?

Yes

Comments: Yes, the conflict-of-interest rules have likely prevented PJM from attracting qualified candidates. Reducing the cooling off period for Board members from two years to one year could help broaden the pool of qualified, potential PJM Board candidates.

5) Should restrictions on Board communications be relaxed to enable more communication between the Board and stakeholders?

Yes

Comments: Yes, AEP recommends permitting direct communication between stakeholders and individual Board members consistent with the governance practices employed by peer RTOs.

PDF page 28

28

Questions/Comments
Yes
No
6) In order to increase transparency, should Board votes be made public or the Board be required to explain its reasoning?

Yes

Comments: Board meetings and Board votes should be public to promote transparency and accountability. When the Board departs from or rejects the recommendations of the stakeholder process, it should publicly explain the rationale for its decision.

7) In order to increase transparency, should some Board meetings be open or available to the public?

Yes

Comments:  Yes, AEP recommends conducting Board meetings in an open and publicly accessible manner whenever practicable, with only limited executive sessions for matters involving confidential, personnel, litigation, or other legally protected information.

8) Should PJM’s governing documents be revised to explicitly state that the responsibility of PJM and its Board is to serve the public interest?

No

Comments: AEP would not support adding a broad, standalone requirement to PJM’s governing documents that PJM and its Board must serve the “public interest.” While AEP recognizes the importance of considering broader public interests in PJM’s decision-making, the term can be subjective and could create uncertainty or additional complexity in Board deliberations. AEP believes PJM’s existing mission and governance framework, together with FERC’s established oversight, provide an appropriate basis for balancing reliability, affordability, and the diverse interests of PJM stakeholders.

9) Should state representatives have at least one voting member on the Nominating Committee?

Yes

Comments: Yes, state representatives should have at least one voting member on the Nominating Committee.

10) Should PJM adopt public performance metrics and tie management
compensation to their achievement?
Yes

Comments: Yes, the Board should undertake a process of identifying measurable goals for PJM leadership. The goals should be implemented and made public prior to each new year.

PDF page 29

29
Section 205 Filing Rights

Questions/Comments
Yes
No
11) Should the stakeholder process be advisory, i.e., stakeholder votes only inform the Board?

Yes

Comments: Yes, the stakeholder process should be advisory and inform, rather than direct, the Board. The process should provide the Board with the benefit of diverse stakeholder perspectives, technical expertise, and thoughtful analysis while preserving the Board’s responsibility to exercise independent judgment. The Board should carefully consider stakeholder recommendations but retain the authority to make decisions in the best interests of PJM’s reliability, affordability, and overall effectiveness. Where the Board reaches a different conclusion from the stakeholder process, it should provide a clear explanation of the rationale for its decision.

12) Should PJM have section 205 filing rights over the energy market and ancillary services unencumbered by the requirement to obtain approval of two-thirds of the Members Committee?

Yes

Comments: Yes, PJM should have Section 205 filing rights over core functional matters such as energy and ancillaries markets, regional transmission planning, resource adequacy, and interconnection reform.

13) Should PJM have section 205 filing rights over Regional Transmission Expansion Planning (RTEP) unencumbered by the requirement to

obtain approval of two-thirds of the Members Committee?
Yes

Comments:  Yes, PJM should have 205 filings rights over regional transmission planning. Providing PJM with appropriate filing authority would allow the organization to more effectively implement regional planning reforms and respond to evolving reliability and system needs. This authority should be paired with appropriate stakeholder input and Board oversight, while preserving FERC’s ultimate authority to review and approve proposed changes.

14) Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal?

Yes

Comments: Yes, AEP supports a limited “jump ball” framework for resource adequacy filings where there is broad state consensus. Such a framework could promote collaboration, strengthen state and stakeholder engagement, and allow FERC to evaluate competing proposals in a single proceeding under the just and reasonable standard. However, any such right should be subject to clear safeguards. It should be available only where the alternative proposal reflects support from a supermajority of PJM states (10 or greater states), not merely a narrow supermajority, and it should not be used to

PDF page 30

30

Questions/Comments
Yes
No
shift the costs of one state’s public policy choices to neighboring states.  For example, in 2020/21, only 11 PJM states had a renewable or clean energy standard, raising the problem of cost shifts to states without those standards from public policy projects.

15) Should the Members Committee have “jump ball” filing rights over the portions of the tariff where PJM has 205 filing rights when a

supermajority of stakeholders approves an alternative proposal?
Yes

Comments: Yes, PJM should evaluate adopting a “jump ball” filing process similar to other regional transmission organizations. When PJM, Transmission Owners, or a supermajority of states disagree on a proposed tariff revision, FERC should have the opportunity to evaluate competing Section 205 proposals in a single proceeding. A jump ball framework promotes collaboration, strengthens stakeholder engagement, and allows FERC to select the proposal that best satisfies the just and reasonable standard.

Stakeholder Process

Questions/Comments
Yes
No
16) Should the approval threshold in the Members Committee be lowered from two-thirds sector-weighted voting?

Yes

Comments: AEP’s preferred approach is for the stakeholder process to be advisory over matters where PJM has 205 filing rights.  As noted above, PJM’s filing rights should be expanded to include core functional matters.  The Members Committee’s authority over corporate governance of the RTO should be distinguished from rights over core functional matters.  The Members Committee may retain its existing two-thirds sector- weighted voting for corporate governance matters.

17) Should the voting rules barring affiliate votes, which apply to senior standing committees, also apply to lower-level committees?

Yes

Comments: AEP’s preferred approach is for the stakeholder process to be advisory.

PDF page 31

31
State Participation

Questions/Comments
Yes No
18) In addition to OPSI, should there be a second state representative group consisting of governors’ representatives and/or state legislators’

representatives?
Yes

Comments: Yes, there could be a second state representative group. However, each group must have well-defined roles, responsibilities and membership. Also, each group must have accountability alongside their defined responsibility.

19) Should state representatives have a formal voting role in the stakeholder process (limited to certain topics, such as resource adequacy and regional transmission cost allocation) in addition to the consumer advocate votes? Yes

Comments: Yes, provided that the stakeholder process is advisory. Any new state role should be well-defined and rights and responsibilities should align with accountability.

20) Should PJM be required to consult with OPSI prior to making a section 205 filing related to resource adequacy and transmission cost allocation? Yes

Comments: Yes. AEP supports a formal consultation right for the states with respect to Section 205 filings on matters within state jurisdiction, with the exception of certain transmission cost allocation issues. The consultation process should provide states with a meaningful opportunity to review and provide input before a filing is submitted, while preserving the Board’s ability to act within appropriate timelines.

PJM Transmission Owners already have Section 205 filing rights, and any state consultation process should recognize and preserve those existing rights. Consultation with OPSI should also occur today as a matter of course on matters affecting state interests and does not require a change to PJM’s governing documents. More broadly, the process should apply to whatever entity or body is ultimately established to represent the collective interests of the states before PJM, whether that remains OPSI or is replaced by a new state body.

The consultation process should be clearly defined and structured to promote transparency and meaningful state input without creating unnecessary delays or ambiguity regarding filing authority.

PDF page 32

CERTIFICATE OF SERVICE

I hereby certify that on this 21st day of August, 2026, I have served a copy of the foregoing document on the official service list compiled by the Office of the Secretary for the above-referenced proceeding.

/s/ LaChon Turner
LaChon Turner
Paralegal
American Electric Power Service Corporation
801 Pennsylvania Ave NW
Suite 735
Washington, DC 20004
(202) 383-3465
lturner@aep.com