Post-Conference Comments of CTC Global Corporation re PJM Governance and Stakeholder Reforms
PDF page 1
1
UNITED STATES OF AMERICA
Before The
FEDERAL ENERGY REGULATORY COMMISSION
PJM Governance and Stakeholder Reforms
)
)
)
Docket No. AD26-7-000
POST-CONFERENCE COMMENTS OF CTC GLOBAL
CTC Global Corporation (“CTC”)1 respectfully submits these comments in response to the
Federal Energy Regulatory Commission’s (“Commission” or “FERC”) Notice Requesting Post-
Technical Conference Comments concerning PJM Interconnection, L.L.C.’s (“PJM”) governance
and stakeholder processes.
I. Comments
CTC agrees that governance structure, Board independence, stakeholder participation,
transparency, and clearly allocated decision-making authority are important. But governance reform should ultimately be judged by results: whether PJM is better able to identify urgent system needs, evaluate available solutions, make decisions, and implement those decisions on timelines responsive to the reliability and affordability challenges facing the region.
One of the clearest tests of effective governance is PJM’s ability to respond to the rapidly increasing need for transmission capability. PJM faces extraordinary electricity demand growth
1 CTC Global Corporation (“CTC”) is a U.S.-based manufacturer and technology company headquartered in Irvine, California, and the inventor and global leader in advanced transmission conductors. CTC manufactures the carbon composite core used in ACCC® Conductors, which have been deployed by utilities around the world in 70 countries to increase transmission capacity, reduce electrical losses, mitigate conductor sag, and make greater use of existing transmission rights-of-way and structures. With 140,000 miles deployed over the last two decades, CTC’s technologies are designed to help utilities add meaningful grid capacity on timelines substantially shorter than those typically required for new transmission development, while providing significant cost saving benefits like shorter tower height and longer spans on new greenfield projects and line rebuilds. CTC is also advancing real-time transmission-system monitoring through GridVista®, which incorporates live, always-on, fiber-optic sensing within the conductor system to provide operators with detailed information regarding line temperature, mechanical conditions, and other operating characteristics and conditions such as ice or wind load, line contacts, damage, or near line events like lightning strikes or wildfires. Through these technologies, CTC works at the intersection of transmission planning, grid modernization, and the rapid deployment of additional electric system capacity.
PDF page 2
2
while new generation, large loads, and existing customers increasingly depend on a transmission system that takes too long to expand. PJM itself has projected approximately 30 GW of load growth between 2025 and 2030 and substantial additional growth thereafter, adding 70 GW over 15 years.2 Governance reforms that increase the speed and quality of PJM decision-making can therefore make an important contribution to reliability and affordability if they enable PJM to gain more capability from the transmission system sooner.
A. Governance Reform Should Be Evaluated by Whether It Enables PJM to Address
Urgent Reliability, Affordability, and Transmission Needs
Many of the challenges currently confronting PJM—resource adequacy, generation interconnection, large-load integration, affordability, and reliability—are closely linked to the availability of sufficient transmission capability. New generation cannot reliably serve customers if the transmission system cannot accommodate and deliver its output. Likewise, even well- designed energy and capacity markets cannot function, much less produce their full benefits, if inadequate transmission prevents resources from responding to market signals. Although PJM and the PJM Board have taken steps to increase generation, neither has taken significant steps to either accelerate transmission development or hasten transmission capacity increases by upgrading existing infrastructure in existing rights-of-ways.
While PJM needs to significantly increase the region’s transmission development, not every transmission need requires a new transmission corridor. A central part of meeting PJM’s near-term challenge should be to establish timely mechanisms to evaluate the full range of technically mature solutions that can maximize the capability of infrastructure already in service and of existing transmission rights-of-way. Mature, widely deployed advanced transmission
2 PJM Inside Lines: 2025 Year in Review: Planning Prepares for Burgeoning Electricity Demand https://insidelines.pjm.com/2025-year-in-review-planning-prepares-for-burgeoning-electricity-demand/
PDF page 3
3
technologies can increase capacity much faster than conventional greenfield development, as well as reduce the costs of new greenfield transmission while also increasing efficiency by reducing line losses.
Advanced reconductoring is an important example. Carbon composite core advanced conductors can substantially increase the capacity of existing transmission corridors while reducing electrical resistance and conductor sag. In many applications, reconductoring can use existing structures and existing rights-of-way to double the amount of electricity that can move on the line while reducing system losses by up-to 40%. Reconductoring, which can be done with live lines, can be implemented on timelines materially shorter than construction of new greenfield transmission. These attributes are particularly important where the system is in critical need of significant additional capability within the next few years rather than the next decade. These same attributes enabled by the carbon core of advanced conductors, allow for shorter towers and longer spans (fewer towers) on both line rebuilds and new transmission lines, reducing siting risk and project costs while improving the performance capabilities of the line.
The governance question for the Commission is therefore not whether PJM should select any particular technology. It is whether PJM’s governing structures and stakeholder processes permit the organization to identify urgent needs, evaluate the full range of technically mature solutions, and reach timely decisions based upon capacity, reliability, cost and deployment time. With these measures, PJM will be able to move resolutely past its current resource adequacy and governance crisis.
B. PJM Should Establish Time-Bound Processes for Critical System Needs and Ensure Mature Transmission Technologies Receive Timely, Technically Sound Evaluation The Commission specifically asked whether PJM should make greater use of fast-path or time-bound procedures for matters of high importance. CTC believes it should. For designated
PDF page 4
4
critical reliability, transmission-capacity, or load-growth issues, PJM should establish a process containing, at a minimum:
1. Clearly defined system need and planning criteria that recognize that the speed at which new transmission capacity can come online is a critical component for both reliability and consumer costs;
2. A defined, reasonably expedited timetable for technical analysis and stakeholder input;
3. Technology-inclusive, performance-based evaluation of mature alternatives that is not skewed towards legacy technologies;
4. Transparent assumptions and changes to modeling sufficient to permit meaningful comparison of alternatives;
5. Fixed and transparent decision date identified early in the process and adhered to; and
6. Clearly identified decision authority if the stakeholder process does not produce consensus within the prescribed period.
The objective should not be to circumvent stakeholder participation. It should be to prevent stakeholder process from becoming an indefinite substitute for decision-making. For transmission needs in particular, PJM’s analysis should be capable of comparing alternatives based not simply on initial capital cost, but on the amount of capacity delivered, time to deployment, lifecycle cost, electrical losses, reliability performance, constructability, use of existing structures and rights-of-way, and siting requirements. Governance procedures should also ensure that PJM has access to the models and technical information necessary to accurately represent mature transmission technologies like carbon composite core advanced conductors.
This is especially important for technologies that can materially increase the capability of existing infrastructure. PJM should have governance and planning processes that allow advanced conductors to be evaluated quickly and on comparable technical and economic terms when they may provide a faster or less costly solution.
PDF page 5
5
The Commission’s agenda specifically identified fast-path and time-bound review procedures for critical issues as a potential governance reform. Such a process would directly advance the objectives identified by the Commission in this proceeding: improving PJM’s responsiveness, transparency and ability to take necessary action in a timely manner. Other stakeholders raised, in their pre-technical conference comments, the need for greater oversight of PJM’s transmission planning. Some asked that PJM consider an Independent Transmission Monitor.3 Others asked that PJM implement tariff reforms that would require the immediate evaluation of alternative transmission technologies to maximize existing transmission system capacity.4 CTC broadly supports emphasizing the critical role of new technologies, including advanced conductors, in PJM governance, including the stakeholder process and before the PJM Board. The actions necessary to rapidly increase PJM’s transmission capacity to meet its burgeoning need will not occur without greater inclusion of advanced transmission technologies in the solution.
C. The PJM Board's Collective Qualifications Should Include Transmission Planning, Grid Operations, and Technology Deployment Expertise
CTC also believes that PJM’s Board qualification criteria should reflect the extraordinary operational and infrastructure challenges now facing the region. This does not require every Board member to possess the same technical background, nor should it diminish the importance of Board independence. Rather, the Board should possess a mix of competencies sufficient to oversee one of the largest and most complex electric systems in the world.
3 Commissioner Led Technical Conference on PJM Governance and Stakeholder Reform, Comments of the PJM Cities and Communities Coalition at 16, Docket No. AD26-7-000 (filed July 22, 2026).4 Commissioner Led Technical Conference on PJM Governance and Stakeholder Reform, Comments of the PJM Legislators’ Collaborative at 31, 41 Docket No. AD26-7-000 (filed July 23, 2026).
PDF page 6
6
That competency matrix should expressly include meaningful experience in areas such as bulk-power-system operations, regional transmission planning, transmission development, utility regulation, and deployment of commercially mature grid technologies. These skills are particularly important in an environment where decisions involving transmission capability, resource adequacy, large-load growth, and technology deployment can have multibillion-dollar consequences for customers.
The Board should also receive regular, transparent reporting on PJM’s performance in addressing critical system needs. Relevant metrics could include the time between identification of a system need and a planning decision; the alternatives evaluated; anticipated capacity provided; projected cost; expected in-service date; and progress toward implementation. This would connect governance reform to measurable outcomes rather than treating governance structure as an end.
II. Conclusion
CTC supports reforms that make PJM more independent, responsive, transparent and capable of timely action. The ultimate measure of those reforms should be whether they improve PJM’s ability to solve the operational and market challenges confronting the region. PJM faces a period in which electricity demand and transmission needs are growing much faster than traditional infrastructure-development timelines can comfortably accommodate. Governance reform should therefore empower PJM to identify urgent needs, evaluate the full range of mature solutions, make timely decisions, and hold itself accountable for implementation. For transmission, that means not only planning new infrastructure where it is required but also maximizing the capability of the infrastructure already in place. Mature, advanced transmission technologies—including advanced conductors capable of substantially increasing capacity within existing transmission corridors—can be an important part of that effort. A
PDF page 7
7
governance structure capable of identifying, evaluating and acting on those opportunities promptly will better serve reliability, affordability and the customers that depend upon the PJM system.
Respectfully submitted,
/s/ Theodore J. Paradise
Theodore J. Paradise
Chief Policy and Grid Strategy Officer
Paige Rodrigues
Senior Manager, Policy and Grid Strategy
prodrigues@ctcglobal.com
Dated: August 21, 2026