Post-Conference Comments of CTC Global Corporation re PJM Governance and Stakeholder Reforms
Text extracted from the eLibrary original (SHA-256 aab9e67137486901…). Download the original from the official source.
Contents · 5 sections
Read topic-matched comments in AD26-7
Topics in the text: Reliability and curtailment
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
1 UNITED STATES OF AMERICA Before The FEDERAL ENERGY REGULATORY COMMISSION PJM Governance and Stakeholder Reforms ) ) ) Docket No.Read this passage
I. Comments
printed heading
Comments CTC agrees that governance structure, Board independence, stakeholder participation, transparency, and clearly allocated decision-making authority are important.Read this passage
A. Governance Reform Should Be Evaluated by Whether It Enables PJM to Address
printed heading · Topic match: Reliability and curtailment
Governance Reform Should Be Evaluated by Whether It Enables PJM to Address Urgent Reliability, Affordability, and Transmission Needs Many of the challenges currently confronting PJM—resource adequacy, generation interconnection, large-load integration, affordability, and reliability—are closely…Read this passage Filed comments: Reliability and curtailment
B. PJM Should Establish Time-Bound Processes for Critical System Needs and Ensure
printed heading
PJM Should Establish Time-Bound Processes for Critical System Needs and Ensure Mature Transmission Technologies Receive Timely, Technically Sound Evaluation The Commission specifically asked whether PJM should make greater use of fast-path or time-bound procedures for matters of high importance.Read this passage
C. The PJM Board's Collective Qualifications Should Include Transmission Planning,
printed heading
These skills are particularly important in an environment where decisions involving transmission capability, resource adequacy, large-load growth, and technology deployment can have multibillion-dollar consequences for customers.Read this passage
II. Conclusion
printed heading
Conclusion CTC supports reforms that make PJM more independent, responsive, transparent and capable of timely action.Read this passage