AD26-7-000 · 2026-08-21 · FirstEnergy Service Company

Comments of FirstEnergy Service Company re PJM Governance and Stakeholder Reforms

Text extracted from the eLibrary original (SHA-256 463437c19289bcb0…). Download the original from the official source.

Contents · 12 sections
  1. I. INTRODUCTION p. 1
  2. II. RESOURCE ADEQUACY AND INADEQUATE CAPACITY ARE THE p. 2
  3. A. The Current Resource Adequacy Challenge in the PJM Footprint Is Not p. 2
  4. B. PJM Governance Reform Will Not Solve the Missing Megawatt Problem. p. 3
  5. C. PJM’s Diverse Footprint is Distinct from Neighboring RTOs/ISOs and p. 4
  6. III. THE COST OF ADDRESSING THE RESOURCE ADEQUACY p. 5
  7. A. Existing Customers Are Bearing the Costs of the Growing Resource p. 5
  8. B. New Large Load Customers Should Be Required to Bring the Generation p. 6
  9. C. Generation Procured for Native Load Growth Should Flow Through a p. 6
  10. D. FirstEnergy Supports Resource Adequacy Solutions that Assign Costs to p. 7
  11. IV. GOVERNANCE REFORMS SHOULD BE LIMITED TO REFORMS p. 8
  12. V. CONCLUSION p. 10

Read topic-matched comments in AD26-7

Topics in the text: Reliability and curtailment · Cost allocation · Registry access

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

1 UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION ) ) PJM Governance and Stakeholder Reforms ) Docket No.
Read this passage

I. INTRODUCTION

printed heading · Topic match: Reliability and curtailment

The central problem in the PJM region is not governance itself; it is a shortage of generation needed to ensure resource adequacy.
Read this passage Filed comments: Reliability and curtailment

II. RESOURCE ADEQUACY AND INADEQUATE CAPACITY ARE THE

printed heading · Topic match: Reliability and curtailment

RESOURCE ADEQUACY AND INADEQUATE CAPACITY ARE THE CENTRAL CHALLENGE
Read this passage Filed comments: Reliability and curtailment

A. The Current Resource Adequacy Challenge in the PJM Footprint Is Not

printed heading · Topic match: Reliability and curtailment

As the Commission and industry have recognized, electric load demand is outpacing supply at an unprecedented rate due to the rise in new large loads interconnection requests.4 Further compounding the challenge is the premature retirement of existing generation and the delayed rate of entry of new…
Read this passage Filed comments: Reliability and curtailment

B. PJM Governance Reform Will Not Solve the Missing Megawatt Problem.

printed heading · Topic match: Reliability and curtailment

Section 201 of the Federal Power Act reserves to the states the authority over generation development, siting, and resource adequacy.10 While PJM has limited tools to support resource adequacy, including administering markets to produce price signals and curtailment mechanisms, under the…
Read this passage Filed comments: Reliability and curtailment

C. PJM’s Diverse Footprint is Distinct from Neighboring RTOs/ISOs and

printed heading · Topic match: Reliability and curtailment

PJM’s Diverse Footprint is Distinct from Neighboring RTOs/ISOs and Contributes to both Resource Adequacy and Governance Challenges.
Read this passage Filed comments: Reliability and curtailment

III. THE COST OF ADDRESSING THE RESOURCE ADEQUACY

printed heading · Topic match: Reliability and curtailment

THE COST OF ADDRESSING THE RESOURCE ADEQUACY CHALLENGE SHOULD NOT FALL TO EXISTING CUSTOMERS
Read this passage Filed comments: Reliability and curtailment

A. Existing Customers Are Bearing the Costs of the Growing Resource

printed heading · Topic match: Reliability and curtailment

Existing Customers Are Bearing the Costs of the Growing Resource Adequacy Challenge.
Read this passage Filed comments: Reliability and curtailment

B. New Large Load Customers Should Be Required to Bring the Generation

printed heading · Topic match: Cost allocation

As the Commission considers appropriate reforms to address the resource adequacy challenge, the central focus of any solution must be to bring more generation online.
Read this passage Filed comments: Cost allocation

C. Generation Procured for Native Load Growth Should Flow Through a

printed heading · Topic match: Cost allocation

Consistent with cost causation principles, once a state, utility, or other responsible entity determines that new generation must be procured to serve native load growth, distinct from large load growth, the associated costs should be recovered through a transparent pass-through tariff.
Read this passage Filed comments: Cost allocation

D. FirstEnergy Supports Resource Adequacy Solutions that Assign Costs to

printed heading · Topic match: Cost allocation

FirstEnergy Supports Resource Adequacy Solutions that Assign Costs to the Customers Driving the Demand or Benefiting from the New Generation.
Read this passage Filed comments: Cost allocation

IV. GOVERNANCE REFORMS SHOULD BE LIMITED TO REFORMS

printed heading · Topic match: Reliability and curtailment

The PJM governance structure must incorporate meaningful input from the PJM states.
Read this passage Filed comments: Reliability and curtailment

V. CONCLUSION

printed heading · Topic match: Reliability and curtailment

CONCLUSION For the reasons set forth above, FirstEnergy respectfully urges the Commission to issue an order that: (i) recognizes resource adequacy, not governance alone, as the central challenge facing PJM; (ii) directs PJM to pursue targeted governance reforms that improve efficiency while…
Read this passage Filed comments: Reliability and curtailment

CERTIFICATE OF SERVICE

printed heading · Topic match: Cost allocation

X Comments: 14) Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal?
Read this passage Filed comments: Cost allocation