AD26-7-000 · 2026-07-23 · Energy Artisans, LLC

Comments of Energy Artisans, LLC re PJM Interconnection, L.L.C.'s governance and stakeholder processes

Text extracted from the eLibrary original (SHA-256 20a506013bb6a7fa…). Download the original from the official source.

Contents · 16 sections
  1. EXECUTIVE SUMMARY p. 1
  2. I. MARKETS EXIST TO SERVE CUSTOMERS p. 1
  3. II. GOVERNANCE SHOULD BE MEASURED BY RESULTS p. 2
  4. III. CUSTOMERS SHOULD HAVE A STRONGER VOICE p. 2
  5. IV. COMPETITION REWARDS PREPARATION p. 2
  6. V. RULES SHOULD SOLVE DEMONSTRATED PROBLEMS p. 3
  7. VI. GOVERNANCE HAS BECOME A CONSTRAINT ON INVESTMENT p. 3
  8. VII. WHEN PROCESS BECOMES THE BOTTLENECK, PRICE SIGNALS LOSE THEIR p. 4
  9. VIII. RECOMMENDED REFORMS p. 4
  10. A. Establish Governance Performance Metrics p. 4
  11. B. Create Expedited Procedures p. 4
  12. C. Improve Transparency p. 4
  13. D. Conduct Periodic Governance Reviews p. 4
  14. IX. RESPONSES TO THE COMMISSION'S QUESTIONS p. 4
  15. X. CONCLUSION p. 5
  16. H. Bertram Wilson, CFA p. 6

Read topic-matched comments in AD26-7

Topics in the text: Reliability and curtailment · Connecting load and generation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

1 8060 Main Street Ellicott City, MD 21043 866-95-ENERG (36374) UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Governance and Stakeholder Reforms Docket No.
Read this passage

EXECUTIVE SUMMARY

printed heading

EXECUTIVE SUMMARY Power markets, like all markets, exist for one purpose: to serve customers.
Read this passage

I. MARKETS EXIST TO SERVE CUSTOMERS

printed heading

MARKETS EXIST TO SERVE CUSTOMERS The Commission's Notice asks how PJM's governance can become more responsive, transparent, accountable, and capable of addressing operational and market needs in a timely manner.
Read this passage

II. GOVERNANCE SHOULD BE MEASURED BY RESULTS

printed heading · Topic match: Reliability and curtailment

Institutions designed during a period of relative stability must now demonstrate that they remain capable of responding at the pace required by today's markets.
Read this passage Filed comments: Reliability and curtailment

III. CUSTOMERS SHOULD HAVE A STRONGER VOICE

printed heading

CUSTOMERS SHOULD HAVE A STRONGER VOICE One aspect of PJM governance deserves particular attention.
Read this passage

IV. COMPETITION REWARDS PREPARATION

printed heading

Developers, industrial customers, and investors must often commit substantial capital years before projects become operational.
Read this passage

V. RULES SHOULD SOLVE DEMONSTRATED PROBLEMS

printed heading

RULES SHOULD SOLVE DEMONSTRATED PROBLEMS Every institution accumulates rules over time.
Read this passage

VI. GOVERNANCE HAS BECOME A CONSTRAINT ON INVESTMENT

printed heading · Topic match: Connecting load and generation

As a practical example, we have a project that entered PJM's interconnection queue in February 2021 and is in the current Transition Cycle 2 with no network impacts.
Read this passage

VII. WHEN PROCESS BECOMES THE BOTTLENECK, PRICE SIGNALS LOSE THEIR

printed heading

WHEN PROCESS BECOMES THE BOTTLENECK, PRICE SIGNALS LOSE THEIR EFFECTIVENESS Recent market results reinforce this conclusion.
Read this passage

VIII. RECOMMENDED REFORMS

printed heading

RECOMMENDED REFORMS Energy Artisans respectfully recommends four practical reforms.
Read this passage

A. Establish Governance Performance Metrics

printed heading

Establish Governance Performance Metrics PJM should annually report objective measures including average decision timelines, implementation schedules, stakeholder participation, and completion of major initiatives, and new generation in service net of retirements.
Read this passage

B. Create Expedited Procedures

printed heading · Topic match: Reliability and curtailment

Create Expedited Procedures Certain issues—including reliability, resource adequacy, cybersecurity, and significant market integrity concerns—should be eligible for accelerated stakeholder review with clearly defined timelines.
Read this passage Filed comments: Reliability and curtailment

C. Improve Transparency

printed heading

Improve Transparency Stakeholders would benefit from publicly available tracking of significant initiatives, including expected decision milestones, implementation schedules, and reasons for material delays.
Read this passage

D. Conduct Periodic Governance Reviews

printed heading

Conduct Periodic Governance Reviews Just as utilities periodically reassess planning assumptions, PJM governance should undergo regular review to ensure that governance structures continue to support evolving market conditions.
Read this passage

IX. RESPONSES TO THE COMMISSION'S QUESTIONS

printed heading

RESPONSES TO THE COMMISSION'S QUESTIONS The Commission's questions generally focus upon Board authority, stakeholder representation, transparency, responsiveness, governing documents, and opportunities for reform. 5 8060 Main Street Ellicott City, MD 21043 866-95-ENERG (36374) Energy Artisans…
Read this passage

X. CONCLUSION

printed heading

CONCLUSION Energy Artisans, LLC develops, owns, finances, operates, and advises commercial, industrial, institutional, and utility energy projects throughout the PJM region.
Read this passage

H. Bertram Wilson, CFA