AD26-7-000 · 2026-08-21 · PJM Interconnection, L.L.C.

Post-Technical Conference Comments of PJM Interconnection, L.L.C. re PJM Governance and Stakeholder Reforms

Text extracted from the eLibrary original (SHA-256 ef2fbfc58742144a…). Download the original from the official source.

Contents · 5 sections
  1. I. Summary p. 3
  2. II. PJM’s Proposed Governance & Stakeholder Reforms (Term Sheet) p. 4
  3. III. Results of Recent PJM Members Survey p. 6
  4. VI. Conclusion p. 7
  5. A. Process for Independent Filings p. 16

Read topic-matched comments in AD26-7

Topics in the text: Reliability and curtailment · Cost allocation · Credit and exit

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

For Public Use Post-Technical Conference Comments from PJM Interconnection, L.L.C.
Read this passage

I. Summary

printed heading · Topic match: Cost allocation

PJM must be able to respond to emerging reliability risks, evolving market conditions, changes in the resource mix and demand, and other circumstances that may require action within time frames that do not always lend themselves to prolonged stakeholder deliberation.
Read this passage Filed comments: Cost allocation

II. PJM’s Proposed Governance & Stakeholder Reforms (Term Sheet)

printed heading · Topic match: Reliability and curtailment

State (including the District of Columbia) “Jump Ball” 205 Filing Rights Over Resource Adequacy PJM proposes to utilize its Section 205 rights over the Reliability Assurance Agreement and Attachment DD of the Tariff to make a “jump ball” filing on behalf of OPSI on a matter that pertains to…
Read this passage Filed comments: Reliability and curtailment

III. Results of Recent PJM Members Survey

printed heading

Results of Recent PJM Members Survey To gain insight into the Members’ perspectives on governance and stakeholder process reforms, PJM issued a survey to Voting Members.
Read this passage

VI. Conclusion

printed heading · Topic match: Reliability and curtailment

ER25- 785-000 at 2 (Dec. 20, 2024) (“Must-Offer Expansion Proposal”) (proposing to reflect Intermittent Resources, Capacity Storage Resources, and Hybrid Resources in the capacity market supply curve by sunsetting the categorical exemption from the capacity must- offer requirement applicable to…
Read this passage Filed comments: Reliability and curtailment

A. Process for Independent Filings

printed heading

Manual 34, Section 6.3, provides that, “[a]ny issue deemed important to a Member, PJM, OPSI or the IMM shall at least receive consideration in a meeting agenda…” The section includes five avenues for a new issue to be addressed: (1) worked within a Committee; (2) forwarded to an appropriate…
Read this passage