AD26-7-000 · 2026-08-21 · American Municipal Power, Inc.

Post-Conference Comments of American Municipal Power, Inc. on the issues addressed at the 07/23/2026 technical conference re PJM Governance and Stakeholder…

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Governance and Stakeholder Reforms
)
Docket No. AD26-7-000
POST-CONFERENCE COMMENTS OF
AMERICAN MUNICIPAL POWER, INC.
In accordance with the July 30, 2026 Notice Requesting Post-Conference
Comment issued by the Federal Energy Regulatory Commission (“Commission” or “FERC”),1 American Municipal Power, Inc. (“AMP”) submits its comments regarding the issues addressed at the July 23, 2026 technical conference in the above-captioned docket. AMP’s Vice President of Transmission & Regulatory Affairs, Steven Lieberman, was a conference panelist, and AMP appreciates this opportunity to further address these important issues. AMP’s comments focus on key topics from the conference and respond to the questions included in the appendix to the Notice.

I. COMMENTS
A. It is essential to identify the problems we are trying to solve.
Governance reforms are essential for PJM Interconnection, L.L.C. (“PJM”) as the region faces daunting resource adequacy and affordability challenges attributable in large measure to data center-driven load growth. Accomplishing the Commission’s goal of improving PJM’s ability “to address [its] operational and market needs in a timely and efficient manner,”2 however, first requires clearly identifying the aspects of PJM governance that have contributed to a lack of efficiency and effectiveness – and those that have not.

1 PJM Governance and Stakeholder Reforms, Notice Requesting Post-Conference Comment, Docket No. AD26-7-000 (July 30, 2026) (“Notice”). 2 Id. at 1.

PDF page 2

2
As Mr. Lieberman observed,3 a number of significant obstacles to efficient
decision-making in PJM – including a lack of issue prioritization – can be readily addressed without major structural changes to the PJM stakeholder process. While stakeholders should consider how best to ensure that PJM receives greater state input on key matters and respond to concerns that the PJM Board of Managers lacks adequate independence, these matters, too, likely could be effectively addressed with more tailored revisions to the existing governance framework. In contrast, the technical conference record does not support a conclusion that the current two-thirds sector-weighted member approval required for certain Federal Power Act (“FPA”) section 205 filings by PJM is a cause of PJM’s inability to respond efficiently and effectively to pressing problems. In fact, the record contains statements from multiple panelists, including Mr. Lieberman, showing that PJM already has the FPA section 205 rights it needs to address the resource adequacy and related reliability problems it is facing today,4 as demonstrated by numerous prior PJM filings where PJM has used its section 205 filing rights to address resource adequacy problems.5

3  Pre-Technical Conference Statement of Steven Lieberman on Behalf of American Municipal Power, Inc., Docket No. AD26-7-000, at p. 2 (July 14, 2026) (“Lieberman Statement”).
4 See id. at 12; see also, e.g., Pre-Conference Statement of Mason Emnett on Behalf of Constellation Energy Generation, LLC, Docket No. AD26-7-000, at pp. 2-3 (July 14, 2026) (“Emnett Statement”); Pre- Filed Statement of Pamela Quinlan, Principal, GQS New Energy Strategies, Docket No. AD26-7-000, at p. 9 (July 16, 2026).
5 See, e.g., PJM Interconnection, L.L.C., 195 FERC ¶ 61,076 (2026) (accepting PJM FPA section 205 filing to amend the PJM Tariff to extend a price collar for certain Reliability Pricing Model (“RPM”) auctions); PJM Interconnection, L.L.C., 190 FERC ¶ 61,117, order on reh’g, 191 FERC ¶ 61,221 (2025) (accepting PJM FPA section 205 filing to amend the PJM Tariff to extend the capacity must-offer requirement to all available Existing Generation Capacity Resources and update the Market Seller Offer Cap); PJM Interconnection, L.L.C., 190 FERC ¶ 61,088, order on reh’g, 192 FERC ¶ 61,135 (2025) (accepting PJM FPA section 205 filing to modify several aspects of RPM).

PDF page 3

3
B. PJM could meaningfully improve the stakeholder process through
better issue prioritization and other straightforward reforms.
The technical conference evidenced significant agreement among the participants regarding key deficiencies in the stakeholder process, particularly a lack of strategic planning and issue prioritization by PJM.6 The concern includes PJM’s failure to schedule meetings on important issues in a way that promotes prompt resolution.7 It is within PJM’s power to address these problems without changes to the PJM governing documents, and PJM’s acknowledgement of these deficiencies and its expressed willingness to address them are encouraging.

There also appeared to be general alignment over revisiting the existing voting structure of lower-level stakeholder committees. Providing corporate affiliates separate votes in these committees gives entities with multiple affiliates undue influence over the proposals that are endorsed for consideration by the higher-level committees, and, in turn, allows them to veto proposals that are more likely to garner consensus stakeholder support. A simple fix would be to apply the same sector-weighted voting approach used in the standing committees to lower-level committee voting. While this change would require the stakeholders to approve changes to Manual 34, the agreement expressed by panelists on this issue suggests that this may be achievable.

6 See, e.g., Lieberman Statement at 12-14; Submitted Statement of Kent Chandler, Senior Fellow, Energy and Environmental Policy, R Street Institute, Docket No. AD26-7-000, at p. 5 (July 14, 2026); Emnett Statement at 9-11; Pre-Conference Statement of J. Arnold Quinn, Senior Vice President, Regulatory Policy, Vistra Corp., Docket No. AD26-7-000, at pp. 8-9 (July 15, 2026).
7 See Lieberman Statement at 15. To be clear, the solution is not to hold more meetings, it is to increase the cadence of meetings on key issues, even if that means deprioritizing other issues.

PDF page 4

4
PJM and its stakeholders should prioritize these straightforward “blocking and tackling” reforms to the stakeholder process, as they would go a long way toward improving efficiency and effectiveness.

C. Enhanced state input is desirable.
AMP supports enhancing state input into the PJM stakeholder process. While there are various proposed paths toward achieving this goal, increased participation by the Organization of PJM States, Inc. (“OPSI”) under the current arrangements would be one simple, highly effective, and seemingly uncontroversial way to improve the ability of the states to make their voices heard. Resource constraints should not limit OPSI’s ability to provide its valuable perspective in PJM stakeholder debates, as OPSI determines its own budget, which is funded by PJM customers.

Another effective way to bring an enhanced state perspective to PJM governance would be to revise the PJM Board qualification criteria by adding a requirement that at least one Board member have experience working for state government or a state regulatory commission. Focusing on Board qualification criteria seems more effective than assigning state representatives one or more seats on the PJM Nominating Committee. AMP looks forward to further engagement with the states’ representatives on approaches to ensuring that state perspectives are adequately considered in PJM governance.

D. Concerns about PJM Board independence and transparency should
be addressed.
Although PJM’s existing governance framework strikes an appropriate balance between Board independence and RTO responsiveness to stakeholder views, concerns were expressed at the technical conference that the current framework does not ensure adequate Board independence. Those concerns should be addressed, with due

PDF page 5

5
consideration given to the various potential responses. Revising PJM’s governing documents, for example, to state that the Board owes a duty to the public interest should be considered. As with most governance reforms considered in this proceeding, changes aimed at enhancing Board independence are likely to come with trade-offs that should be considered as part of a more holistic discussion. In considering any such changes, moreover, PJM, stakeholders, and the Commission must ensure that Board

independence is balanced against the need for responsiveness to stakeholder concerns, as required by Order No. 719.8

E. FPA section 205 filing rights are not the problem.
The technical conference included significant discussion of whether the PJM governing documents should be changed to eliminate the requirement for two-thirds sector-weighted approval by the Members Committee for certain PJM section 205 filings. Such revisions, however, are not necessary to improve PJM’s ability to address efficiently its operational and market needs because PJM’s authority with respect to making FPA section 205 filings is simply not the problem.

A number of technical conference panelists – most prominently, those representing PJM itself – argued that giving PJM unconditioned FPA section 205 filing rights over the regional transmission planning protocol and the rules governing the energy and ancillary services (“EAS”) markets would improve PJM’s ability to address current challenges. But neither the PJM representatives nor any other panelist, persuasively explained how providing PJM with unconditioned FPA section 205 filing rights over transmission planning 8

Wholesale Competition in Regions with Organized Elec. Mkts., Order No. 719, 125 FERC ¶  61,071, at PP 502-503 (2008), order on reh'g, Order No. 719-A, 128 FERC ¶  61,059, order on reh'g, Order No. 719-B, 129 FERC ¶  61,252 (2009).

PDF page 6

6
would enhance the RTO’s ability to tackle its looming resource adequacy and affordability crises more effectively. The most glaring rebuttal to PJM’s position is: PJM already has unconditioned FPA section 205 filing rights over its capacity construct, yet it has been unable to effectively respond to the region’s increasingly dire resource adequacy deficits, as observed by Mr. Lieberman and other technical conference panelists.

The requirement for Members Committee approval of certain PJM section 205 filings promotes development of well-informed, consensus-driven proposals for changes to the EAS markets and transmission planning protocol. The value of this approval requirement should not be discounted based on unproven claims. In situations where consensus support for a section 205 filing is required but is not achievable in a timely manner, filing under FPA section 206 is a reasonable path currently available for PJM to present important issues to the Commission.

The existing requirement for Members Committee approval is critical to ensuring PJM’s independence from any market participant or class of participants.9 The Commission has found that the Members Committee’s sector-weighted voting promotes RTO independence and responsiveness by “ensur[ing] that no single stakeholder group can dominate.”10 The independence-promoting function of the Members Committee approval requirement is an important check on what PJM’s Independent Market Monitor (“IMM”) has characterized as the Transmission Owner sector’s “unique ability to affect the decision making of the PJM Board and PJM staff.”11 Indeed, inclusion of the transmission planning protocol in the PJM Operating Agreement – and the attendant requirement for Members

9 See 18 C.F.R. § 35.34(j)(1)(ii) (2025).
10 PJM Interconnection, L.L.C., 133 FERC ¶ 61,071, at P 44 (2010).
11  PJM IMM, Comments, Docket No. AD26-7-000, at 3 (July 17, 2026) (“IMM Statement”).

PDF page 7

7
Committee approval of any proposed changes to the planning protocol under FPA section 205 – was expressly designed to insulate PJM from the influence of any market participant or group, and particularly transmission owners.12

The technical conference participants considered potential changes to the existing FPA section 205 filing rights framework in PJM, such as adoption of a “jump ball” filing requirement, or use of a “shot clock” approach where PJM would have unconditioned FPA section 205 filing rights if the Members Committee failed to act on a proposal within a defined period of time. While these concepts are not necessary to resolve concerns about the efficiency and effectiveness of PJM decision making, they could be considered as part of a broader governance reform discussion. In any case, the jump ball and shot clock approaches present complications, including time limits on the shot clock, the scope and duration of PJM filing rights once the shot clock expires, stakeholders’ rights to compel the jump ball filing, and the processes that develop and identify competing filings, including the entity tasked with drafting responsibilities.

II. RESPONSE TO SPECIFIC QUESTIONS
In the table below, AMP responds to the questions included in the appendix to the Notice, and provides brief explanatory comments for each response. AMP is a member of the Electric Distributor (“ED”) sector in PJM. The ED sector is comprised of non-profit and not-for-profit organizations that, by their nature, are not profit motivated and serve the citizens of their communities.

12 See Atl. City Elec. Co., 77 FERC ¶ 61,148, at p. 61,578; Pennsylvania-New Jersey-Maryland Interconnection, 81 FERC ¶ 61,257, at p. 62,275 (1997), order on reh’g, 92 FERC ¶ 61,282 (2000), modified sub nom. Atl. City Elec. Co. v. FERC, 295 F.3d 1 (D.C. Cir. 2002).

PDF page 8

8
Consistent with the Commission's instructions, AMP has answered the questions independently, addressing each issue in isolation. As the Commission observed, however, the “questions contain individual elements that are interrelated and potential changes to one element may affect others.”13 AMP is open to considering governance changes in a holistic discussion of PJM governance reform, and AMP’s position on specific issues may evolve in response to agreed-upon or mandated changes on other issues. AMP’s positions, therefore, should not be understood as signifying an unwillingness to engage with PJM, states, and other stakeholders on governance changes. PJM Board Independence

Questions/Comments
Yes
No
1) Should Board members’ terms be extended to five or more years? 

Comments: The current three-year Board term does not impose a significant constraint on Board independence or on effective PJM governance. A three-year term, subject to re-election, gives Board members time to develop perspective on the issues facing the RTO, while providing stakeholders with an appropriate mechanism to promote RTO responsiveness. PJM’s Board term of three years, moreover, is consistent with the other RTOs, including MISO, ISO-NE, SPP, ERCOT, and Cal-ISO. NYISO has four-year terms.

2) Should there be a maximum number of years that a Board member
may serve (e.g., 10 years)?

Comments: The Board has already adopted limits on the duration of a Board member’s service. As explained in PJM’s Board fact sheet, “[s]ervice is limited to five terms, and only candidates younger than age 75 are eligible.” Thus, terms are effectively limited to fifteen years. There is no need to change this structure. Arbitrary adoption of shorter term limits could deprive PJM and its stakeholders of qualified, experienced, and trusted Board members, with little or no RTO governance benefit.

3) Should the Board member qualification rules be revised to provide a preference for some Board members that reside in the PJM region?


13  Notice at 3 (Appendix).

PDF page 9

9
Comments: There should be no formal geographical preference for Board members to reside in the PJM region. The emphasis should be on selecting the best available candidates regardless of where they reside. To the extent that a prospective Board member has valuable experience with PJM or the PJM region, the Nominating Committee would presumably give appropriate weight to that experience in selecting Board candidates.

4) Should the conflict-of-interest rules be revised to reduce the cooling off period for Board members from two years to one year?


Comments: It has not been demonstrated that the two-year cooling off period is a significant constraint on the ability to identify qualified Board candidates. Even if the two-year rule does have some such impact, this cooling off period remains an appropriate conflict of interest mitigation measure. If there is even an appearance of a conflict of interest, confidence in Board member independence could be significantly compromised. To the extent there is a valid concern that two years is too long, consideration should be given to a shorter one-year cooling off period, consistent with MISO’s approach, but the cooling off period should not be eliminated.

5) Should restrictions on Board communications be relaxed to enable more communication between the Board and stakeholders?


Comments: There is no reason to modify any current rules pertaining to communication between the Board and stakeholders, as provided for in PJM’s Manual 34. Ex parte rules exist for good reason: to ensure that no person or stakeholder has an undue advantage or ability to influence a decision maker, in this case PJM’s Board of Managers. The PJM Board needs more transparency, not less.

Relaxing the PJM Board’s ex parte rules may allow incumbent PJM transmission owners (individually or collectively) to exercise greater influence over PJM Board action than they can today. As the Independent Market Monitor for PJM has observed, transmission owners possess “a unique ability to affect the decision making of the PJM Board,”14 and allowing PJM transmission owners to meet behind closed doors with the PJM Board would only exacerbate such RTO independence concerns.

6) In order to increase transparency, should Board votes be made public or the Board be required to explain its reasoning?


Comments: Yes, transparency on all levels is severely lacking in PJM. Contrast that with the manner in which the boards operate at SPP and MISO, as described in Mr. Lieberman’s written statement. Board votes should be made public, meeting minutes published, and a requirement for the Board to explain its reasoning, including whether it reviewed alternative solutions beyond those 14  IMM Statement at 3.

PDF page 10

10
proposed by PJM staff.
7) In order to increase transparency, should some Board meetings be open or available to the public?


Comments: Other than meetings or sessions specifically convened to discuss confidential information, as would occur in executive session, Board meetings should be open to and available for the public. PJM should consider the MISO approach to board meetings, which allows the public to attend and listen to board and board committee meetings, followed by an opportunity for the public to make comments to the board or committee at the end of the meeting. Similarly, SPP has board meetings that are open to the public.

8) Should PJM’s governing documents be revised to explicitly state that the responsibility of PJM and its Board is to serve the public interest? 

Comments: As PJM stated at the July 23 technical conference, repeated in its pre- conference statement, and includes on its website, “PJM operates a competitive wholesale electricity market and manages the high-voltage electricity grid to ensure reliability for more than 67 million people.” Given this mission, the interests of PJM as an organization already are generally aligned with the public interest, and a provision in PJM’s governing documents making this explicit could be appropriate.

9) Should state representatives have at least one voting member on the Nominating Committee?


Comments: Changes to improve state confidence in PJM’s decision-making could be useful. But the technical conference record and Mr. Lieberman’s own experience serving on the PJM Nominating Committee show that the absence of explicit state representation on that committee does not undermine effective PJM governance. Nominating Committee members do not appear to have shown a pattern of “voting their interests” in lieu of nominating the most qualified candidates, nor would providing state representatives with one or more votes on the Committee necessarily result in more Board candidates focused on state interests.

A more effective way to help ensure that state interest perspectives are represented on the PJM Board could be to revise the Board qualifications. For example, the Operating Agreement could be revised to add a requirement that at least one Board member has experience working for state government or a state regulatory commission. While PJM maintains a list of required skills for Board members based on section 7.2 of the PJM Operating Agreement, there is currently no requirement for this specific experience on the PJM Board. This approach also avoids any potential complications associated with having non-Member state representatives on the Nominating Committee.

PDF page 11

11
10) Should PJM adopt public performance metrics and tie management compensation to their achievement?


Comments: Presently, there is little or no insight into or accountability for PJM management’s performance. Tying performance evaluation and compensation to publicly available metrics would likely increase confidence in PJM’s decision making. But any such performance assessment framework must be carefully designed to avoid misaligned incentives. For example, metrics that simply promote speed in decision-making might encourage PJM management to act quickly on a given issue, at the expense of pursuing a better solution that takes more time to develop.

Section 205 Filing Rights
Questions/Comments
Yes
No
11) Should the stakeholder process be advisory, i.e., stakeholder votes only inform the Board?


Comments: Currently the stakeholder process is advisory on matters solely contained within the Open Access Transmission Tariff, meaning stakeholder votes only inform the Board but do not bind the Board’s decision about whether to make an FPA section 205 filing and what to include in the filing.15 While PJM FPA section 205 filings to change the Operating Agreement require a favorable two- thirds sector-weighted vote, as discussed below and supported by the technical conference record, there is no reason to modify this requirement (or the sector- weighted voting approach) to resolve concerns about the efficiency and effectiveness of PJM decision-making.

12) Should PJM have section 205 filing rights over the energy market and ancillary services unencumbered by the requirement to obtain approval of two-thirds of the Members Committee?


Comments: Consistent with the Commission’s goals, PJM governance improvements should target those aspects of the existing governance framework that undermine the RTO’s ability “to address operational and market needs in a timely and efficient manner.”16 The need for Members Committee approval for PJM to make an FPA section 205 filing to modify energy and ancillary services (“EAS”) market rules is not part of the problem. As was observed by multiple technical conference panelists (including the IMM), PJM currently has unilateral

15  PJM’s recent filing regarding its proposed reliability backstop auction in Docket No. ER26-3380-000 is an example of where the PJM Board directed an FPA section 205 filing that did not reflect the approach supported by stakeholders.
16  Notice at 1.

PDF page 12

12
FPA section 205 rights over its RPM capacity construct, yet resource adequacy has been the principal focus of concern in PJM for some time, showing that unilateral FPA section 205 rights are not a panacea for PJM’s governance challenges.

As the Commission is well aware, PJM has frequently availed itself of these section 205 rights to unilaterally modify RPM, only to find that further revisions are needed -- in some cases to address concerns that were raised by stakeholders but dismissed by PJM.17 PJM has moved swiftly to change the capacity construct rules again and again, proving that speed in the wrong direction only makes things worse.

The longstanding requirement for Members Committee approval of section 205 changes to the EAS markets serves PJM, its Members, and the public by promoting the development of well-informed, consensus-driven proposals. To be sure, there are times when decisive action may be necessary and efforts to achieve consensus should not delay action by PJM. In such a situation, a filing under FPA section 206 is a reasonable way to put the issue before the Commission. Absent such exigent circumstances, a collaborative stakeholder process is likely to result in more well-informed and durable proposals to the Commission, and the current Members Committee approval requirement

promotes such a process.
The Members Committee approval requirement has the salutary benefit of helping ensure that the PJM decision-making process is independent of control by any market participant or class of participants. Eliminating the collective say that the PJM sectors currently have regarding proposed Operating Agreement

modifications could provide a particular sector or sectors with the ability to exert undue influence on PJM.

As with other issues, however, AMP is willing to consider changes to PJM’s FPA section 205 filings rights framework as part of a broader discussion of PJM governance.

13) Should PJM have section 205 filing rights over Regional
Transmission Expansion Planning (RTEP) unencumbered by the
requirement to obtain approval of two-thirds of the Members
Committee?

Comments: There is no evidence that PJM’s lack of unencumbered section 205
17  For example, PJM disputed AMP’s arguments that implementation of a marginal effective load carrying capability (“ELCC”) approach applied to all generation capacity resources could contribute to significant increases in capacity prices, see PJM Interconnection, L.L.C., 186 FERC ¶ 61,080, at P 273 (2024), but the IMM later concluded that “holding everything else constant, use of the ELCC approach rather than the prior, EFORd approach, resulted in a 49.1 percent increase in RPM revenues” when prices skyrocketed in the 2025/2026 Base Residual Action. IMM, Analysis of the 2025/2026 RPM Base Residual Auction Part A, at 1 (Sept. 20, 2024), https://www.monitoringanalytics.com/reports/Reports/2024/IMM_Analysis_of_the_20252026_RPM_Ba se_Residual_Auction_Part_A_20240920.pdf.

PDF page 13

13
filing rights over the RTEP protocol has been an obstacle to the implementation of necessary transmission planning reforms. Indeed, when PJM filed a complaint in Docket No. EL24-119 claiming that the Operating Agreement had become unjust and unreasonable on such grounds, PJM offered no historical examples of where the longstanding stakeholder voting requirement had hindered PJM’s transmission planning.18

Further, the role of the Members Committee approval requirement in ensuring PJM independence from any class of participants is particularly important with respect to the RTEP protocol. Absent the Members Committee approval requirement, the Transmission Owner sector would be better positioned to exert their “unique ability to affect the decision making of the PJM Board”19 on transmission planning matters. While no one industry segment should be able to exercise authority over PJM’s planning process, ex parte communications between the transmission owners and the Board are particularly concerning due to the conflict of interests caused by the transmission owners’ financial interests: “utilities that own or control transmission facilities naturally wish to maximize profit. The transmission-owning utilities thus can be expected to act in their own interest to maintain their monopoly. . . .”20

14) Should the Organization of PJM States Inc (OPSI) have “jump ball” rights over resource adequacy and transmission cost allocation filings when a supermajority of OPSI agrees on an alternative proposal?


Comments: OPSI is not a Member of PJM and therefore it is unclear why OPSI should have authority to develop changes to the OA or Tariff that PJM would be required to file under FPA section 205 as part of a “jump ball” filing. OPSI’s existing opportunities for input to PJM, including the opportunity for OPSI and its members to join PJM, along with OPSI’s ability to file proposed changes to the OA and Tariff under FPA section 206, currently provide pathways for OPSI to address any OPSI-endorsed changes to the OA or Tariff. It is therefore not clear why OPSI would need jump ball filing rights.

15) Should the Members Committee have “jump ball” filing rights over the portions of the tariff where PJM has 205 filing rights when a supermajority of stakeholders approves an alternative proposal?


Comments: Yes. When broad support for a proposal to amend the Tariff is demonstrated by a two-thirds sector-weighted vote of the Members Committee and the PJM Board declines to direct PJM to file that proposal, the Members should have an ability to require PJM to submit the Members Committee-endorsed

18 See, e.g., Duquesne Light Co., 189 FERC ¶ 61,181, at P 93 (2024), reh’g denied, 192 FERC ¶ 61,051 (2025), aff’d, PJM Transmission Owners v. FERC, 2026 U.S. App. LEXIS 16255 (D.C. Cir. June 5, 2026).
19  IMM Statement at 3.
20 Transmission Access Policy Study Grp. v. FERC, 225 F.3d 667, 684 (D.C. Cir. 2000), aff’d sub nom N.Y. v. FERC, 535 U.S. 1 (2002).

PDF page 14

14
Tariff proposal along with any PJM proposal on equal footing under FPA section 205. To the extent that the PJM Board is provided unconditioned FPA section 205 filing rights over the OA (which AMP does not support), a similar “jump ball” filing requirement should apply to proposed OA amendments.

Stakeholder Process
Questions/Comments
Yes
No
16) Should the approval threshold in the Members Committee be lowered from two-thirds sector-weighted voting?


Comments: The two-thirds majority was established to drive a consensus building stakeholder process intended to result in well-informed, durable proposals for changes to the Operating Agreement. Lowering the sector-weighted voting approval threshold would diminish the effectiveness of this framework, which has worked well historically. Moreover, the Members Committee approves the vast majority of issues that come before it. While a lower approval threshold might result in easier passage of proposals on more contentious issues, there is no reason to think that it would improve the quality and durability of those proposals. Well-informed, consensus proposals are most helpful on contentious issues.

17) Should the voting rules barring affiliate votes, which apply to senior standing committees, also apply to lower-level committees?


Comments: As explained in Mr. Lieberman’s pre-conference statement,21 this is a relatively simple reform that could meaningfully improve the effectiveness of the PJM stakeholder process. The current practice of allowing affiliates to vote at the lower level committees gives disproportionate influence to entities with multiple affiliates by allowing them effectively to determine the proposals that are endorsed for consideration at higher-level committees. This practice interferes with the development of consensus proposals, can result in the endorsement of proposals that are unlikely to pass at senior-level committees,22 and raises RTO independence concerns to the extent that the RTO’s decision-making process is ultimately unduly influenced by a particular class of market participants.

21  Lieberman Statement at 8-12.
22  To cite just one example, in the ELCC Senior Task Force, lower level voting identified significant support for a PJM proposal (76.7%), yet the proposal received only a 1.53 sector-weighted vote at the Markets and Reliability Committee, equivalent to 30.6% support.

PDF page 15

15
State Participation
Questions/Comments
Yes
No
18) In addition to OPSI, should there be a second state representative group consisting of governors’ representatives and/or state

legislators’ representatives?

Comments: While the PJM Governors Collaborative and Independent State Agencies Committee (ISAC) already provide valuable state input on PJM matters, AMP does not object to the states exploring the formation of other groups to participate in the PJM stakeholder process.

19) Should state representatives have a formal voting role in the stakeholder process (limited to certain topics, such as resource adequacy and regional transmission cost allocation) in addition to the consumer advocate votes?


Comments: A formal voting role for state representatives could add value to the PJM stakeholder process, although this concept may raise complex questions about who should be considered “state representatives” entitled to vote. One currently available path is for state representatives to become PJM Members. The record indicates that state regulators originally did not want a formal vote because they did not want to be in a position of having voted on PJM rules that then resulted in costs coming before them to allocate at the retail level. This concern – to the extent it is still operative – would presumably apply under any approach that provides states with formal voting rights. Providing state representatives with voting rights through PJM membership would have the benefit of avoiding major changes to the existing PJM stakeholder framework, while giving state representatives a more direct voice in PJM governance.

20) Should PJM be required to consult with OPSI prior to making a section 205 filing related to resource adequacy and transmission cost allocation?


Comments: A formal requirement for PJM to consult with OPSI is unwarranted, and, in any event, would not necessarily improve the likelihood of achieving durable resource adequacy and transmission cost allocation reforms. OPSI already participates in the stakeholder process, and funding is available for OPSI to allow it to participate even more effectively than it already does. Additionally, OPSI meets with the PJM Board several times a year. Finally, it is worth noting that the PJM transmission owners currently have FPA section 205 filing rights over regional transmission cost allocation, not PJM.

PDF page 16

16
III. CONCLUSION
American Municipal Power, Inc. requests that the Commission consider the forgoing comments in taking any further action in this proceeding. Respectfully submitted,

/s/ John McCaffrey
John McCaffrey
Stinson LLP
1775 Pennsylvania Avenue NW
Suite 800
Washington, DC 20006
(202) 728-3026
john.mccaffrey@stinson.com
DATED: August 21, 2026
/s/ Gerit F. Hull
Lisa G. McAlister
Senior Vice President & General Counsel
Gerit F. Hull
Deputy General Counsel for Regulatory Affairs
American Municipal Power, Inc.
1111 Schrock Road, Suite 100
Columbus, OH 43229
(614) 540-1111
lmcalister@amppartners.org
ghull@amppartners.org

PDF page 17

CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person designated on the official service list compiled by the Secretary in this proceeding. Dated at Washington, D.C., this 21st day of August, 2026.

/s/ John McCaffrey
John McCaffrey
Stinson LLP
1775 Pennsylvania Avenue NW
Suite 800
Washington, DC 20006
(202) 728-3026
john.mccaffrey@stinson.com