Pre-Technical Conference Comments of PPL Electric Utilities Corporation re the PJM Governance and Stakeholder Reforms
Text extracted from the eLibrary original (SHA-256 e91b74e8c24d6dd3…). Download the original from the official source.
Contents · 7 sections
Read topic-matched comments in AD26-7
Topics in the text: Reliability and curtailment · Registry access · Cost allocation
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text
UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Governance and Stakeholder Reforms Docket No.Read this passage
I. BACKGROUND AND NEED FOR REFORM
printed heading · Topic match: Reliability and curtailment
As PPL’s Wendy Stark told the Commission at a different technical conference last year, “[f]un- damental reform to address resource adequacy must be focused on the states.”2 Deregulation stat- utes have prevented the utilities from responding to the clear and direct need for more generation…Read this passage Filed comments: Reliability and curtailment
II. INTRODUCTORY COMMENTS
printed heading · Topic match: Cost allocation
There, it works directly with PJM through the PJM Tariff and Manuals, including but not limited to planning, interconnections, cost allocation, rates and rate design, and operations.Read this passage Filed comments: Cost allocation
A. The Board of Managers and Filing Rights
printed heading
It must have independent executive power to make decisions without being controlled by or be- holden to outside parties with their own agendas.Read this passage
B. The PJM Members and the Stakeholder Process
printed heading
The PJM Members and the Stakeholder Process In addition to the PJM Board, PJM has a large and active Membership that has retained significant control, formally and informally, over the organization.Read this passage
C. The Role of the States
printed heading · Topic match: Reliability and curtailment
PPL Electric’s strong view remains that “the deregulated states must exercise more au- thority over generation planning and investment than they have in the past.”10 At a minimum, this will require coordination between the states and PJM beyond the level that has occurred in the past.Read this passage Filed comments: Reliability and curtailment
III. RESPONSES TO QUESTIONS
printed heading · Topic match: Registry access
For example, in Pennsylvania, the governor appoints the PUC commissioners, but not the consumer advocate.26 State governments should clar- ify what powers they delegate to interstate organizations like OPSI or a new state “governor committee.” It may also be advisable to limit positions in such…Read this passage Filed comments: Registry access
IV. CONCLUSION
printed heading
CONCLUSION PPL Electric thanks the Commission for raising these important topics and asks that its comments be considered part of the record.Read this passage