AD26-7-000 · 2026-07-22 · PPL Electric Utilities Corporation
Pre-Technical Conference Comments of PPL Electric Utilities Corporation re the PJM Governance and Stakeholder Reforms
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Governance and Stakeholder
Reforms
Docket No. AD26-7-000
PRE-TECHNICAL CONFERENCE COMMENTS
OF PPL ELECTRIC UTILITIES CORPORATION
In this docket, the Federal Energy Regulatory Commission (FERC or Commission) in- vites comments from interested parties related to PJM Interconnection, L.L.C.’s (PJM) govern- ance and stakeholder processes, focusing on potential reforms to improve PJM’s ability to ad- dress operational and market needs in a timely and efficient manner.1 PPL Electric Utilities, Inc. (PPL Electric) thanks the Commission for raising these important questions and responds as fol- lows:
I. BACKGROUND AND NEED FOR REFORM
PPL Electric was founded in 1920 as the Pennsylvania Power & Light Company. PPL Electric is a Pennsylvania corporation and wholly owned indirect subsidiary of PPL Corporation (PPL). It owns and operates transmission and distribution facilities in 29 counties in eastern and central Pennsylvania. PPL Electric was a founding member of PJM in 1927. PPL Electric has ac- tively participated in every version of PJM, from an early power pool to a regional transmission organization. It is a signatory to the PJM Consolidated Transmission Owners Agreement (CTOA), PJM Operating Agreement (OA), and PJM Reliability Assurance Agreement (RAA). PPL Electric remains deeply committed to the integrated regional transmission network, owning
1 See PJM Governance and Stakeholder Reform, Notice of Commission-Led Technical Conference, Docket No. AD26-7 (May 12, 2026).
PDF page 2
2
more than 5,000 miles of transmission lines, representing more than $7 billion in capital invest- ment, under PJM’s operational control. PPL Electric’s more than 1.5 million customers also rely on the PJM markets for wholesale power supply.
Although, as discussed below, PPL Electric and the other transmission owners believe there are appropriate reforms to PJM governance related to transmission, the pressing need for change is on the markets side. There, the resource adequacy crisis is undermining confidence in the energy markets and driving this conversation. As prices have risen, PPL Electric’s customers share in the pain. Its average residential retail bills have gone up more than $20 per month as a result of the capacity market price increases since the 2024/25 auction. This money flows di- rectly to incumbent power generators. None goes to the utility and none is spent on improving service to customers. Under the state’s deregulation laws, PPL Electric and the other Pennsylva- nia utilities are no longer able to build and own electric generation resources under the jurisdic- tion of the Pennsylvania Public Utilities Commission (PA PUC). This makes the failure of the PJM capacity market to adequately incentivize new generation resources the single biggest risk to reliable electric service in PPL Electric’s service territory. Other than as an extreme minority voter in the PJM stakeholder process (where its vote constitutes approximately 1/12th of the transmission owner sector’s 20% vote, barely 1% of the overall sector-weighted vote), PPL Elec- tric is entirely powerless to close this gaping hole in its ability to provide reliable service. To the extent PJM governance reform leads to beneficial changes in the energy markets, PPL Electric applauds the effort and stands ready to assist. However, a note of caution is war- ranted: The Commission and the participants in this docket should be sober about the limited ability of governance reform to address resource adequacy and should embark on this process with eyes open toward the real risk that things can get worse. PJM manages one of the largest
PDF page 3
3
and most important power markets in the world. They support hundreds of millions of customers, attract hundreds of billions of dollars of investment, and enable trillions of dollars of economic activity. Each of the more than one thousand PJM Members and all fourteen PJM states (includ- ing the District of Columbia) has a deeply held opinion on how the markets should be man- aged—sometimes more than one within a given organization—and many are willing to spend significant legal fees defending embedded rights all the way to the United States Supreme Court. Any change imposed from the outside—even one that seems inconsequential—will almost cer- tainly lead to years of expensive litigation. This litigation will further reduce certainty in the mar- kets that already face a crisis—and crisis is understating it—of underinvestment. Thus, the Commission should be cautious and approach this effort with an eye toward in- cremental change focused on the real problem to be solved: resource adequacy and the need to get generation built now. This requires a focus on the states, particularly the deregulated states. As PPL’s Wendy Stark told the Commission at a different technical conference last year, “[f]un- damental reform to address resource adequacy must be focused on the states.”2 Deregulation stat- utes have prevented the utilities from responding to the clear and direct need for more generation capacity in the region caused primarily by the growth in large load data centers, making them en- tirely reliant on failing market constructs. In a vertically integrated state, the public utilities would already be building large dispatchable baseload generators to meet the anticipated de- mand—and would have started years ago—under the regulatory supervision of their state com- missions and following an integrated resource planning process. It follows that the real solution to the crisis PJM faces lies in facilitating appropriate changes to state law that facilitate real
2 Meeting the Challenge of Resource Adequacy in Regional Transmission Organization and Independent System Operator Regions, Pre-Conference Statement of Wendy Stark on Behalf of PPL Corporation, Docket No. AD25-7 (May 16, 2025) at 2.
PDF page 4
4
resource planning. Any focus on PJM governance changes, including expanding the role of the states, such as in nominating Board members, should advance that goal.
II. INTRODUCTORY COMMENTS
PJM is a large and complex organization, with an equally complex governing structure. At an extremely high level, it is divided into two components: transmission planning/operations and energy markets. PPL Electric’s primary focus as a transmission owner has always been on the former. There, it works directly with PJM through the PJM Tariff and Manuals, including but not limited to planning, interconnections, cost allocation, rates and rate design, and operations. Governance issues are certainly relevant on the transmission side, and reforms are necessary in certain areas. For example, PPL Electric and the other PJM transmission owners recently put for- ward a major effort to empower the PJM Board to propose changes to the Regional Transmission Expansion Planning Protocol, where the existing status quo gives a minority of PJM members veto power over any change to the planning rules.3 This effort was unsuccessful on other grounds, but PPL Electric remains committed to removing this impediment to rational, independ- ent regional transmission planning, and hopes that such a change will be part of any package of reforms to come from this process.
On the energy markets and resource adequacy side of the house, PPL Electric’s interest as a “poles and wires” transmission and distribution utility has historically been more indirect, but is nonetheless critically important. PPL Electric’s customers are reliant on the PJM markets to provide the capacity, energy, and ancillary services needed to keep the lights on. Approxi- mately half of PPL Electric’s customers shop through Pennsylvania’s deregulated retail market,
3 See Duquesne Light Company, Docket No. ER24-2338 (Jun. 21, 2024).
PDF page 5
5
with their Electric Generation Supplier (EGS)4 procuring wholesale power products at PJM. The other half take default service from PPL Electric, which is also entirely reliant on the PJM mar- kets for these products. To put it very simply, the wholesale markets are failing these customers. While PPL Electric believes the solution lies more in changes to state policy rather than PJM governance, certain reforms may be appropriate and helpful.
A. The Board of Managers and Filing Rights
No change to PJM governance can succeed without recognizing the essential role of the independent Board of Managers. PJM is a public utility under FERC jurisdiction pursuant to the Federal Power Act.5 It directs the operation of both the country’s largest transmission grid and generation fleet. It is under constant pressure from both market participants and political actors. It must have independent executive power to make decisions without being controlled by or be- holden to outside parties with their own agendas. As such, the PJM Board should have full con- trol over all elements of the RTO delegated to PJM in the CTOA. This starts with filing rights. Although such rights are much sought after, federal law is clear: they are unambiguously granted to the owners of FERC-jurisdictional assets and can only be transferred voluntarily by those owners.6 The modern version of PJM started with such a grant. In the CTOA, the PJM transmis- sion owners collectively agreed to transfer to PJM, exclusively and unilaterally, operational con- trol over their billions of dollars of transmission assets, as well as their right under federal law to establish and make changes to the terms and conditions of transmission service in a FERC Tariff,
4 66 Pa. C.S. § 2803.5 16 U.S.C. § 824(e).6 Atl. City Elec. Co. v. FERC, 295 F.3d 1, 9–11 (D.C. Cir. 2002) (“Atlantic City”), enforced, 329 F.3d 856 (D.C. Cir. 2003).
PDF page 6
6
retaining limited authority for themselves over certain matters, primarily rates and rate design.7 PJM is not free to further delegate filing rights to third parties; nor can the Commission require that they be surrendered to any other entity. However, to the extent that any other PJM governing documents purport to limit the PJM Board’s exercise of control over powers delegated to it by the transmission owners, that limitation can and should be removed.
As to the specifics of how the Board is selected and how it exercises power in PJM, FERC’s role is also limited. The courts have generally not allowed the Commission to reach into the internal governance of the public utilities under its jurisdiction, including the RTOs.8 That said, it is entirely appropriate to use this forum to share ideas from other regions and discuss best practices that may be included in a package of appropriate reforms. For example, PPL Electric generally believes that it has become too difficult to find potential Board members who (1) have the relevant experience and expertise, (2) are willing to serve in an increasingly fraught role, and
(3) qualify under PJM’s onerous independence rules. It supports changes to the OA that would ease the Board selection process and attract larger numbers of qualified candidates for a difficult job. These reforms may include changes to term and tenure (extending it to increase independ- ence), reducing certain restrictions on affiliation with market participants that has pushed away experienced personnel from the region (in fact, a qualified preference for geographic proximity may be appropriate), and changes to ex parte communication rules that have been interpreted to restrict Board member access to information or member opinion outside highly structured formal meetings. In short, reforms should address PJM rules and processes that hinder intelligent and informed Board decision-making.
7 CTOA §§ 4.1, 6.3.2, 7.5.1. 8 See California Independent System Operator Corp. v. FERC, 372 F. 3d 395, 403 (2004).
PDF page 7
7
B. The PJM Members and the Stakeholder Process
In addition to the PJM Board, PJM has a large and active Membership that has retained significant control, formally and informally, over the organization. When PJM was established, filing rights over the OA were placed in the hands of the Members Committee, and PJM practice has been to respect that allocation even when the Board would prefer a different allocation of re- sponsibility. At heart, the OA governs the organization itself akin to corporate bylaws, including key questions like Board selection and the stakeholder process. Again, FERC’s authority over such matters of internal governance is relatively minimal, but it can advocate for common sense solutions like the Board recommendations discussed above. It can also recommend an advisory stakeholder process as is common elsewhere in the country.
PPL Electric’s core transmission-related concerns are of course associated with the stake- holder process and are located in substantive schedules to the OA, particularly Schedule 6 gov- erning transmission planning. Because these are not related to PJM’s internal governance or or- ganizational design, FERC’s authority is clearer and the need for change more direct. FERC should work to facilitate the movement of these substantive provisions to the PJM Tariff where they will be under Board control.9 Beyond these issues, PPL Electric supports changes to the stakeholder process that will streamline its own decision-making and increase accountability. Ideas include reducing the number of sectors from five to three (transmission owners, power sup- pliers, and customers) to more closely match interest alignment and investment in the system.
9 PPL Electric commits to work with the other PJM transmission owners to make necessary changes to the CTOA to facilitate this change. It will also continue to pursue related and non-controversial changes to update and modernize that agreement.
PDF page 8
8
C. The Role of the States
Finally, because addressing resource adequacy will require the deregulated states to come to the table with changes to their energy policies, it is appropriate to address the elephant in the room: what should the role of the states be in PJM?
PPL Electric’s strong view remains that “the deregulated states must exercise more au- thority over generation planning and investment than they have in the past.”10 At a minimum, this will require coordination between the states and PJM beyond the level that has occurred in the past. Such coordination is essential to ensure the success of the state energy policies within the federally regulated market construct. The worst possible outcome would be for the states to make a good faith effort to expand generation, but then see that effort stymied through uncoordi- nated PJM market rules or inconsistent federal policy. PPL Electric continues to support this in- creased coordination and is open to efforts to deepen it, including more formal roles for OPSI, state executives, and other officials where appropriate.
On the resource adequacy technical conference panels last year, many voices went fur- ther, calling for a more direct and potentially controlling role for the states in PJM.11 At the time, PPL’s response called this effort a mistake for three reasons:
10 See Meeting the Challenge of Resource Adequacy in Regional Transmission Organization and Inde- pendent System Operator Regions, Docket No. AD25-7, Pre-Conference Statement of Wendy Stark on Behalf of PPL Corporation (May 16, 2025) at 3.11 See, e.g., Meeting the Challenge of Resource Adequacy in Regional Transmission Organization and In- dependent System Operator Regions, Technical Conference Transcript Volume 1, Docket No. AD25-7 (Jun. 4, 2025) at 184:4–185:5 (Chair Thompson stating “the states … need to have more rights and more say in what that capacity construct looks like”); 186:12–187:14 (Mr. Finkel stating “you don’t have … sufficient or, you know, comparatively really any state opportunity for engagement at PJM in a formal way”); 188:12–18 (President Guhl-Sadovy stating “[w]e certainly do need more of a role in the resource adequacy planning conversation at PJM”).
PDF page 9
9
•
Who speaks for the state? There are practical difficulties in securing a single voice to speak for the states collectively, or even any individual state. PJM’s re- cent experience is that governors and their staffs, public utility commissions (and individual commissioners) and their staffs, siting boards, consumer advocates,
legislators, and others have all attempted at times to speak on behalf of the state.
•
PJM does not need more gatekeepers. PJM’s process is already largely bogged
down and adding an additional layer of approval risks making the problem worse. Even the most constructive process can evolve for the worse over time. Adding to the mix 14 additional potential chokepoints, each promoting distinct (and often contradictory) energy policies, is at best a challenge.
•
States are sovereigns and not § 205 rights holders. The Federal Power Act is clear in reserving a sovereign role for the states.12 They are not given authority to file for rate changes or tariff terms under § 205.13
PPL Electric expects to hear many of the same arguments at the upcoming technical conference, likely refined into more specific requests for state control over PJM, perhaps including a request for state filing rights over the PJM Tariff. PPL Electric approaches these questions with an open mind, but reiterates the points it made earlier doubting the legal and practical arguments for state control of the RTO. It also recognizes that these types of fights get ugly quickly and can lead di- rectly to increased uncertainty in the energy markets. It’s worth saying again: the core problem
12 16 U.S.C. § 824(b)(1) (disclaiming federal jurisdiction “over facilities used for the generation of elec- tric energy or over facilities used in local distribution or only for the transmission of electric energy in in- trastate commerce, or over facilities for the transmission of electric energy consumed wholly by the trans- mitter”). 13 16 U.S.C. § 824d. See also Meeting the Challenge of Resource Adequacy in Regional Transmission Or- ganization and Independent System Operator Regions, Post-Technical Conference Comments of PPL Corporation, Docket No. AD25-7 (Jul. 7, 2025) at 12–13.
PDF page 10
10
PJM faces in 2026 is underinvestment in generation. Only state policy changes can solve this. PJM must deepen its coordination with the states, but must focus on steps that will increase in- vestment in generation. This requires it to also remain independent of state control.
III. RESPONSES TO QUESTIONS
PPL Electric provides responses to the questions being discussed at the technical confer- ence below:
A. Responses to Potential Questions: Panel 1
1. What is the PJM Board’s role in ensuring that PJM is sufficiently tackling the region’s operational and market challenges? How does the Board eval-
uate its effectiveness in that role? How often, and under what circum-
stances, does the Board act unilaterally, and should this change?
PJM’s Board sits at the center of nearly all the relevant questions facing PJM and the re- gion. First, the PJM Board controls PJM Tariff terms and conditions. This authority was dele- gated by the PJM transmission owners in the CTOA. Specifically, among other delegated re- sponsibilities, the PJM transmission owners granted the Board the power to (1) direct the opera- tion and coordinating the maintenance of their transmission facilities,14 (2) administer the PJM Tariff and provide transmission service thereunder,15 (3) conduct certain regional transmission planning,16 and (4) conduct transmission billing and payments.17 The PJM Board must act con- sistent with (A) safe and reliable operations, (B) a robust, competitive electric power market, and (C) protecting against undue influence over operations.18 It embodies PJM’s core responsibility to ensure reliable service and just and reasonable rates.
14 CTOA, §§ 4.1.2, 4.8, 6.3.1.15 CTOA, §§ 4.1.1, 4.1.3, 6.3.2.16 CTOA, §§ 4.1.4, 6.3.3, 3.4.17 CTOA, § 6.3.6.18 PJM Operating Agreement, § 7.7(i); CTOA, § 6.3.1.
PDF page 11
11
PJM’s practice has been for the Board to act in concert with its stakeholders where possi- ble. On the transmission side, PJM should certainly continue to work with its transmission own- ers, who have collectively invested tens of billions of dollars in the system and who have their own concurrent obligations to ensure reliability and just and reasonable rates. On the market side, acting by consensus, or at least with strong majority support, strengthens the Board’s hand. A successful stakeholder process provides legitimacy for the Board’s decisions, increasing the durability of market rule changes and reducing the friction to their acceptance at the Commis- sion. However, the Board must also be able to act without stakeholder support in appropriate cases. This is certainly true in emergent or emergency situations, unfortunately becoming more common as the region’s surplus generation margin continues to tighten. But it is also true where the Board reasonably determines that a lack of support stems not from concerns over reliability, but from parochial stakeholder interests or a misguided desire to affect short-term prices at the expense of long-term reliability and price stability.
Although the current Board has acted without stakeholder support at times, this level of independence is difficult to sustain given the structural restraints on the Board built into the OA. Moving to an advisory stakeholder process would reduce these constraints and empower the Board to take actions it sees as necessary, while retaining the ability of Members to advocate for their position and persuade the Board to change course. Of course, no set of governance rules can limit interested parties’ statutory right to advocate at the Commission under § 205 and § 206 of the FPA and Commission rules, rights highly relevant to those on the losing end of a Members Committee vote.
PDF page 12
12
2. How should states, through the Organization of PJM States, Inc. (OPSI) or
other structures, interface with the Board to enable the region to meet op-
erational and market challenges while respecting PJM’s independence?
Because much of the current discussion around PJM governance reform is focused on the role of the states, it may be worthwhile to start with a caveat: PJM and the other RTOs are feder- ally (FERC) regulated public utilities. They provide interstate transmission service and wholesale power sales. They do not provide retail service or generation planning, which are reserved to the states under the FPA.19 Thus, the role of the states is simply more limited than in those areas where they have direct jurisdiction. That said, the states have an important role at PJM—espe- cially the deregulated states, which are not doing integrated resource planning. This role has not always been well-defined. Now that the deregulated states face a crisis of generation planning and resource adequacy that will take serious public policy changes to address, it is absolutely ap- propriate to seek clarity and refinement in their interactions with PJM.
Even without changes, state participation at PJM is already robust. The PJM Tariff pro- vides for—with funding from PJM customers—two broad advocacy groups for state participa- tion in the stakeholder process and other PJM functions:
•
The Consumer Advocates of PJM States, Inc. (CAPS) consists of the state con-
sumer advocates from each of the PJM states. CAPS is funded through the PJM
Tariff20 and is an active participant in the stakeholder process, as are many of the consumer advocates themselves. Consumer advocates are also PJM Members,
participating (i.e., voting) in the End Use Customer sector.2119 See § 824(b)(1), Note 12, supra.20 PJM Tariff, Schedule 9-CAPS, available at https://agreements.pjm.com/oatt/26422.21 Other state entities are also PJM Members. For example, many municipalities participate in the Electric Distributors sector.
PDF page 13
13
•
The Organization of PJM States, Inc. (OPSI) consists of representatives from each of the state public utility commissions. It is also funded through the PJM Tariff22 and is an active participant in the PJM stakeholder process. Although OPSI mem- bers are not PJM Members and cannot vote in the Members Committee, OPSI
meets privately with the PJM Board pursuant to a Memorandum of Understand-
ing23 and has § 206 rights to intervene in FERC proceedings. OPSI is highly influ- ential in setting PJM policy.
In addition to these formal methods, the PJM states also interact with PJM informally through public interactions, private meetings and other communications, and various industry forums.24 Even these preliminary and informal interactions have already led to immediate and significant impacts on the PJM markets.25
There are now proposals for an additional structure for PJM to interact with the states through their governors’ energy offices. It should go without saying that the governors are key constituents of PJM. As elected executives, governors are responsible for public safety, eco- nomic development, and emergency response coordination in their states, each directly con- nected to PJM’s mission. PPL Electric applauds the governors’ attention to PJM and is
22 PJM Tariff, Schedule 9-OPSI, available at https://agreements.pjm.com/oatt/4417.23 Memorandum of Understanding between PJM Interconnection, L.L.C., and the Organization of PJM States, Inc. (Jun. 1, 2005), available at https://opsi.us/wp-content/uploads/2020/02/OPSI_PJM_MOU_ex- ecuted_June_8_2005-1-1.pdf.24 See PJM Governors’ Collaborative, Joint Statement of Intent, available at https://www.pjm.com/-/me- dia/DotCom/about-pjm/who-we-are/public-disclosures/2025/20250925-pjm-governors-collaborative- joint-statement-of-intent.pdf (identifying functions including “strategic engagement of PJM staff”).25 See Commonwealth of Pennsylvania v. PJM Interconnection, L.L.C.¸ Order Accepting Tariff Revisions and Dismissing Complaint, 191 FERC ¶ 61,066, Docket Nos. ER25-1357, EL25-46 (Apr. 21, 2025) (ac- cepting settlement establishing capacity market price collar after complaint from Pennsylvania Governor Shapiro).
PDF page 14
14
committed to working toward a structure for this interaction that empowers them and makes sense for the region.
Although there has been limited detail publicly provided, PPL Electric understands the PJM governors are working on a model based on the New England State Committee on Electric- ity (“NESCOE”). As the governors develop this concept, PPL Electric proposes some considera- tions to keep in mind:
•
More formality and structure is better. Rather than purporting to speak for a state or “the states” generally, this new entity should transparently lay out who it speaks for and under what authority. This will avoid confusion, especially given other organizations like OPSI also participate in PJM on behalf of state govern- ment. Ultimately the region may have to decide if it makes sense to have two sep- arate organizations speaking for the states.
•
State entities should be very clear as to their authority under state law. Each of the PJM states has its own constitution and each allocates power differently within its executive branch. For example, in Pennsylvania, the governor appoints the PUC commissioners, but not the consumer advocate.26 State governments should clar- ify what powers they delegate to interstate organizations like OPSI or a new state “governor committee.” It may also be advisable to limit positions in such commit- tees to officers of state government—selected by an elected official and con- firmed by a legislature pursuant to state law—rather than informal advisors.
•
The states must be extremely careful not to mix their sovereign regulatory role with their advocacy roles in the federally regulated markets. As discussed above,
26 66 Pa. C.S. § 301(a); 71 P.S. § 732‑201(b).
PDF page 15
15
the states have formal roles as regulators and public policymakers separate from their advocacy positions on federal issues. PJM is a federally regulated utility and should be extremely cautious about mixing roles or giving authority to entities that are not entitled to it under federal law.
•
Any role for the states must respect the rights and obligations of public utilities under the Federal Power Act. As noted earlier, efforts to require these rights be surrendered to other entities have been soundly rejected by the courts.27
With these considerations, PPL Electric applauds efforts to increase state participation in PJM and hopes that the Commission can identify proposals that will work for the region.
3. What governance reforms would best improve accountability and respon-
siveness?
As discussed above, PPL Electric supports limiting the Members to an advisory role, as well as certain changes to the PJM Board rules that would facilitate its independence and lead to the selection of more qualified candidates. PPL Electric is open to further discussions of matters such as resource adequacy filing rights and state involvement in PJM governance—particularly if the deregulated states amend their energy policies and need to coordinate generation planning with the PJM markets—but is cautious about proposing deep changes to PJM governance that will lead to litigation and uncertainty in the energy markets.
4. How does the division of Federal Power Act section 205 filing rights
among PJM, Transmission Owners, and the Members Committee affect
PJM’s ability to act effectively and quickly, when warranted, to address
operational and market needs?
The PJM transmission owners retained filing rights over a limited set of matters in the PJM Tariff, notably rates and rate design. This division of authority has stood the test of time
27 See Atlantic City, 295 F.3d 1, Note 6 supra.
PDF page 16
16
since initially negotiated more than 20 years ago.28 Although the substance of transmission rates and cost allocation are frequently (exhaustively) litigated,29 this merely reflects the significant investments made in regional transmission facilities rather than a problem with transmission owner filing rights. When the states have shown an interest in more direct involvement in trans- mission rates, they have been able to assert their influence even without filing rights.30 There is simply no need for a change here and no legal ability for the Commission to order one.
The PJM Transmission Owners delegated their filing rights over Tariff terms and condi- tions to PJM through the Atlantic City settlement and the CTOA.31 Unfortunately that settlement only extended to filing rights over the PJM Tariff and did not reach key PJM functions, including transmission planning and energy and capacity market administration, governed by the OA. As discussed above, the OA purports to require stakeholder approval before it can be amended through a § 205 filing. With the benefit of hindsight, placing substantive provisions under this governance structure was clearly a mistake. These provisions should be moved to the Tariff and placed under the control of the PJM Board. For example, the well-documented failure of PJM to control the Planning Protocol, located in Schedule 6 of the OA, has impeded necessary
28 Pennsylvania-New Jersey-Maryland Interconnection, 105 FERC ¶ 61,294 (2003), appeal dismissed sub nom., Old Dominion Elec. Coop. v. FERC, 171 F. App’x 862 (D.C. Cir. 2005).29 See, e.g., Consolidated Edison Co., et al., Order on Remand, Complaint, Rejecting Tariff Proposal and Settlement, Directing a Compliance Filing, and Establishing Paper Hearing Procedures, 194 FERC ¶ 61,179, Docket Nos. EL15-18, et al. (Mar. 6, 2026) (non-final order on seven open PJM cost allocation dockets dating back to 2014).30 See PJM Interconnection, L.L.C., Offer of Settlement, Docket No. EL05-121-009 (filed June 15, 2016); PJM Interconnection, L.L.C., 163 FERC ¶ 61,168 (2018), order on clarification and reh’g, 169 FERC ¶ 61,238 (2019), aff’d sub nom, Long Island Power Auth. v. FERC, 27 F.4th 705 (D.C. Cir. 2022). The states were instrumental in bringing to a close more than eleven years of litigation over cost allocation in PJM.31 See PJM CTOA, § 7.5.1(a).
PDF page 17
17
transmission planning.32 Non-transmission-owning stakeholders with various business interests in discouraging transmission development were accidentally gifted a major veto point—one they have been extremely reluctant to give up.33 Notwithstanding the recent failure of the transmission owner / PJM attempt to remedy this situation through a FERC decision which did not determine whether transferring the Planning Protocol to the Tariff was just and reasonable,34 this change remains a top priority.
To summarize: the correct principles governing the allocation of filing rights are found in the CTOA. All filing rights that a FERC-regulated public utility would have, that were not re- tained by the transmission owners, should be delegated to PJM and exercised by the Board. This includes administering the power markets and conducting resource planning (to the extent per- mitted by law). Everything transmission owners retain should be exercised by them, individually or collectively pursuant to the CTOA.
5. To what extent do provisions in PJM’s Operating Agreement, Transmis-
sion Owner Agreement, Open Access Transmission Tariff, Reliability As-
surance Agreement, or Manuals impede timely decision-making by PJM?
As discussed above, PJM should transition the stakeholders to an advisory role on sub- stantive issues. This should include moving the substantive schedules from the OA to the Tariff.
32 See Duquesne Light Company, Docket No. ER24-2338, Note 3 supra, at Exhibit C (unrebutted Declara- tion of Mr. Pulin Shah, highlighting how PJM’s inability to independently propose changes to the Plan- ning Protocol severely limited its ability to address system needs through planning).33 See Supplemental Voting Results, PJM Members Committee (May 6, 2024), available at https://www.pjm.com/-/media/DotCom/committees-groups/committees/mc/2024/20240506-annual/mc- voting-results---item-08---proposed-oa-and-tariff-revisions-effectuating-the-transfer-of-the-regional- transmission-expansion-planning-protocol.ashx at 3 (reporting vote against moving Planning Protocol to Tariff despite overwhelming transmission owner support).34 See PJM Transmission Owners, et al. v. FERC, No. 25-1064, 2026 WL 1617585 (D.C. Cir. June 5, 2026) (upholding denial of CTOA amendments because FERC could have reasonably found proposed amendment allowing transmission owners to delay PJM § 205 filing was unjust and unreasonable).
PDF page 18
18
As proposed in Docket No. ER24-2336 and related dockets, this will require amendments to the CTOA, OA, and Tariff. It may also require amendments to the RAA.
PJM should also amend the portions of the OA necessary to effect the changes to Board tenure and selection, as discussed above.
Finally, PJM should consider changes to its stakeholder process Manuals to streamline the stakeholder process. These changes do not require FERC approval, but are worth briefly ex- plaining here: PJM’s stakeholder process was designed to allow maximum openness and trans- parency. While these are important considerations and should not be casually disregarded, they can sometimes come at a real cost in terms of timeliness and efficiency. In recent years, the num- ber of consequential issues considered in the stakeholder process has risen. This has attracted more attention and increased the time and cost of participating—costs which are passed on to customers. This increased issue valence has also attracted participation of non-PJM Members, who run the gamut from academics proposing detailed changes to the energy markets to land- owners whose primary interest is protecting their real estate values and viewsheds. PJM may need to propose changes to its Manuals such as firm timelines on action. Limiting participation in certain meetings to Members therefore makes sense.
6. Recognizing regional differences, are there lessons from other regional
transmission organization/independent system operator (RTO/ISO) gov-
ernance structures that PJM could reasonably adopt to improve its respon-
siveness to the region’s operational and market challenges?
Different RTOs and ISOs evolved at different times and with different underlying rea- sons. The Commission is right to caution that they may thus require different approaches to the common problems of RTO/ISO governance. However, there are always benefits to information sharing and comparing best practices with others. Through its 2022 acquisition of The
PDF page 19
19
Narragansett Electric Company,35 now doing business as Rhode Island Energy, PPL is also a par- ticipant in the ISO-NE and NEPOOL stakeholder processes. It has gathered some lessons in New England that may be applicable in the PJM region as well:
•
A work plan provides valuable structure and guidance to the stakeholder process. ISO-NE crafts an annual work plan, where each sector can suggest two to three priorities for the coming year, with the final work plan ultimately decided upon by ISO-NE. This allows for a give-and-take on strategy before diving into any given (contentious) issue. It avoids some, but certainly not all, ambiguity about where the region intends to change direction.
•
An advisory stakeholder process lowers the temperature and allows clear guid- ance to ISO-NE. Like most other regions (other than PJM), the stakeholder pro- cess in New England is largely advisory. ISO-NE and NEPOOL members work to achieve consensus. Rather than an arbitrary voting rule falsely conveying an au- thoritative decision, the stakeholder process usually culminates in an advisory vote where ISO-NE and its Board can observe which sectors (or sometimes indi- vidual companies) support or oppose an initiative. While the ISO-NE Board pro- vides valuable input and oversight, unlike the PJM Board, it does not frequently vote on major filings and initiatives.
•
Limiting attendance to some meetings facilitates give and take. NEPOOL meeting attendance is limited to ISO-NE employees, NEPOOL members (generators, transmission owners, customer representatives, and others), ISO-NE Board
35 See PPL Corporation et al., Order Authorizing Disposition of Jurisdictional Facilities, 176 ¶ FERC 61,175, Docket No. EC21-87 (Sep. 23, 2021).
PDF page 20
20
members, and approved guests. Because almost everyone is an experienced player and understands the “rules” of participating, there is more frank, honest discus- sion that leads to better outcomes than in the PJM stakeholder process.
•
More informal meetings foster personal connection. NEPOOL sector meetings are held throughout the year with policymakers, ISO-NE senior staff, and ISO-NE
Board members. This also allows for personal connections and more open dia-
logue than regularly occurs in PJM.
B. Responses to Potential Questions: Panel 2
1. Do sector-weighted voting and existing voting thresholds strike the right
balance between achieving consensus and taking timely action?
The PJM Members Committee rules require a weighted supermajority to act. This pro- vides formal limits on PJM’s ability to amend the OA, including its substantive schedules. PJM practice is to follow Members Committee direction in most circumstances where it is not re- quired as well, providing an informal but real check on its ability to amend Tariff terms and con- ditions, Manuals, and the RAA. This gives veto power to a relatively small set of stakeholders.36 The stakeholder voting threshold was made deliberately high to require an effort to reach consen- sus. It has prevented both good and bad filings, although until fairly recently, PJM was generally able to navigate the process despite the restriction.
More recently, it has become apparent that changes need to be made to PJM governance, including at least some change to Member voting. Such changes should focus on making the stakeholder process advisory overall, reducing the ability of minority stakeholder coalitions to veto actions, but also reducing the ability of majority coalitions to ram through bad policies over
36 See PJM OA, § 8.4 (defining Members Committee voting structure and requiring 2/3 majority of weighted vote to act, thus allowing 1/3 to block).
PDF page 21
21
PJM’s objection. Everyone will of course still retain the ability to provide information and argu- ment for why their preferred policy is best, and to participate fully at FERC, but PJM and its Board will be empowered to make a decision as to what to file.
Other potential changes, in addition to or perhaps instead of, a move to advisory voting can also be considered. For example, the five sectors of the Members Committee (transmission owners, generation owners, distributors, end-use-customers, and other suppliers) are largely arbi- trary and reflect overlapping interests with an overemphasis on customer voting that is not con- sistent with the FPA’s overall regulatory scheme (where utilities have unilateral power to file at FERC and customers and other stakeholders are given significant rights in the regulatory process itself). A more streamlined model, still a compromise from the statutory scheme, would reduce the membership to three sectors (transmission owners, power suppliers, and customers), better reflecting the real dynamics of PJM and providing clearer guidance to the Board as to how a given policy will be received.37
Other more afield ideas include dividing the Tariff into subject areas with different stake- holders having more or less influence over those areas depending on interest or investment level. (TOs would continue to have more say over transmission issues, generators more say over the power markets, etc.) This is more complex and will likely be difficult to implement, so it may not be the optimal path to begin with.
37 This change is best imagined in an advisory stakeholder process where the actual voting power of any given sector is less relevant, but may be even more necessary if the Members Committee retains its exist- ing veto points. It is highly destabilizing for customers (who do not own any jurisdictional assets) to be able to unilaterally veto a proposed change to the Tariff without having to persuade a regulator the change is not just and reasonable.
PDF page 22
22
2. What transparency reforms would improve the quality of PJM’s stake-
holder process and increase stakeholder confidence in its decision-mak-
ing?
Transparency is a useful metric for an organization as important as PJM, but increased transparency is unlikely to lead to an improvement in the quality of the process or increased con- fidence in the decision-making. When FERC created ISOs in Order 88838 (and later refined the concept in an RTO in Order 2000),39 it placed great emphasis on creating an independent organi- zation that nevertheless was open to input from its many stakeholders and largely operated in a transparent process.40 With 25 years of experience, PJM’s processes have been shown to be very open and transparent, with the current risk being too many “cooks in the kitchen” to produce a viable product. Instead of forcing additional openness that may impact the ability to have tough conversations and incentivize appropriate stakeholder compromises, PJM should focus on its goals of reliability and just and reasonable rates. PJM governance reform should be deemed a success if we achieve better outcomes on those metrics, rather than seeking additional transpar- ency for its own sake.
3. Are there structured opportunities in the stakeholder process for state par- ticipation (e.g., defined consultation windows, joint technical sessions) to
provide input on topics that are of interest to the states?
As discussed above in response to Panel 1, Question 2 (incorporated herein by reference), there are already numerous formal structures for state participation in PJM. State Consumer Ad- vocates and municipalities participate directly in the stakeholder process as Members, and some
38 Promoting Wholesale Competition Through Open Access Non-Discriminatory Transmission Servs. by Pub. Utils.; Recovery of Stranded Costs by Pub. Utils. & Transmitting Utils., Order No. 888, FERC Stats. & Regs. ¶ 31,036 (1996), aff’d in relevant part sub nom. Transmission Access Policy Study Grp. v. FERC, 225 F.3d 667 (D.C. Cir. 2000), aff’d sub nom. New York v. FERC, 535 U.S. 1 (2002).
39 Reg’l Tran. Orgs., Order No. 2000, FERC Stats. & Regs. ¶ 31,089 (1999).40 Although transparency is not actually named as an RTO characteristic in Order 2000 and we should be careful about imputing it as a requirement where it is not.
PDF page 23
23
have customer-funded organizations like CAPS to further facilitate this participation. Likewise, OPSI provides a similar service (again funded by PJM customers) for the state public utility commissions, including meetings with the PJM Board. OPSI also has direct access to the PJM Board via its Memorandum of Understanding.41
4. Do existing governing document provisions (e.g., Operating Agreement,
Manuals) impede stakeholder decision-making and what changes could be
made to address them?
Stakeholder decision-making is not the goal. The goal is reliable operations at just and reasonable prices.
As to the details of the governing documents and how stakeholders can act to influence policy, there is likely no perfect solution. PJM’s consensus-based issue resolution (CBIR) pro- cess was designed by experts in the field and has been continuously refined over many years to maximize opportunities for input. Over time, as stakeholders have formalized their participation, they have rationally become more firmly set in their opinions and unwilling to compromise on positions—which are based on the very real financial interests of their companies. Many issues in the stakeholder process simply come down to issues where no consensus can reasonably be reached: should prices be high or low? Should the region prioritize transmission investment or generation investment? Should the region favor state-specific clean energy programs that are not endorsed by other states in the region? No process document, no matter how refined, can elimi- nate the disagreements that exist over these issues or the interest of Members in advocating their positions.
Instead, the Members should select an impartial Board to make the hard decisions neces- sary to operate a public utility and energy market as large and as complex as PJM. Members and
41 See OPSI MOU, Note 23, supra at 3.
PDF page 24
24
other stakeholders would remain free to advocate their positions to this Board, through whatever formal or informal processes exist. And they can provide significant expertise in the details of implementation and market design. But asking a diverse set of stakeholders with directly com- peting interests to decide major important questions is simply setting the region up for stagnation and ultimately failure.
5. What reforms to the stakeholder process could ensure PJM can meet the
region’s challenges?
First and foremost, the stakeholder process that currently hamstrings many PJM decisions should be made advisory. The Board of Managers should run the organization, with the stake- holders providing input and expertise, but not deciding major questions.
Other questions, like who participates in the stakeholder process, what questions are pre- sented to it, how long everyone can speak, how long the process overall can continue, etc. are important details that do not need to be dictated by the Commission and may be initiated via a separate PJM-initiated stakeholder process reform effort following these proceedings. These de- tails will follow if the Board is able to exert its independence over critical decisions through the OA and RAA.
6. What near-term reforms to stakeholder representation could PJM and its
Members take to improve speed in decision-making while preserving
stakeholder input?
Speed in decision-making is not the goal. PJM’s mission is reliable operations at just and reasonable prices. To the extent PJM needs to speed its decision-making process, that largely falls on the Board who is ultimately responsible for the RTO.
To the extent the Board is hindered by the stakeholder process, reforms should remove that hinderance by making the stakeholders advisory. Other reforms, like reducing the number of sectors, are discussed above. There are certain formal changes to the OA that are necessary for
PDF page 25
25
such changes, but ultimately PJM’s culture needs to change to allow more independent action by the Board where necessary.
7. Are there elements of PJM’s committee structure that routinely contribute
to delays? Are there stakeholder processes or issues that could be expe-
dited or changed to provide greater focus on key issues and allow faster or
more unilateral action on others?
PJM’s lower committees have been rendered largely irrelevant because the voting rules at the Senior Standing Committees (Markets and Reliability Committee and Members Committee) have different voting structures. Stakeholders who are more empowered by the MRC/MC rules often refuse to engage in the lower committees, where they will be out-voted due to affiliate vot- ing rules, and instead save their substantive participation for the end of the process where they have more influence. The result is an extended stakeholder process, with detailed issue charges, problem statements, stakeholder education, interest identification, package design, and compro- mise voting—all of which takes significant time and investment—being thrown out after months (sometimes, years) of work and replaced by the preferred outcome of the working stakeholder majority. The result is a lengthy and inefficient process that does not result in a viable product, because PJM or key stakeholders cannot accept the majority package which is the result of the arbitrary Members Committee voting rules rather than reasoned decision-making.
Again, the details can always be improved to speed the process and create better out- comes, but the fundamental problem is the veto points built into the Members Committee voting rules. If the PJM Board were the ultimate decider, the process would simply work differently. In- stead of trying to reach a winning vote in an arbitrary process, the stakeholders would instead fo- cus on honing their market designs (or other proposed tariff changes) with an eye toward per- suading an independent decision-maker (first the PJM Board, and ultimately the Commission).
PDF page 26
26
8. Should PJM increase the use of fast-path or time-bound review procedures
to expedite committee action on high-importance topics?
Yes, where appropriate. These processes are an important tool and should remain in the toolbox. They have developed something of a stigma in the stakeholder process because they are looked at as an “end-run” around the more deliberative “proper” process. But in many cases, they are the only way for PJM to arrive at a decision fast enough to respond to market needs.
Again, the better solution is to empower the Board to act independently and convert the stakeholder process into an advisory process. When the stakeholders know the Board will make a decision on a given timeline, they work toward the deadline to advocate and educate and will be less incentivized to use the stakeholder process to strategically delay action.
9. Recognizing regional differences, are there lessons from other RTO/ISO
stakeholder processes that PJM could reasonably adopt to improve speed
in voting processes and stakeholder representation?
As discussed above in response to Panel 1, Question 6 (incorporated herein by reference), the ISO-NE and NEPOOL stakeholder processes work in a different context that cannot be di- rectly translated to PJM, but nevertheless there are some lessons that can be drawn from them, including creating a work plan, moving to an advisory stakeholder process, limiting attendance to certain meetings, and increasing opportunities for informal discussion.
PDF page 27
27
IV. CONCLUSION
PPL Electric thanks the Commission for raising these important topics and asks that its comments be considered part of the record.
Respectfully submitted,
Steven M. Nadel
Senior Counsel
PPL Services Corp.
645 Hamilton Street, Suite 601
Allentown, PA 18101
Tel. 610.774.4775
SMNadel@pplweb.com
Counsel for PPL Electric Utilities Corp.
July 22, 2026