ER26-3552-000 · 2026-08-18 · Midcontinent Independent System Operator, Inc.

Tab D - Redline ZGIA to pro forma GIA.pdf

Contents · 12 sections
  1. A. Constructing MISO Transmission Owner p. 151
  2. B. SPP: p. 151
  3. A. Interconnection Customer Milestones p. 152
  4. B. Transmission Owner Milestones p. 157
  5. C. Affected System Owner Milestones p. 159
  6. A. General p. 166
  7. B. Response to Abnormal Conditions p. 167
  8. C. Reactive Power p. 168
  9. D. Primary Frequency Response p. 169
  10. E. Supervisory Control and Data Acquisition (SCADA) Capability p. 171
  11. F. Disturbance Monitoring and Reporting Requirements p. 171
  12. G. Applicability p. 173

Read the parent filing

Read topic-matched comments in ER26-3552

Topics in the text: Connecting load and generation · Registry access · Reliability and curtailment

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Connecting load and generation

Surplus Interconnection Service shall mean any Interconnection Service that is derived from the unneeded portion of Interconnection Service established in a GIA or in agreement with, or under the tariff of, a Transmission Owner prior to integration into MISO, such that if Surplus Interconnection…
Read this passage Filed comments: Connecting load and generation

A. Constructing MISO Transmission Owner

printed heading

Constructing MISO Transmission Owner 1. ______________ 2. ______________ 3. ______________ 4. ______________
Read this passage

B. SPP:

printed heading

Selected Option pursuant to Article 5.1: Interconnection Customer selects the [_____________] Option as described in Article 5.1.[ ], 5.1.[ ] and 5.1.[ ] shall not apply to this GIAZGIA. 2.
Read this passage

A. Interconnection Customer Milestones

printed heading · Topic match: Connecting load and generation

Enter into amendment of this GIAZGIA, if required, for Interconnection Requests that did not elect optional negotiation period adjustment for Interconnection Facilities Study pursuant to GIAZGIA Section 11.3.1.
Read this passage Filed comments: Connecting load and generation

B. Transmission Owner Milestones

printed heading

Transmission Owner to enter Network Upgrade information into Transmission Provider’s MTEP database and model on demand. 10 Business Days after Effective Date.
Read this passage

C. Affected System Owner Milestones

printed heading

Transmission Owner shall provide the following “as-built” drawings, information and documents regarding the Transmission Owner’s Interconnection Facilities pursuant to Article 5.11 of this GIAZGIA. 2.
Read this passage

A. General

printed heading

General The IBR plant shall adhere to IEEE 2800-2022 Clause 4 requirements, except for subclauses 4.1 (introduction), 4.5 (operational measurement and communication capability), 4.6 (control capability requirements), 4.8 (isolation devices), 4.9 (inadvertent energization of TS), 4.11…
Read this passage

B. Response to Abnormal Conditions

printed heading

Response to Abnormal Conditions The IBR plant shall adhere to IEEE 2800-2022 Clause 7 requirements, except for subclauses 7.2.1 (voltage protection) and 7.3.1 (mandatory frequency tripping).
Read this passage

C. Reactive Power

printed heading

Reactive Power The IBR plant shall adhere to IEEE 2800-2022 Clause 5 requirements.
Read this passage

D. Primary Frequency Response

printed heading

Primary Frequency Response The IBR plant shall adhere to IEEE 2800-2022 Clause 6 requirements, except for Subclause 6.2 (fast frequency response).
Read this passage

E. Supervisory Control and Data Acquisition (SCADA) Capability

printed heading · Topic match: Reliability and curtailment

Transmission Provider and Interconnection Customer shall determine what SCADA information is essential for the proposed IBR plant, taking into account the size of the plant and its characteristics, location, and importance in maintaining generation resource adequacy and transmission system…
Read this passage Filed comments: Reliability and curtailment

F. Disturbance Monitoring and Reporting Requirements

printed heading

Disturbance Monitoring and Reporting Requirements IBR plants with generating capacities of more than 20 MW must monitor and record data for all frequency ride-through events, transient low-voltage disturbances that initiated reactive current injection, reactive current injection or momentary…
Read this passage

G. Applicability

printed heading · Topic match: Connecting load and generation

MISO Attachment X: Appendix 619 FERC Electric Tariff GeneratorZG Interconnection Agreement (GIAZGIA) ATTACHMENTS 11031.0.0 Appendix I to GIAZGIA Requirements Applicable to Surplus Interconnection Service Where this GIAZGIA provides for Surplus Interconnection Service, Interconnection Customer…
Read this passage Filed comments: Connecting load and generation