ER27-527-000 · 2026-11-16 · Midcontinent Independent System Operator, Inc.

MISO files the Grid Responsive Integration Transmission Service under section 205

MISO files tariff revisions under section 205 on November 16, 2026, in a new docket, ER27-527-000, creating the Grid Responsive Integration Transmission Service (GRITS). It is a permanent mix of firm and non-firm contract demand service for large loads willing to limit their withdrawals. MISO says it cannot run before January 1, 2029.

Asks FERC to: Accept the revisions effective March 16, 2027, 120 days after filing, with implementation in early 2029.

Filed under section 205 to answer the E-8 show cause order's call for a permanent contract demand service for flexible loads in MISO.

E-8 MISO: Show cause or propose tariff changes in 60 days (p. 5) E-8 MISO: Services for flexible / co-located loads (P 6(d), p. 7) E-8 MISO: Alternative transmission technologies (P 119, p. 74)

Key points

  1. GRITS is a permanent firm and non-firm contract demand service for large loads that can cut their withdrawals.
    GRITS provides a permanent firm and non-firm contract demand-based, Transmission Service option for Large Loads willing and able to limit their withdrawals under specified price and reliability conditions. PDF p. 1
  2. MISO says it answers FERC's concern that no permanent contract demand service exists in MISO.
    the need for a permanent contract demand transmission service in the MISO region PDF p. 2
  3. The earliest start is January 1, 2029, because of software changes.
    the earliest MISO will be able to implement GRITS is January 1, 2029 PDF p. 2
  4. Example: a 500 MW load could take 200 MW firm and 300 MW non-firm.
    a Large Load Transmission Customer representing a Large Load of 500 MW may desire to only take 200 MW of firm transmission service PDF p. 4
  5. Customers need not move toward firm service.
    does not require the Large Load Transmission Customer to progress toward firm service for any or all of its GRITS Load Limit PDF p. 3
  6. GRITS is not limited to loads served by a co-located generator.
    is not limited to Large Load being served by a co-located generator PDF p. 4
  7. Rates are still being developed with the transmission owners.
    to continue the development of rates applicable to GRITS in concert with the MISO Transmission Owners PDF p. 2
  8. A customer must request GRITS through the Large Load Project Review, the same study route as other large-load service.
    A Large Load Transmission Customer must request GRITS through the applicable LLPR process PDF p. 4
Contents · 22 sections
  1. I. EXECUTIVE SUMMARY p. 2
  2. II. BACKGROUND p. 3
  3. III. PROPOSED GRITS SERVICE p. 4
  4. A. Eligibility, service quantities, and agreements. p. 4
  5. B. Reservations and service priority. p. 5
  6. C. Transmission charges and gross-load billing. p. 5
  7. D. Price-based interruption. p. 6
  8. E. Reliability based Curtailment and enforcement. p. 7
  9. F. Resource Adequacy, ARR Entitlements, and market participation. p. 8
  10. G. Planning and commercial model treatment. p. 9
  11. IV. Response to the Show Cause Order p. 9
  12. V. DESCRIPTION OF PROPOSED TARIFF REVISIONS p. 10
  13. A. Definitions p. 11
  14. B. Module B p. 12
  15. Attachment F-1 p. 15
  16. Attachment G-1 p. 15
  17. VI. STAKEHOLDER ENGAGEMENT p. 15
  18. VII. DOCUMENTS SUBMITTED IN THIS FILING p. 16
  19. VIII. EFFECTIVE DATE AND REQUEST FOR CONTINUED ABEYANCE p. 16
  20. IX. COMMUNICATIONS p. 17
  21. X. NOTICE AND SERVICE p. 17
  22. XI. CONCLUSION p. 18

Topics in the text: Reliability and curtailment · Filing procedure · Connecting load and generation

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

MISO requests that the Commission accept the proposed revisions effective 120-days from the date of this filing (i.e., March 16, 2027) in order to facilitate MISO’s development of software 1 This filing is made pursuant to section 205 of the Federal Power Act (“FPA”), 16 U.S.C. § 824d, and Part 35…
Read this passage

I. EXECUTIVE SUMMARY

printed heading · Topic match: Cost allocation

MISO recognizes the desire for the proposed service as noted by certain stakeholders and agrees that GRITS must provide a reliable and workable path for customers that elect permanent contract demand-based firm and/or non-firm transmission service and is committed to implementation of GRITS…
Read this passage

II. BACKGROUND

printed heading · Topic match: Connecting load and generation

GRITS addresses both of these needs as it provides the Large Load Transmission Customer the option to determine the appropriate combination of firm and non-firm contract demand transmission services needed to meet its operational needs, but does not require the Large Load Transmission Customer to…
Read this passage

III. PROPOSED GRITS SERVICE

printed heading

III.
Read this passage

A. Eligibility, service quantities, and agreements.

PDF bookmark

A Large Load Transmission Customer must request GRITS through the applicable LLPR process and will be required to execute a GRITS Service Agreement and a GRITS Operating Agreement specifying the quantities, operational limits, communications, and control requirements.
Read this passage

B. Reservations and service priority.

PDF bookmark · Topic match: Reliability and curtailment

Reservation priority determines the order in which requests are evaluated; curtailment priority determines which existing service is reduced when the system cannot support scheduled use.
Read this passage

C. Transmission charges and gross-load billing.

PDF bookmark

Co-located generation serving a Large Load receiving GRITS service must be registered as a Generation Resource, and the Large Load Transmission Customer must procure Transmission Service to receive service from the co-located resource.
Read this passage

D. Price-based interruption.

PDF bookmark

Non-Firm GRITS will be interrupted when the Locational Marginal Price at its CPNode exceeds the GRITS Offer Cap, which is $100/MWh.
Read this passage

E. Reliability based Curtailment and enforcement.

PDF bookmark · Topic match: Reliability and curtailment

Xie explains how Resource Adequacy is maintained if the Non-Firm GRITS Load is excluded from the Planning Resource Auction because the GRITS Offer Cap will ensure these Loads are curtailed whenever LMP rises above the GRITS Offer Cap.10 In the event a Capacity Advisory declaration is made while LMP…
Read this passage

F. Resource Adequacy, ARR Entitlements, and market participation.

PDF bookmark · Topic match: Reliability and curtailment

Resource Adequacy, ARR Entitlements, and market participation.
Read this passage

G. Planning and commercial model treatment.

PDF bookmark

The firm component of GRITS Load is included in ongoing MISO Transmission Expansion Plan (“MTEP”) planning, while the total GRITS Load remains subject to applicable Interconnection Reliability Requirements (“IRR”) and stability review.
Read this passage

IV. Response to the Show Cause Order

PDF bookmark · Topic match: Reliability and curtailment

RESPONSE TO THE SHOW CAUSE ORDER Section 205 requires jurisdictional rates and practices to be just and reasonable and prohibits undue preferences and unreasonable differences in service.15 GRITS ties the Transmission Customer’s rights to the service it requests: firm quantities retain firm…
Read this passage

V. DESCRIPTION OF PROPOSED TARIFF REVISIONS

printed heading · Topic match: Reliability and curtailment

Conforming revisions to Module C of the Tariff implement separate commercial model representation requirements, establish ARR eligibility only for Firm GRITS, establish Resource Adequacy treatment, participation restrictions, and the co-located ZG Resource accreditation interface.
Read this passage

A. Definitions

printed heading · Topic match: Reliability and curtailment

Definitions MISO proposes the following, new definitions for GRITS: Firm Grid Response Integration Transmission Service (Firm GRITS): The amount of firm Transmission Service that is reserved and/or scheduled to a specific Point(s) of Delivery pursuant to the Form of Service Agreement for GRITS.
Read this passage

B. Module B

printed heading · Topic match: Reliability and curtailment

Tariff Section Tariff Section Title Brief Description of changes Module B 37B.1 GRITS Term Establishes the minimum service terms for Firm GRITS and Non-Firm Grits 37B.2 GRITS Reservation Priority Establishes the reservation priority for Firm GRITS and Non-Firm GRITS relative to other Transmission…
Read this passage

Attachment F-1

printed heading

Attachment F-1 Form of Service Agreement for Grid Responsive Integration Transmission Service Form of Service Agreement for GRITS and related exhibits including specification sheets.
Read this passage

Attachment G-1

printed heading

Attachment G-1 Form of GRITS Operating Agreement for Grid Responsive Integration Transmission Service Form Operating Agreement for GRITS service.
Read this passage

VI. STAKEHOLDER ENGAGEMENT

printed heading · Topic match: Reliability and curtailment

Stakeholders addressed how the proposed services would differ in rates, curtailment priority, resource adequacy treatment, and ARR eligibility.
Read this passage

VII. DOCUMENTS SUBMITTED IN THIS FILING

printed heading

DOCUMENTS SUBMITTED IN THIS FILING In addition to this Transmittal Letter, this submission includes the following materials, with the final tab and exhibit designations identified in the filing index: Tab A – Redline Tariff29 Tab B – Clean Tariff Tab C – Testimony of Zhaoxia Xie
Read this passage

VIII. EFFECTIVE DATE AND REQUEST FOR CONTINUED ABEYANCE

printed heading · Topic match: Filing procedure

EFFECTIVE DATE AND REQUEST FOR CONTINUED ABEYANCE MISO requests an effective date 120-days from the date of this filing (i.e., March 16, 2027), with implementation of GRITS to begin January 1, 2029.
Read this passage

IX. COMMUNICATIONS

printed heading

COMMUNICATIONS MISO respectfully requests waiver of Rule 203(b)(3) of the Commission’s Rules of Practice and Procedure, 18 C.F.R. § 385.203(b)(3) (2026), to the extent necessary to permit the designation of more than two persons for service on behalf of MISO in this proceeding and requests all…
Read this passage

X. NOTICE AND SERVICE

printed heading · Topic match: Filing procedure

Operator, Inc., 196 FERC P 61,133, at PP 8-9 (2026) (“Abeyance Order”).
Read this passage

XI. CONCLUSION

printed heading

CONCLUSION For all of the foregoing reasons, MISO respectfully requests that the Commission accept this filing and grant waiver of any Commission regulations the Commission deems in order for the Commission to accept it as proposed.
Read this passage