PJM requests more time to answer the June 18 show cause order
PJM moves to hold the E-7 show cause proceeding in abeyance for 90 days from August 17, 2026 so it can develop a section 205 filing alongside its co-located load compliance work, with stakeholder sessions and an October 28 advisory vote.
Asks FERC to: Grant a 90-day abeyance starting August 17, 2026, shorten the answer period to five days, and rule by August 6, 2026.
Asks to defer the E-7 60-day show cause response, tying it to the E-2 co-location compliance order and its Interim NITS service. FERC granted the abeyance on August 14, 2026.
E-7 PJM: Show cause or propose tariff changes in 60 days (p. 7) E-2 PJM: Interim NITS (P 2, p. 3) E-7 PJM: 30-day report on serving large loads with adequate generation (p. 8)
Key points
- PJM seeks a 90-day abeyance because the show cause reforms build on co-located load compliance changes.
Many of the changes contemplated in the Large Load Order will build upon compliance changes recently ordered for Co-Located Load in Docket Nos. EL25-49-000, et al. PDF p. 1
- PJM expects its section 205 filing in early to mid-November.
PJM anticipates submitting that filing by early to mid-November. PDF p. 2
- The overlap covers expanded transmission services, study procedures and operational requirements.
(1) expansion of new transmission services; (2) study procedures; and (3) operational requirements. PDF p. 4
- PJM's planned filing covers study processes with alternative transmission technologies, cost shifting and transparency, flexible load services, and proximate generation study.
achieve efficient transmission service application and study processes, including through the consideration of alternative transmission technologies PDF p. 6
- PJM schedules stakeholder sessions on July 30, August 18 and September 16, with an advisory vote on October 28, 2026.
with the goal of taking an advisory stakeholder vote on the proposal at the meeting of the Members Committee on October 28, 2026 PDF p. 7
Contents · 8 sections
Read topic-matched comments in EL26-67
Topics in the text: Filing procedure · Connecting load and generation · Cost allocation
Elsewhere in the record
Other parties on the same questions, in their own documents.
- Constellation supported more time with a condition Constellation Energy Generation
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Filing procedure
This development, however, must be done in conjunction with PJM’s already ongoing efforts to implement changes directed by the Order on Rehearing, Clarification, Compliance Filing, and Paper Hearing (“Compliance Order”) in the PJM Co-Located Load proceeding. 4 Many of the changes contemplated in…Read this passage Filed comments: Connecting load and generation
I. background
PDF bookmark
I.Read this passage
A. Large Load Order
PDF bookmark · Topic match: Cost allocation
Large Load Order The Large Load Order is an important component of the Commission’s ongoing efforts to efficiently and cost effectively integrate large loads with the transmission system.7 The Large Load Order found that several aspects of PJM’s Tariff appeared unjust and unreasonable due to the…Read this passage Filed comments: Cost allocation
B. Co-Located Load Proceeding
PDF bookmark · Topic match: Connecting load and generation
Co-Located Load Proceeding Also on June 18, 2026, the Commission issued the Compliance Order in the PJM Co-Located Load proceeding.15 The Compliance Order accepted most of PJM’s proposed Tariff changes, but directed that PJM make a number of additional changes within sixty days.16 Among other…Read this passage Filed comments: Connecting load and generation
C. Overlap Between Proceedings
PDF bookmark · Topic match: Connecting load and generation
Third, the Compliance Order directed PJM to revise the Tariff to provide additional detail regarding the operational requirements and necessary control technologies to be employed for customers taking new transmission services on behalf of Eligible Load.25 Similarly, the Large Load Order directed…Read this passage Filed comments: Connecting load and generation
D. Compliance Plan
PDF bookmark · Topic match: Connecting load and generation
Among other things, PJM’s intended FPA section 205 filing will advance a proposal that delivers faster and more flexible processes that also: (1) achieve efficient transmission service application and study processes, including through the consideration of alternative transmission technologies; (2)…Read this passage Filed comments: Connecting load and generation
II. motion to hold proceeding in abeyance
PDF bookmark · Topic match: Filing procedure
MOTION TO HOLD PROCEEDING IN ABEYANCE PJM respectfully requests the Commission hold this proceeding in abeyance for ninety days to allow PJM adequate time to develop a section 205 filing to respond to the 29 Donnie Bielak, Show Cause Order for Large Loads Conceptual Approach: Co-Located Load Order…Read this passage Filed comments: Connecting load and generation
III. REQUEST FOR SHORTENED ANSWER PERIOD AND EXPEDITED TREATMENT
PDF bookmark · Topic match: Filing procedure
REQUEST FOR SHORTENED ANSWER PERIOD AND EXPEDITED TREATMENT PJM respectfully requests that the Commission shorten the answer period for this motion to five days and grant expedited treatment to issue an order ruling on the abeyance motion within ten days, by August 6, 2026.Read this passage
IV. conclusion
PDF bookmark · Topic match: Filing procedure
Porter Craig Glazer Vice President – Federal Government Policy PJM Interconnection, L.L.C. 1200 G Street, NW, Suite 600 Washington, DC 20005 (202) 423-4743 (202) 393-7741 craig.glazer@pjm.com Wendy B.Read this passage
CERTIFICATE OF SERVICE
printed heading
Dated at Washington, D.C., this 28th day of July 2026. /s/ Ruth M.Read this passage