SPP requests more time to answer the June 18 show cause order
SPP and a group of transmission owners (Joint Movants) move for a 95-day abeyance of the EL26-68 show cause proceeding, to November 20, 2026, and describe the section 205 revisions SPP plans on alternative technologies, cost shifting, co-location and flexible-load service.
Asks FERC to: Hold the proceeding, including the briefing questions deadline, in abeyance for 95 days through November 20, 2026, with a five-day answer period and prompt action.
Invokes the E-9 abeyance option and previews SPP's section 205 package on the order's alternative-technology, cost-recovery, co-location and flexible-load directives.
E-9 SPP: Show cause or propose tariff changes in 60 days (p. 5) E-9 SPP: Evaluate alt tech by default (P 46, p. 52) E-9 SPP: Cost-recovery + crediting (Ordering (B)(1)(b), p. 21) E-9 SPP: New services for flexible loads (Ordering (B)(1)(d), p. 22)
Key points
- Joint Movants ask for 95 days, five more than the order contemplates, to fit SPP's Board meeting.
The additional five (5) days is necessary to accommodate SPP's full stakeholder process, which culminates in a scheduled Board of Directors PDF p. 3
- SPP will add alternative transmission technology evaluation to its HILL study process, which does not now require it.
it does not currently require SPP to evaluate alternative transmission technologies when studying HILLs. PDF p. 9
- SPP will revise pro forma NITS and point-to-point service agreements to carry HILL operational requirements.
to develop revisions to the Tariff's pro forma transmission service agreements PDF p. 10
- The CARE Team is weighing financial security, direct assignment of upgrade costs and minimum contributions from customers serving large loads.
direct assignment, in whole or in part, of Network Upgrade costs associated with large load delivery point additions or modifications PDF p. 13
- On co-location and behind-the-meter generation, stakeholders must settle terminology, the study process and overlap among transmission, interconnection and market registration.
the overlap between transmission service, interconnection, and market registration requirements. PDF p. 15
- Price Adaptive Load Service would create non-firm service with usage-based pricing and mandatory dispatchability.
PALS would establish a new transmission service under which participating loads would receive transmission service subject to usage-based pricing, mandatory dispatchability requirements PDF p. 16
- Working group votes run September and October, MOPC in October, RSC in November, and the Board on November 17, 2026.
culminating in working group votes during September and October, MOPC in October, the RSC where applicable in November, and final Board consideration on November 17, 2026. PDF p. 17
Contents · 12 sections
- I. INTRODUCTION
- II. GOOD CAUSE EXISTS TO HOLD THIS PROCEEDING IN ABEYANCE
- III. SPP’S STAKEHOLDER PROCESS NECESSITATES ADDITIONAL TIME
- IV. ANTICIPATED SECTION 205 FILING
- A. Transmission Service to Eligible Customers on Behalf of Large Loads
- B. Cost Shifting Risk Among Transmission Customers
- C. Co-Location Arrangements and Load with Behind-The-Meter
- D. Extending New Transmission Services to Eligible Customers Taking
- V. OVERALL SCHEDULE AND ANTICIPATED SECTION 205 FILING
- VI. REQUEST
- VII. CONCLUSION
- C. Patrick Woods
Read topic-matched comments in EL26-68
Topics in the text: Filing procedure · Cost allocation · Connecting load and generation
Elsewhere in the record
Other parties on the same questions, in their own documents.
- Missouri supports five extra days to secure a state review Missouri Public Service Commission
- SPP’s state committee wanted time to develop a cost proposal SPP Regional State Committee
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Filing procedure
EL26-68-000 JOINT MOVANTS’ MOTION TO HOLD SECTION 206 PROCEEDING IN ABEYANCE Southwest Power Pool, Inc. (“SPP”), American Electric Power Service Corporation, Evergy, Inc., GridLiance High Plains LLC, ITC Great Plains, LLC, Mountrail-Williams Electric Cooperative, NextEra Energy Transmission…Read this passage Filed comments: Filing procedure
I. INTRODUCTION
printed heading · Topic match: Filing procedure
Specifically, the Commission states that it: will consider requests from SPP and/or the Transmission Owners to hold, for up to 90 days, all or certain aspects of this FPA section 206 proceeding in abeyance, including the deadline to respond to this order.Read this passage Filed comments: Filing procedure
II. GOOD CAUSE EXISTS TO HOLD THIS PROCEEDING IN ABEYANCE
printed heading · Topic match: Filing procedure
GOOD CAUSE EXISTS TO HOLD THIS PROCEEDING IN ABEYANCE Good cause exists to grant the Joint Movants' abeyance request.Read this passage Filed comments: Filing procedure
III. SPP’S STAKEHOLDER PROCESS NECESSITATES ADDITIONAL TIME
printed heading · Topic match: Filing procedure
By contrast, the requested ninety-five (95) day abeyance will permit, although still on an expedited time frame, SPP to convene the necessary stakeholder meetings, develop and refine draft revisions to the Committee, comprising a committee or working group that is charged with specific…Read this passage Filed comments: Filing procedure
IV. ANTICIPATED SECTION 205 FILING
printed heading · Topic match: Filing procedure
ANTICIPATED SECTION 205 FILING Unlike a typical request to defer a procedural deadline, the Commission expressly directed respondents seeking abeyance to provide a detailed description of the anticipated Tariff revisions that would be developed during the requested abeyance period.12 Consistent…Read this passage Filed comments: Filing procedure
A. Transmission Service to Eligible Customers on Behalf of Large Loads
printed heading · Topic match: Filing procedure
High Impact Large Loads must register as such in accordance with Attachment AE of the Tariff and follow the processes specified in Attachment BA of the Tariff.”. 16 Tariff, Attachment BA. 17 Tariff, Attachment BA, Section 2.1.3.4.Read this passage Filed comments: Filing procedure
B. Cost Shifting Risk Among Transmission Customers
printed heading · Topic match: Cost allocation
Cost Shifting Risk Among Transmission Customers The Commission preliminarily found that the Tariff is unjust and unreasonable because it does not require the public posting, of information regarding transmission 19 Show Cause Order at P 46. 20 Id. 21 Tariff, Attachment F. 22 Tariff, Attachment A.…Read this passage
C. Co-Location Arrangements and Load with Behind-The-Meter
printed heading · Topic match: Connecting load and generation
Co-Location Arrangements and Load with Behind-The-Meter Generation The Commission preliminarily found that the Tariff should provide greater clarity regarding the treatment of co-located29 resources and behind-the-meter generation, including the circumstances under which such resources are subject…Read this passage
D. Extending New Transmission Services to Eligible Customers Taking
printed heading · Topic match: Reliability and curtailment
Correspondingly, PALS would establish a new transmission service under which participating loads would receive transmission service subject to usage-based pricing, mandatory dispatchability requirements, and Curtailment during transmission constraints, Emergency Conditions, or local reliability…Read this passage
V. OVERALL SCHEDULE AND ANTICIPATED SECTION 205 FILING
printed heading · Topic match: Filing procedure
A ninety-five (95) day abeyance is necessary because the Board must provide final authorization for the Section 205 filing described herein and is not scheduled to meet until November 17, 2026.37 Following Board authorization, SPP requires a brief period to finalize and submit the resulting Section…Read this passage Filed comments: Filing procedure
VI. REQUEST
printed heading · Topic match: Filing procedure
The Show Cause Order requires abeyance requests to be filed by August 3, 2026, and expressly contemplates that the Commission will issue an order on any such request prior to the response deadline of August 17, 2026 (14 days after the abeyance request deadline). 19 administrative efficiency and…Read this passage Filed comments: Filing procedure
VII. CONCLUSION
printed heading · Topic match: Filing procedure
CONCLUSION For the reasons stated herein, Joint Movants respectfully request the Commission: (1) Grant this Motion and hold the above-captioned proceeding in abeyance for ninety-five (95) days, up to and including November 20, 2026, to permit SPP to complete its stakeholder process and submit a…Read this passage Filed comments: Filing procedure
C. Patrick Woods
printed heading
Patrick Woods President ITC Great Plains, LLC 3500 SW Fairlawn Rd., Ste. 101 Topeka, KS 66614 On Behalf of ITC Great Plains, LLC Meredith Powell Justin A.Read this passage
CERTIFICATE OF SERVICE
printed heading
Dated at Little Rock, Arkansas, this 3rd day of August, 2026. /s/ Cassie Butler Cassie Butler Southwest Power Pool, Inc. 201 Worthen Drive Little Rock, AR 72223-4936 (501) 614-3200Read this passage