MISO requests more time to answer the June 18 show cause order
MISO and its Transmission Owners ask FERC to hold the E-8 show cause proceeding in abeyance for 90 days, through November 16, 2026, while they use the Large Load Working Group to prepare a series of section 205 filings.
Asks FERC to: Hold the proceeding in abeyance for 90 days starting August 17, 2026, with a shortened answer period and expedited treatment.
Uses the abeyance option in the E-8 order (P 37) to postpone the 60-day show cause deadline and lays out the filings MISO plans, including LARS for proximate generation and a firm step-up service.
E-8 MISO: Show cause or propose tariff changes in 60 days (p. 5) E-8 MISO: 30-day report on serving large loads with adequate generation (p. 7)
Key points
- The movants say the stakeholder process needs the 90 days to craft section 205 filings answering the order.
The Motion is necessary to permit MISO and the MISO Transmission Owners to continue the MISO stakeholder process to develop and submit FPA section PDF p. 2
- MISO says some issues in the order were not in its original workplan, and the 60-day deadline blocks stakeholder development.
The current, imminent compliance deadline in the Show Cause Order effectively prohibits the full development and robust consideration of any potential stakeholder solutions to integrating large loads. PDF p. 5
- Planned filings: a Zero Injection Generator Interconnection Agreement, a large load definition, interconnection reliability requirements, a firm step-up service and a parallel load and resource study (LARS).
a parallel study process for large load and generation resources (i.e., Load Addition and Resource Study process or “LARS”) PDF p. 4
- MISO expects to file the ZGIA by the end of August.
MISO expects to submit the ZGIA filing by the end of August. PDF p. 10
- LARS would study load and generation in parallel within 120 days and address the order's proximate generation concern.
The studies will be run in parallel, and will finish at approximately the same time—within 120 days PDF p. 11
- MISO expects to file the firm service step-up Tariff revisions by November 16, 2026, or earlier if feasible.
MISO expects to make a section 205 filing proposing Tariff revisions incorporating the firm service step-up option by November 16, 2026, or earlier, if feasible. PDF p. 12
- The Large Load Working Group has six scheduled meetings before the abeyance ends.
the LLWG is scheduled to meet six times between the date of this filing and the end of the requested abeyance period PDF p. 13
Contents · 8 sections
Read topic-matched comments in EL26-70
Topics in the text: Filing procedure · Connecting load and generation · Cost allocation
Elsewhere in the record
Other parties on the same questions, in their own documents.
- Support for more time came with a reservation Organization of MISO States
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Filing procedure
AND THE MISO TRANSMISSION OWNERS TO HOLD PROCEEDING IN ABEYANCE AND REQUEST FOR SHORTENED COMMENT PERIOD AND EXPEDITED TREATMENT Pursuant to Rules 212 and 20081 of the Federal Energy Regulatory Commission’s (“FERC” or “Commission”) Rules of Practice and Procedure, and as invited by the Commission’s…Read this passage
I. EXECUTIVE SUMMARY
printed heading · Topic match: Cost allocation
As part of this work plan, and as described in more detail below, MISO and stakeholders have developed designs and/or draft Tariff language for several additional solutions, including: (1) the Zero Injection Generator Interconnection Agreement (“ZGIA”) and related study process, which will provide…Read this passage Filed comments: Cost allocation
II. MISO SHOW CAUSE PROCEEDING
printed heading · Topic match: Cost allocation
MISO SHOW CAUSE PROCEEDING The Show Cause Order identifies an unprecedented increase in requests for transmission service to serve large load, as well as the growing interest in the co-location of loads with generation facilities (i.e., co-location arrangements), while acknowledging the challenges…Read this passage Filed comments: Cost allocation
III. REQUEST FOR ABEYANCE
printed heading · Topic match: Filing procedure
REQUEST FOR ABEYANCE The Show Cause Order demonstrates the high priority the Commission has placed on ensuring that jurisdictional regional grid operators work quickly to meet the challenge of integrating large loads to support the artificial intelligence and manufacturing related national security…Read this passage Filed comments: Reliability and curtailment
IV. COMPLIANCE PLAN
printed heading
IV.Read this passage
A. Overview of Compliance Approach and FPA Section 205 Filings
printed heading · Topic match: Connecting load and generation
The studies will be run in parallel, and will finish at approximately the same time—within 120 days— with the load/transmission model incorporating both the planned generation and planned load.19 LARS, as currently conceived, will address similar issues to those the Show Cause Order identified…Read this passage Filed comments: Connecting load and generation
B. Process and Schedule for Stakeholder Input
printed heading · Topic match: Filing procedure
Process and Schedule for Stakeholder Input To facilitate further stakeholder discussion and formal feedback cycles on proposals to address the Commission’s concerns expressed in the Show Cause Order, MISO has scheduled a series of LLWG meetings during the requested abeyance period.Read this passage
V. REQUEST FOR SHORTENED COMMENT PERIOD AND EXPEDITED TREATMENT
printed heading · Topic match: Filing procedure
REQUEST FOR SHORTENED COMMENT PERIOD AND EXPEDITED TREATMENT MISO and the MISO Transmission Owners respectfully request that the Commission issue an order granting the requested 90-day abeyance on an expedited basis by August 14, 2026.Read this passage
VI. CONCLUSION
printed heading · Topic match: Filing procedure
EL22-65- 000 (Jan. 31, 2024) (holding show cause proceedings in abeyance pending stakeholder process to resolve show cause proceedings via a section 205 filing); PJM Interconnection, L.L.C., 171 FERC ¶ 61,015, at P 34 (2020) (holding a paper hearing proceeding in abeyance to allow stakeholder…Read this passage
CERTIFICATE OF SERVICE
printed heading
Dated at Carmel, Indiana this 3rd day of August, 2026. /s/ Dawn Kaminski Dawn Kaminski Midcontinent Independent System Operator, Inc. 720 City Center Drive Carmel, Indiana 46032 Telephone: (317) 249-5400Read this passage