EL26-71-000 · 2026-11-13 · Valley Electric Association, Inc.

Valley Electric asks FERC to rescind the CAISO show cause order as to it

PDF page 1

TEL (503) 241-7242     ●     FAX (503) 241-8160     ●     bvc@dvclaw.com
107 SE Washington Street, Suite 430
Portland, OR 97214
November 13, 2026
Via Electronic Submission
Ms. Kimberly D. Bose, Secretary
Federal Energy Regulatory Commission
Room 1A East
888 First Street NE
Washington, DC 20426
Re:
California Independent System Operator Corporation, et al.
DOCKET NO.  EL26-71-000
Dear Secretary Bose:
Valley Electric Association, Inc. (“VEA”) hereby submits its Motion to Rescind Show Cause Order and Conditional Request for Extension of Time (“Motion”). VEA is a non-public utility under Section 201(f) of the Federal Power Act and asks the Commission to rescind its June 18, 2026 show cause order as to VEA, as the Commission has said it will do at a non-public utility’s request.1 If the Commission has not acted by November 16, 2026, VEA asks that its time to respond be extended. In addition to this filing letter, VEA submits the Motion and a Certificate of Service. Respectfully submitted,

/s/ Brad Van Cleve
Brad Van Cleve
Davison Van Cleve, P.C.
Attorney for Valley Electric Association, Inc.
1 Cal. Indep. Sys. Operator Corp., 195 FERC ¶ 61,214, at P 2 n.9 (2026) (“If a non-public utility wishes to be removed from this proceeding, we will rescind the show cause order against them at their request.”).

PDF page 2

- 1 -
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

California Independent System Operator
   Corporation
Citizen S-Line Transmission LLC
Citizens Sunrise Transmission LLC
Citizens Sycamore-Penasquitos
   Transmission LLC
DCR Transmission, L.L.C.
DesertLink, LLC
GridLiance West LLC
Horizon West Transmission, LLC
LS Power Grid California, LLC
Morongo Transmission LLC
Pacific Gas and Electric Company
San Diego Gas & Electric Company
Southern California Edison Company
Startrans IO, L.L.C.
SunZia Transmission, LLC
Trans Bay Cable LLC
Valley Electric Association, Inc.
Viridon Path 15, LLC
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)

Docket No. EL26-71-000

MOTION TO RESCIND SHOW CAUSE ORDER AND
CONDITIONAL REQUEST FOR EXTENSION OF TIME
ON BEHALF OF VALLEY ELECTRIC ASSOCIATION, INC.

Pursuant to Rule 212 of the Commission’s Rules of Practice and Procedure,1 Valley Electric Association, Inc. (“VEA”) moves the Commission to rescind the show cause order issued in this proceeding on June 18, 2026,2 as directed to VEA as a Participating Transmission Owner (“TO”) in the California Independent System Operator Corporation (“CAISO”). VEA is an electric cooperative that is not a public utility under Section 201(f) of the Federal Power Act (“FPA”). The Commission has stated that it will rescind the Show Cause Order as to any non-public utility at its

1 18 C.F.R. § 385.212 (2026). 2 Cal. Indep. Sys. Operator Corp., 195 FERC ¶ 61,214 (2026) (“Show Cause Order”).

PDF page 3

- 2 -
request,3 and it granted that relief to the Cities of Anaheim, Azusa, Banning, Colton, Pasadena, and Riverside, California (“Six Cities”) and the Western Area Power Administration (“WAPA”) on August 14, 2026.4 VEA’s continued participation is also unnecessary. Any large load seeking service in VEA’s territory would, either directly or through VEA, interconnect to the 230 kV system of GridLiance West LLC (“GLW”), a public utility that remains a respondent in this proceeding, rather than to VEA’s 138 kV facilities. If the Commission has not acted on this motion by November 16, 2026, VEA conditionally requests, pursuant to Rule 2008, a brief extension of its time to respond to the Show Cause Order until the Commission rules.

I. COMMUNICATIONS
Pursuant to Rule 203(b)(3), VEA requests that all communications and service in this proceeding be directed to the following persons:5

Brad Van Cleve
Davison Van Cleve, P.C.
4675 W. Teco Ave.; Suite 230
Las Vegas, NV 89118
bvc@dvclaw.com

3 Show Cause Order at P 2 n.9. 4 Cal. Indep. Sys. Operator Corp., 196 FERC ¶ 61,131, at PP 5, 7 (2026) (“August 14 Order”).
5 18 C.F.R. § 385.203(b)(3) (2026).

PDF page 4

- 3 -
Gabe DeGuzman
Director of Transmission Services and Load Management
Valley Electric Association, Inc.
800 E Nevada Highway 372
Pahrump, NV 89048
(775) 469-0868
gdeguzman@vea.coop

II. DESCRIPTION OF VEA
VEA is a rural electric distribution cooperative based in Pahrump, Nevada, with a service territory in southern Nevada and a small portion in California.  VEA is generally not regulated by the Commission because it is a rural electric cooperative that sells fewer than 4 million megawatt hours of electricity per year.   In 2011, the Commission accepted a Transition Agreement between VEA and the CAISO that established the process for VEA to join the CAISO as a Participating TO.6

VEA became a Participating TO and a signatory to the Transmission Control Agreement (“TCA”) in 2013, placing its 230 kV and 138 kV facilities under the CAISO’s Operational Control. In 2017, the Commission approved the acquisition of VEA’s 230 kV system by GLW, a Non- Load-Serving Participating TO and a respondent in this proceeding.7 VEA’s only remaining facilities under CAISO Operational Control are its 138 kV facilities, which are Low Voltage Transmission Facilities whose costs are recovered from VEA’s own members.  Interest from large loads in VEA’s territory has focused on GLW’s 230 kV system.

III. BACKGROUND
The Show Cause Order directed the CAISO and its Participating TOs to show cause why their tariffs remain just and reasonable without provisions addressing large and co-located loads,

6 Cal. Indep. Sys. Operator Corp., 137 FERC ¶ 61,194, at PP 1-2 (2011).
7 GridLiance West Transco LLC, 160 FERC ¶ 61,002, at PP 1, 7 (2017).

PDF page 5

- 4 -
or to explain what changes would remedy the Commission’s concerns.8 The Commission recognized that the Participating TOs “include entities that are not subject to the Commission’s jurisdiction because they are not public utilities pursuant to section 201(f),” explained that it included them because their TO Tariffs on file describe the wholesale load interconnection process, and stated that “[i]f a non-public utility wishes to be removed from this proceeding, we will rescind the show cause order against them at their request.”9

The Six Cities and WAPA moved for rescission of the Show Cause Order on July 31 and August 3, 2026. On August 3, VEA joined fourteen other CAISO Participating TOs (collectively, the “Joint PTOs”) in a Request for Abeyance asking the Commission to extend each Joint PTO’s deadline to respond to the Show Cause Order to November 16, 2026.10 The Commission’s August 14 Order granted both forms of relief: it rescinded the Show Cause Order as to the Six Cities and WAPA as utilities exempt under Section 201(f), and it held the proceeding in abeyance through November 16, 2026, suspending the response obligation of any respondent that submits an FPA Section 205 filing by that date.11 The CAISO Board of Governors approved the CAISO’s large load proposal on October 28, 2026. That proposal preserves the existing allocation of responsibilities under which the Participating TOs primarily manage load interconnection studies and financing under their own TO Tariffs, and the CAISO expects complementary filings from the Participating TOs.12

8 Show Cause Order at PP 3, 31.
9 Id. at P 2 n.9 (citing Sw. Power Pool, Inc., 180 FERC ¶ 61,022, at P 40 (2022)). 10 Request for Abeyance of Southern California Edison Company, et al., Docket No. EL26-71-000 (filed Aug. 3, 2026) (Accession No. 20260803-5166) (“Request for Abeyance”); August 14 Order at P 3 & n.6 (listing VEA among the Joint PTOs). The CAISO filed its own motion for abeyance the same day.
11 August 14 Order at PP 2-3 & n.6, 7, 13-15. 12 Memorandum from Neil Millar to CAISO Board of Governors, Re: Response to FERC Large Loads Order to Show Cause, at 1-2, 6 (Oct. 22, 2026); see also Motion for Abeyance of the California Independent System Operator

PDF page 6

- 5 -
IV. JUSTIFICATION FOR RESCISSION
A. VEA Is Exempt From the Commission’s Jurisdiction Under FPA Section 201(f)
Section 201(f) excludes from Part II of the FPA “an electric cooperative that receives financing under the Rural Electrification Act of 1936 . . . or that sells less than 4,000,000 megawatt hours of electricity per year.”13 VEA sells approximately 577,130 MWh’s of electricity per year; therefore, it is exempt from Part II of the FPA pursuant to Section 201(f). As the Six Cities did, VEA acknowledges the Commission’s authority to review VEA’s Transmission Revenue Requirement to ensure that the CAISO’s rates remain just and reasonable.14

VEA stands in the same position as the Six Cities and WAPA. Each is a non-public utility Participating TO with a TO Tariff on file with the Commission, each asked to be removed from this proceeding while committing to continue coordinating with the CAISO, and the Commission granted each request.15 The same result is appropriate for VEA. The timing of this motion is also no obstacle. The Show Cause Order places no deadline on a non-public utility’s request; it provides that the Commission will rescind the order “[i]f a non-public utility wishes to be removed from this proceeding.”16

B. VEA Will Continue to Coordinate with the CAISO and Remains Subject to the
CAISO Tariff
VEA makes the same commitments on which the Commission relied in the August 14
Order. VEA has coordinated and will continue to coordinate and cooperate with the CAISO in

Corporation, Docket No. EL26-71-000, at 5 (filed Aug. 3, 2026) (anticipating “simultaneous Section 205 filings from the Participating Transmission Owners”).

13 16 U.S.C. § 824(f); see City of Anaheim, 171 FERC ¶ 61,263, at PP 19-22 (2020) (cited in Show Cause Order at P 2 n.9).
14 Motion to Rescind Show Cause Order on Behalf of the Cities of Anaheim, Azusa, Banning, Colton, Pasadena, and Riverside, California, Docket No. EL26-71-000, at 4 (filed July 31, 2026) (“Six Cities Motion”).
15 August 14 Order at PP 5, 7.
16 Show Cause Order at P 2 n.9.

PDF page 7

- 6 -
responding to the Show Cause Order, to the extent the CAISO requests its assistance and with respect to the load interconnection provisions of its TO Tariff. VEA has conferred with the CAISO in advance of this filing and is authorized to state that the CAISO supports this motion. VEA is also coordinating with GLW on the respective roles of GLW and VEA in processing large load requests in VEA’s territory.   If VEA determines that changes to its TO Tariff are needed to address the issues in the Show Cause Order, VEA will file proposed revisions with the Commission. Rescission will not diminish the CAISO’s visibility into or authority over large loads in VEA’s territory. VEA remains a party to the TCA and will be subject to the large load provisions of the CAISO Tariff applicable to Participating TOs. VEA is also the Load Serving Entity and Utility Distribution Company for its territory and, through its Scheduling Coordinator, will be subject to the forecasting, telemetry, and scheduling requirements that the CAISO Tariff imposes for any large load in its territory, wherever that load interconnects.

C. VEA’s Participation in the Joint PTOs’ Request for Abeyance Does Not Alter Its Section 201(f) Status

VEA joined the Joint PTOs’ Request for Abeyance to preserve its ability to coordinate with the CAISO and the other Participating TOs and to participate in the CAISO large load stakeholder process to develop a common approach to responding to the Show Cause Order. The Joint PTOs explained that many of the Commission’s concerns “can only be resolved with complementary or, at a minimum, non-conflicting tariff provisions among the CAISO Tariff and the various TO Tariffs,” and that their requests “reflect a coordinated regional effort consistent with Commission direction.”17 VEA supported that effort and continues to support it.

17 Request for Abeyance at 4, 6.

PDF page 8

- 7 -
The Request for Abeyance stated that each Joint PTO planned to develop an FPA Section 205 filing to amend its TO Tariff.18 It also recognized, however, that “there are significant differences among the California PTOs (some PTOs serve load while others do not, for example) such that the appropriate TO Tariff changes to implement the OSC will also likely vary from PTO to PTO,” and it described the anticipated filings as matters that “remain under development and may evolve through coordination with CAISO and stakeholders.”19 The CAISO large load stakeholder process is now complete. The CAISO Board of Governors approved the CAISO’s proposal on October 28, 2026, and the Participating TOs will make individual filings tailored to their own systems rather than a single joint filing. VEA’s 138 kV facilities neither host nor are likely to host a large load, as explained in Section IV.D below. VEA has therefore concluded that a Section 205 filing is not warranted and seeks the relief the Commission has already extended to the other non-public utility respondents.

 Nothing in the Joint PTOs’ Request for Abeyance waived VEA’s status under Section 201(f) or the option the Commission offered non-public utilities in the Show Cause Order. Nor does VEA’s participation in the Request for Abeyance foreclose rescission. The Six Cities paired their motion to rescind with a conditional request for abeyance, and the Commission granted rescission without needing to reach the abeyance request.20

18 Id. at 3-4.
19 Id. at 3, 7; see also id. at 6 n.8 (noting that LS Power Grid California, LLC and DesertLink, LLC would limit any FPA Section 205 filing “to matters that implicate its own TO Tariff or a PTO-administered agreement”).
20 August 14 Order at P 2 n.5.

PDF page 9

- 8 -
D. Large Loads in VEA’s Territory Would Interconnect to GLW’s 230 kV System, Which Remains Before the Commission

The Show Cause Order addresses large loads, which the Commission described as new commercial or industrial customers with a peak load of 50 MW or greater that interconnect to the transmission system at a voltage above 69 kV.21 Large loads seeking service in VEA’s territory likely would not interconnect to VEA’s 138 kV facilities, given the option to interconnect with GLW’s more robust 230 kV system.

Service over those 230 kV facilities is governed by GLW’s TO Tariff, not VEA’s. GLW is a public utility, and remains a respondent in this proceeding, The rates, terms, and conditions the Show Cause Order addresses for large loads in VEA’s territory will therefore remain before the Commission through GLW and the CAISO. Rescinding the Show Cause Order as to VEA leaves no gap in the Commission’s review, and the Commission has already stated that it expects the CAISO to respond regarding a non-public utility’s CAISO Tariff provisions on file with the Commission.22

V. CONDITIONAL REQUEST FOR EXTENSION OF TIME AND WAIVER OF
ANSWER PERIOD
Responses to the Show Cause Order are due November 16, 2026, unless the respondent has submitted a Section 205 filing by that date.23 Rule 2008(a) provides that the time by which any person is required to act under any order may be extended by the decisional authority “for good cause, upon a motion made before the expiration of the period prescribed.”24 Good cause exists here. The Commission has committed to grant rescission to non-public utilities on request and

21 Show Cause Order at P 1 n.2; see also id. at P 57.
22 Id. at P 2 n.9.
23 August 14 Order at PP 14-15.
24 18 C.F.R. § 385.2008(a) (2026).

PDF page 10

- 9 -
acted on the Six Cities and WAPA motions within approximately two weeks; if it does the same here, VEA’s response obligation will be moot. Requiring VEA to prepare a response to a Section 206 order from which the Commission has said it will remove VEA would serve no purpose.

Accordingly, if the Commission has not acted on this motion by November 16, 2026, VEA
requests that its time to respond to the Show Cause Order be extended until thirty days after the Commission acts on this motion. This request is of the same character as the conditional abeyance motion the Six Cities filed on August 3, 2026, which was expressly conditioned on the

Commission’s disposition of their motion to rescind and which the Commission found unnecessary to address once it granted rescission.25 VEA further requests that the Commission waive or shorten any answer period applicable to this motion, as it did for the Six Cities and WAPA motions, so that the Commission may act before November 16, 2026.26

/ / /
/ / /
/ / /
/ / /
/ / /
/ / /
/ / /
/ /
/ / /

25 See August 14 Order at P 2 n.5 (“On August 3, 2026, Six Cities filed a conditional request for a 90-day abeyance of the Show Cause Order in the event the Commission denies their request for rescission. Because we are granting Six Cities Motion for Rescission, as discussed below, we need not address their conditional request for abeyance.”). 26 See Notice Establishing Answer Period, Docket No. EL26-71-000 (Aug. 4, 2026), 91 Fed. Reg. 51,171 (Aug. 7, 2026) (setting an August 7, 2026 answer deadline for the motions for abeyance filed August 3, 2026); August 14 Order at P 6 (noting that answers to the Six Cities and WAPA motions were due August 7, 2026).

PDF page 11

- 10 -
VI. CONCLUSION
WHEREFORE, VEA respectfully requests that the Commission (1) rescind the Show Cause Order as against VEA as a non-public utility and amend the caption accordingly; (2) if the Commission has not acted by November 16, 2026, extend VEA’s time to respond to the Show Cause Order as requested above; and (3) waive or shorten any answer period applicable to this motion.

Respectfully submitted,

/s/ Brad Van Cleve
Brad Van Cleve
Dakota Councilman
Davison Van Cleve, P.C.
4675 W. Teco Ave.; Suite 230
Las Vegas, NV 89118
bvc@dvclaw.com

Attorney for Valley Electric Association, Inc.

November 13, 2026

PDF page 12

- 1 -

CERTIFICATE OF SERVICE

I hereby certify that I have on this 13th day of November, 2026, caused a copy of the foregoing document to be sent to all parties on the list compiled by the Secretary of the Commission in this proceeding, by electronic mail or such other means as may have been specified by such party, pursuant to Rule 2010 of the Commission’s Rules of Practice and Procedure.

/s/ Brad Van Cleve
Brad Van Cleve
Davison Van Cleve, P.C.
4675 W. Teco Ave.; Suite 230
Las Vegas, NV 89118

bvc@dvclaw.com

Attorney for Valley Electric Association, Inc.

PDF page 13

- 2 -
SERVICE LIST
Docket No. EL26-71-000

Party
Primary Person or Counsel of Record
to be Served
Other Contact to be Served
Lisa Melton
Lisa Melton
1833 Lucile Ave
Los Angeles, CALIFORNIA 90026
lM.marlowe@pm.me

Advanced Energy
Management Alliance
Frank Lacey
Principal
Electric Advisors Consulting
3 Traylor Drive
West Chester, PENNSYLVANIA 19382
frank@eacpower.com

Advanced Energy
United
Kelsey Koenig
Solar Energy Industries Associ
Solar Energy Industries Association
1425 K ST NW STE 1000
WASHINGTON, DISTRICT OF
COLUMBIA 20005
kkoenig@seia.org
Michael P Haugh
Policy Director
Advanced Energy United
1010 VERMONT AVE NW
WASHINGTON, DISTRICT OF
COLUMBIA 200
mhaugh@advancedenergyunited.org
Caitlin Marquis
Managing Director
Advanced Energy United
1801 Pennsylvania Ave. N.W
Washington, DISTRICT OF COLUMBIA
20006
cmarquis@advancedenergyunited.org
Amazon Energy LLC
William Friedman
Amazon Web Services, Inc.
410 TERRY AVE N
SEATTLE, WASHINGTON 98109
wfried@amazon.com

American Chemistry
Council
Charles Franklin
Senior Director, Energy, Clima
700 2ND ST NE
WASHINGTON, DISTRICT OF
COLUMBIA 20002
charles_franklin@americanchemistry.com

American Clean Power
Association
Brett White
Deputy General Counsel
American Clean Power Association
1299 Pennsylvania Avenue, N.W.
WASHINGTON, DISTRICT OF
COLUMBIA 20004
bwhite@cleanpower.org

PDF page 14

- 3 -
Party
Primary Person or Counsel of Record
to be Served
Other Contact to be Served
American Council on
Renewable Energy
Elise Caplan
Director of Electricity Policy
American Council on Renewable Energy
1150 CONNECTICUT AVE NW STE
401
WASHINGTON, DISTRICT OF
COLUMBIA 20036
caplan@acore.org

American Electric
Power Service
Corporation
John Crespo
Deputy General Counsel
American Electric Power Company, Inc.
1 Riverside Plaza
29th Floor
Columbus, OHIO 43215
jccrespo@aep.com
Carrie L. Bumgarner
Senior Counsel
American Electric Power Company
1 Riverside Plaza
Columbus, OHIO 43215-2373
clbumgarner@aep.com
Kate Daley
1 Riverside Plaza
Columbus, OHIO 43215
kbdaley@aep.com
Justin Stewart
jcstewart@aep.com
Takis Laios
Director, Transmission Asset S
1 Riverside Plaza
Columbus, OHIO 43215
tlaios@aep.com
FERC Service List
801 Pennsylvania Avenue
Suite 735
Washington, DISTRICT OF COLUMBIA
20004
ferc_service_list@aep.com
LaChon Turner
AEP COMPANIES
801 PENNSYLVANIA AVE NW STE
735
WASHINGTON, DISTRICT OF
COLUMBIA 200
lturner@aep.com
AMERICAN
PETROLEUM
INSTITUTE
Grace Soderberg
Senior Counsel
AMERICAN PETROLEUM INSTITUTE
200 MASSACHUSETTS AVE NW
WASHINGTON, DISTRICT OF
COLUMBIA 20001
soderbergg@api.org

PDF page 15

- 4 -
Party
Primary Person or Counsel of Record
to be Served
Other Contact to be Served
Americans for a Clean
Energy Grid
Jared Nachmias
Americans for a Clean Energy G
Americans for a Clean Energy Grid
10 G ST NE STE 440
WASHINGTON, DISTRICT OF
COLUMBIA 20002
jared.nachmias@cleanenergygrid.org

Anthropic, PBC
Ariel Horowitz
Energy
Anthropic, PBC
500 HOWARD ST
SAN FRANCISCO, CALIFORNIA
94105
arielhorowitz@anthropic.com

Antora Energy, Inc.
Noah Long
Director, State & Regulatory P
Antora Energy LLC
200 W DE VARGAS ST STE 200
SANTA FE, NEW MEXICO 87501
noah.long@antora.com
Eric Smith
Antora Energy, Inc.
604 N Vermont St
Arlington, VIRGINIA 22203
eric.smith@antora.com
Ujvalla Gupta
ujvalla.gupta@antora.energy
Ava Community Energy Dominic Faria
Senior Policy Coordinator
Ava Community Energy
1999 HARRISON ST STE 2300
OAKLAND, CALIFORNIA 94612
dfaria@avaenergy.org
John Newton
Principal Regulatory Senior Ma
Ava Community Energy
1999 HARRISON ST STE 2300
OAKLAND, CALIFORNIA 94612
jnewton@avaenergy.org

Avangrid Networks,
Inc.
Noelle Kinsch
VP, Gen.Counsel & Corp Sec.
80 State Street
Albany, NEW YORK 12207
noelle.kinsch@avangrid.com
Alan Trotta
United Illuminating Company, The
157 Church Street
New Haven, CONNECTICUT 06510
alan.trotta@uinet.com
Avangrid Power, LLC
Leonard Rodriguez
VP & GC
Avangrid Renewables, LLC
180 Marsh Hill Rd
Orange, CONNECTICUT 06477
leonard.rodriguez@avangrid.com
Kevin Kilgallen
Director, Market Structure & P
Avangrid, Inc.
411 OAKLAND DR
DOWNINGTOWN, PENNSYLVANIA
19335
kevin.kilgallen@avangrid.com

PDF page 16

- 5 -
Party
Primary Person or Counsel of Record
to be Served
Other Contact to be Served
Avista Corporation
Lisa Hairston
FERC Compliance Manager
Avista Corporation
1411 E Mission Ave
MSC-4
Spokane, WASHINGTON 99252
lisa.hairston@avistacorp.com
Travis R. Lindsey
Senior Counsel
Avista Corporation
1141 E. Mission Ave.
MSC-33
Spokane, WASHINGTON 99202
travis.lindsey@avistacorp.com
Balancing Authority of
Northern California
C. Anthony Braun
Braun Blaising & Wynne, P.C.
555 Capitol Mall
Suite 570
Sacramento, CALIFORNIA 95814
braun@braunlegal.com
Jessica Melms
Braun Blaising & Wynne, P.C.
2600 Capitol Avenue
Suite 400
Sacramento, CALIFORNIA 95816
melms@braunlegal.com
Base Power Company
Andrew Hosea
Associate General Counsel
Base Power Company
205 E RIVERSIDE DR STE 100
AUSTIN, TEXAS 78704
ahosea@basepowercompany.com
Tori R Villarreal
Base Power Company
205 E RIVERSIDE DR
AUSTIN, TEXAS 78704
tori@basepowercompany.com
Bear Valley Electric
Service, Inc.
Randolph Elliott
McCarter & English, LLP
1301 K Street, NW
Suite 1000 West
Washington, DISTRICT OF COLUMBIA
20005
relliott@mccarter.com

Bloom Energy
Corporation
Joel Newton
VP, Regulatory Law
Bloom Energy Corporation
6611 Dearborn Dr
Falls Church, VIRGINIA 22044
joel.newton@bloomenergy.com

Calibrant Energy
Judith Judson
Executive Vice President, Regu
Calibrant Energy
1 FINANCIAL CTR STE 1500
BOSTON, MASSACHUSETTS 02111
judith.judson@calibrantenergy.com
Joe Macklin
Director, Regulatory Strategy
Calibrant Energy
536 PIEDMONT RD
COLUMBUS, OHIO 43214
joe.macklin@calibrantenergy.com

PDF page 17

- 6 -
California Department
of Water Resources
State Water Project
Lisa Dowden
Senior Counsel
Spiegel & McDiarmid LLP
1818 N Street, NW
8th Floor
WASHINGTON, DISTRICT OF
COLUMBIA 20036
Lisa.Dowden@spiegelmcd.com
Stephen C. Pearson
Spiegel & McDiarmid LLP
1818 N Street, NW
8th Floor
WASHINGTON, DISTRICT OF
COLUMBIA 20036
steve.pearson@spiegelmcd.com
Amanda C. Drennen
Attorney
Spiegel & McDiarmid LLP
1818 N Street, NW
8th Floor
WASHINGTON, DISTRICT OF
COLUMBIA 20036
amanda.drennen@spiegelmcd.com
Samuel B. Whillans
Spiegel & McDiarmid LLP
1818 N ST NW
8TH Floor
WASHINGTON, DISTRICT OF
COLUMBIA 20036
samuel.whillans@spiegelmcd.com
E Service
Spiegel & McDiarmid LLP
1818 N Street NW
8th Floor
Washington, DISTRICT OF COLUMBIA
20036
eservice@spiegelmcd.com
Nhu Nguyen
Deputy Attorney General
1300 I Street
Sacramento, CALIFORNIA 95814
nhu.nguyen@doj.ca.gov
Regina Tochterman
Senior Legal Analyst
1300 I Street
Sacramento, CALIFORNIA 95814
Regina.Tochterman@doj.ca.gov
Robert S Hedrick
Office of the General Counsel
PO Box 899
SACRAMENTO,
Robert.Hedrick@water.ca.gov
Robin M. Hennessy
Office of the General Counsel
Department of Water Resources
PO Box 899

PDF page 18

- 7 -
Party
Primary Person or Counsel of Record
to be Served
Other Contact to be Served
SACRAMENTO,
robin.hennessy@water.ca.gov
Trong Bui
PO Box 899
Sacramento,
Trong.Bui@water.ca.gov
Masoud Shafa
California Department of Water
Resources
PO Box 889
Sacramento, 94236
Masoud.Shafa@water.ca.gov
California Independent
System Operator
Corporation
Heather Curlee
Senior Counsel
250 Outcropping Way
INC000000445898
Folsom, CALIFORNIA 95630
hcurlee@caiso.com
Jacqueline Meredith
250 Outcropping Way
Folsom, CALIFORNIA 95630
caisotariff@caiso.com
California Municipal
Utilities Association
C. Anthony Braun
Braun Blaising & Wynne, P.C.
555 Capitol Mall
Suite 570
Sacramento, CALIFORNIA 95814
braun@braunlegal.com
Jessica Melms
Braun Blaising & Wynne, P.C.
2600 Capitol Avenue
Suite 400
Sacramento, CALIFORNIA 95816
melms@braunlegal.com

PDF page 19

- 8 -
Party
Primary Person or Counsel of Record
to be Served
Other Contact to be Served
California Public
Utilities Commission
Inna Vinogradov
California Public Utilities Commission
505 Van Ness Avenue
SAN FRANCISCO, CALIFORNIA
94102
inna.vinogradov@cpuc.ca.gov
Aaron Jacobs-Smith
California Public Utilities Commission
505 VAN NESS AVE
SAN FRANCISCO, CALIFORNIA
94102
aaron.jacobs-smith@cpuc.ca.gov
Paula Gruendling
Program Manager
California Public Utilities Commission
505 VAN NESS AVE
SAN FRANCISCO, CALIFORNIA
94102
paula.gruendling@cpuc.ca.gov
Le-Quyen Nguyen
California Public Utilities Commission
505 Van Ness Avenue
San Francisco, CALIFORNIA 94102
Le-Quyen.Nguyen@cpuc.ca.gov
Leuwam Tesfai
California Public Utilities Commission
505 Van Ness Avenue
San Francisco, CALIFORNIA 94102
leuwam.tesfai@cpuc.ca.gov
Simon Hurd
Program and Project Supervisor
California Public Utilities Commission
505 Van Ness Avenue
San Francisco, CALIFORNIA 94102
Simon.Hurd@cpuc.ca.gov
Philip Voris
505 Van Ness Avenue
San Francisco, CALIFORNIA 94102
philip.voris@cpuc.ca.gov
Aaron Bloom
California Public Utilities Commission
505 Van Ness Avenue
San Francisco, CALIFORNIA 94102
aaron.bloom@cpuc.ca.gov
Christine J. Hammond
California Public Utilities Commission
505 Van Ness Avenue
San Francisco, CALIFORNIA 94102
christine.hammond@cpuc.ca.gov
Camus Energy

Anthony Harrison
VP,Policy & Strategic Partners
Camus Energy
1821 S Bascom Ave
Suite 515
Campbell, CALIFORNIA 95008
anthony@camus.energy
Capital Power
Corporation
Thomas Millar
Mr. Thomas Millar
Sidley Austin LLP
1501 K Street, N.W.
WASHINGTON, DISTRICT OF
COLUMBIA 20005
tmillar@sidley.com
Darsh Singh
Senior Legal Counsel
Capital Power Corporation
2398 E Camelback Road, Suite 940
Phoenix, ALBERTA 85016
dasingh@capitalpower.com

PDF page 20

- 9 -
Party
Primary Person or Counsel of Record
to be Served
Other Contact to be Served
Chevron U.S.A. Inc.
Vanessa Colon
Senior Counsel
Chevron U.S.A. Inc.
1400 SMITH ST RM 31158
HOUSTON, TEXAS 77002
vanessa.colon@chevron.com

Citizen S-Line
Transmission LLC
Ashley Bond
1730 Rhode Island Avenue, N.W.
Suite 700
Washington, DISTRICT OF COLUMBIA
20036-3155
amb@duncanallen.com
Peter F. Smith
Chief Executive Officer
2 Seaport East
Suite 5C
Boston, MASSACHUSETTS 02210
psmith@citizensenergy.com
Citizens Sunrise
Transmission LLC
Paul Breakman
Attorney
1575 Eye Street, NW
Suite 300
Washington, DISTRICT OF COLUMBIA
20005
paul.breakman@nreca.coop
Ernest Panos
Chief Financial Officer
2 SEAPORT LN STE 5C
BOSTON, MASSACHUSETTS 02210
epanos@citizensenergy.com
Citizens Sycamore-
Penasquitos
Transmission LLC
Peter Smith
Chief Executive Officer
2 Seaport East
Suite 5C
Boston, MASSACHUSETTS 02210
psmith@citizensenergy.com
Ernest Panos
Chief Financial Officer
2 SEAPORT LN STE 5C
BOSTON, MASSACHUSETTS 02210
epanos@citizensenergy.com
City of Anaheim,
California
Elden Krause
Integrated Resources Manager
201 S ANAHEIM BLVD STE 802
ANAHEIM, CALIFORNIA 92805
ekrause@anaheim.net
Margaret Elizabeth McNaul
Attorney
1909 K Street, N.W.
Suite 600
Washington, DISTRICT OF COLUMBIA
20006
mmcnaul@thompsoncoburn.com
City of Azusa,
California
Richard Torres
729 N. Azusa Avenue
Azusa, CALIFORNIA 91702
rtorres@azusaca.gov
Margaret Elizabeth McNaul
Attorney
1909 K Street, N.W.
Suite 600
Washington, DISTRICT OF COLUMBIA
20006
mmcnaul@thompsoncoburn.com
City of Banning,
California
Rebecca Shelton
Attorney
1909 K Street NW
Suite 600
Washington, DISTRICT OF COLUMBIA
20006
rshelton@thompsoncoburn.com
Margaret Elizabeth McNaul
Attorney
1909 K Street, N.W.
Suite 600
Washington, DISTRICT OF COLUMBIA
20006
mmcnaul@thompsoncoburn.com

PDF page 21

- 10 -
Party
Primary Person or Counsel of Record
to be Served
Other Contact to be Served
City of Colton,
California
Kinda Salloum
650 N. La Cadena Blvd
Colton, CALIFORNIA 92324
ksalloum@coltonca.gov
Margaret Elizabeth McNaul
Attorney
1909 K Street, N.W.
Suite 600
Washington, DISTRICT OF COLUMBIA
20006
mmcnaul@thompsoncoburn.com
City of Pasadena,
California
Herman Leung
150 Los Robles #200
Pasadena, ALBERTA 91101
CANADA
hleung@cityofpasadena.net
Margaret Elizabeth McNaul
Attorney
1909 K Street, N.W.
Suite 600
Washington, DISTRICT OF COLUMBIA
20006
mmcnaul@thompsoncoburn.com
City of Riverside,
California
Ruthann Salera
rsalera@riversideca.gov
Margaret Elizabeth McNaul
Attorney
1909 K Street, N.W.
Suite 600
Washington, DISTRICT OF COLUMBIA
20006
mmcnaul@thompsoncoburn.com
City of Santa Clara, CA
d/b/a Silicon Valley
Power
Lisa Gast
Attorney
Duncan, Weinberg, Genzer & Pembroke
PC
1667 K Street NW
Suite 700
Washington, DISTRICT OF COLUMBIA
20006
lsg@dwgp.com
Peter Scanlon
Partner
Duncan, Weinberg, Genzer & Pembroke
PC
1667 K ST NW STE 700
WASHINGTON, DISTRICT OF
COLUMBIA 20006
pjs@dwgp.com
Paige Punzalan
Duncan Weinberg Genzer & Pembroke,
PC
915 L Street, Suite 1410
SACRAMENTO, CALIFORNIA 95814
plp@dwgp.com
Rebekah G Chikuni
Legal Assistant
Duncan Weinberg Genzer & Pembroke,
PC
1667 K ST NW STE 700
WASHINGTON, DISTRICT OF
COLUMBIA 20006
rgc@dwgp.com

PDF page 22

- 11 -
Party
Primary Person or Counsel of Record
to be Served
Other Contact to be Served
Clearway Energy Group
LLC
Gretchen Schott
Assistant General Counsel, Reg
Clearway Energy Group LLC
1200 SMITH ST STE 600
HOUSTON, TEXAS 77002
gretchen.schott@clearwayenergy.com
Julia Zuckerman
Senior Direc., Exter. & Mark.
Clearway Energy Group LLC
100 California Street
Suite 650
San Francisco, CALIFORNIA 94111
julia.zuckerman@clearwayenergy.com
Constellation Energy
Generation, LLC
Christopher Wilson
Director, Fed. Regulatory A
Constellation Energy Generation, LLC
250 Massachusetts Avenue NW
Suite 760
Washington, DISTRICT OF COLUMBIA
20001
FERCe-filings1@Constellation.com
Carrie Allen
SVP & Deputy General Counsel
Constellation Energy Corporation
101 Constitution Ave. NW Suite 400 East
Washington, DISTRICT OF COLUMBIA
20001
carrie.allen@constellation.com
Todd Brecher
VP and Managing Counsel
Constellation Energy Generation, LLC
250 Massachusetts Ave. NW
Suite 700
Washington, DISTRICT OF COLUMBIA
20001
todd.brecher@constellation.com

Corporate Energy
Buyers Association
John Miller
Director, Transmission Policy
Corporate Energy Buyers Association
1501 M ST NW STE 900
WASHINGTON, DISTRICT OF
COLUMBIA 20005
jmiller@ceba.org
Bryn Baker
Corporate Energy Buyers Associ
Corporate Energy Buyers Association
1501 M ST NW STE 900
WASHINGTON, DISTRICT OF
COLUMBIA 20005
bbaker@ceba.org
Kyle L. Davis
Senior Director, Policy Resear
Corporate Energy Buyers Association
1501 M ST NW STE 900
WASHINGTON, DISTRICT OF
COLUMBIA 20005
kdavis@ceba.org

PDF page 23

- 12 -
Party
Primary Person or Counsel of Record
to be Served
Other Contact to be Served
Data Center Coalition
Morgan Sipple
Data Center Coalition
1250 H ST NW
WASHINGTON, DISTRICT OF
COLUMBIA 20005
morgan@datacentercoalition.org

DCR Transmission,
L.L.C.
Joseph Hall
700 Sixth Street, NW
Ste. 700
Washington, DISTRICT OF COLUMBIA
20001-3980
joehall@eversheds-sutherland.com
Jeffrey S Levy Esq
General Counsel
Five Greenwich Office Park
2nd Floor
GREENWICH, CONNECTICUT 06831
jlevy@LotusPartners.com
DesertLink, LLC
Daniel Arzola
Director, Transmission Rates
16150 Main Circle Drive, Suite 310
Chesterfield, MISSOURI 63017-4689
earzola@lspower.com
Mark Milburn
Vice President
400 Chesterfield Center
Suite 110
Chesterfield, MISSOURI 63017
mmilburn@lspower.com
Digital Realty Trust,
L.P.
Zach O’Farrell Huber
601 W 2ND ST FL 32
AUSTIN, TEXAS 78701
zofarrellhuber@digitalrealty.com

EDF Power Solutions,
Inc.
Linda Walsh
Husch Blackwell LLP
1801 Pennsylvania Ave. NW, Suite 1000
Washington, DISTRICT OF COLUMBIA
20006
linda.walsh@huschblackwell.com
Emily B Starobin
Attorney
Husch Blackwell LLP
914 VEIRS MILL RD
ROCKVILLE, MARYLAND 20851
emily.starobin@huschblackwell.com
Temujin J Roach
Senior Director - Transmission
EDF Renewables, Inc.
3600 American Blvd., W, Suite 400
Minneapolis, MINNESOTA 55413
temujin.roach@edf-re.com
Emma Simon
Director, Transmission Policy
EDF Renewables Development, Inc.
15445 Innovation Dr
San Diego, CALIFORNIA 92128
emmanix.simon@edf-re.com
Edison Electric Institute
Kevin Huyler
Managing Director, Edison Elec
Edison Electric Institute
701 PENNSYLVANIA AVE NW
WASHINGTON, DISTRICT OF
COLUMBIA 20004
khuyler@eei.org
Leet W Wood
Manager, Federal Regulatory Af
Edison Electric Institute
701 PENNSYLVANIA AVE NW
WASHINGTON, DISTRICT OF
COLUMBIA 20004
leetwood@eei.org

PDF page 24

- 13 -
Party
Primary Person or Counsel of Record
to be Served
Other Contact to be Served
EDP Renewables North
America LLC
Carla Jones
Director of Legal
EDP Renewables North America LLC
1501 McKinney Street
Suite 1300
Houston, TEXAS 77010
carla.jones@edp.com
Meredith Chambers
Van Ness Feldman
825 TOWN AND COUNTRY LN STE
1200
HOUSTON, TEXAS 77024
mchambers@vnf.com
Electric Power Supply
Association
Nancy Bagot
1401 NEW YORK AVE NW STE 950
WASHINGTON, DISTRICT OF
COLUMBIA 20005
nbagot@epsa.org

Electricity Consumers
Resource Council
Karen Onaran
Vice President
ELCON
1101 K Street NW
Suite 700
Washington, DISTRICT OF COLUMBIA
20005
KOnaran@elcon.org

Electricity Customer
Alliance
Jeffery Dennis
Electricity Customer Alliance
1001 PENNSYLVANIA AVE NW
WASHINGTON, DISTRICT OF
COLUMBIA 20004
Dennis@co2efficient.com

Emerald AI
Swasti Jain
swasti.jain@emeraldai.co
Michael Panfil
Emerald AI
4535 Westhall Dr NW
Washington, DISTRICT OF COLUMBIA
20007
michael.panfil@emeraldai.co

PDF page 25

- 14 -
Party
Primary Person or Counsel of Record
to be Served
Other Contact to be Served
Enchanted Rock, LLC
Steven Shparber
Mintz, Levin, Cohn, Ferris, Glovsky and
Popeo,
P.C.
555 12TH ST NW STE 1100
WASHINGTON, DISTRICT OF
COLUMBIA 20004
sshparber@mintz.com
Omar Bustami
Mintz, Levin, Cohn, Ferris, Glovsky and
Popeo,
P.C.
3580 Carmel Mountain Road
Suite 300
San Diego, CALIFORNIA 92130
OBustami@mintz.com

Enel North America,
Inc.
Jessica Greenberg
Enel Green Power North America, Inc.
10 Mill Pond Drive
Georgetown, ONTARIO L7G 4S6
CANADA
jessica.greenberg@enel.com
Mona Tierney-Lloyd
Head, Regulatory & Institution
Enel North America, Inc.
2071 ALTAIR LN
RENO, NEVADA 89521
mona.tierney-lloyd@enel.com
Juan Diaz
Director RA and IA
Enel Companies (Enel Green Power North
Am
and EnerNOC, Inc.)
100 BRICKSTONE SQ STE 300
ANDOVER, MASSACHUSETTS 01810
juan.diaz9@enel.com
Energy Trading Institute Noha Sidhom
Executive Director
64 Bryant Street, N.W.
Washington, DISTRICT OF COLUMBIA
20001
noha@energytradinginstitute.org

Environmental Defense
Fund
Phelps Turner
Senior Attorney, U.S. Clean En
Environmental Defense Fund
257 PARK AVE S
ENVIRONMENTAL DEFENSE FUND
NEW YORK, NEW YORK 10010
pturner@edf.org

Eolian, L.P.
Eric Stoutenburg
Eolian, L.P.
988 Howard Ave Ste
Burlingame, CALIFORNIA 94010
eric.stoutenburg@eolianenergy.com

PDF page 26

- 15 -
Party
Primary Person or Counsel of Record
to be Served
Other Contact to be Served
EQUINIX, INC.
Arthur Haubenstock
Sr. Counsel
EQUINIX INC.
700 K ST NW
WASHINGTON, DISTRICT OF
COLUMBIA 20001
ahaubenstock@equinix.com
Cy K McGeady
cmcgeady@equinix.com
FuelCell Energy, Inc.
Alexandrea Isaac
3 GREAT PASTURE RD
DANBURY, CONNECTICUT 06810
aisaac@fce.com

Global Capacity
Alliance
Jesse Gossett
Interim Executive Director
3909 Petes Path
Austin, TEXAS 78731
jesse@globalcapacityalliance.org

Google LLC
Chimera Thompson
Attorney
White & Case LLP
701 13th St NW
Washington, DISTRICT OF COLUMBIA
20005
chimera.thompson@whitecase.com
Rebecca Kennedy
Attorney
701 13th St NW
Washington, DISTRICT OF COLUMBIA
20005
kennedyre@google.com
GridLiance West LLC
Elizabeth Ramey
Senior Attorney
801 Pennsylvania Avenue NW
Suite 220
Washington, DISTRICT OF COLUMBIA
20004
elizabeth.ramey@nexteraenergy.com
Jaime Hoffman
330 W Canon Perdido St
Santa Barbara, CALIFORNIA 93101
Jaime.Hoffman@nexteraenergy.com
GridStor LLC
Jason Burwen
GridStor LLC
7 SE STARK ST STE 850
PORTLAND, OREGON 97214
jason.burwen@gridstor.com
William B Lackey
GridStor LLC
7 SE STARK ST STE 850
PORTLAND, OREGON 97214
ben.lackey@gridstor.com
Honeywell International
Inc.
Dane Farrell
Honeywell International Inc.
101 CONSTITUTION AVE NW STE
500W
WASHINGTON, DISTRICT OF
COLUMBIA 20001
Dane.farrell@honeywell.com

Horizon West
Transmission, LLC
Jaime Hoffman
330 W Canon Perdido St
Santa Barbara, CALIFORNIA 93101
Jaime.Hoffman@nexteraenergy.com
Elizabeth Ramey
Senior Attorney
801 Pennsylvania Avenue NW
Suite 220
Washington, DISTRICT OF COLUMBIA
20004
elizabeth.ramey@nexteraenergy.com

PDF page 27

- 16 -
Party
Primary Person or Counsel of Record
to be Served
Other Contact to be Served
Imperial Irrigation
District
Jamie Asbury
General Manager
Imperial Irrigation District
333 E. Barioni Boulevard
Imperial, CALIFORNIA 92251
jlasbury@IID.com
Sean Neal
Attorney
Duncan, Weinberg, Genzer & Pembroke
PC
915 L Street
Suite 1410
Sacramento, CALIFORNIA 95814
smn@dwgp.com
Andrea Sarmentero Garzon
Duncan, Weinberg, Genzer & Pembroke,
P.C.
1667 K Street, N.W.
Suite 700
Washington, DISTRICT OF COLUMBIA
20006
asg@dwgp.com
Paige Punzalan
Duncan Weinberg Genzer & Pembroke,
PC
915 L Street, Suite 1410
SACRAMENTO, CALIFORNIA 95814
plp@dwgp.com
Salena R Garcia
Administrative Support Special
Duncan Weinberg Genzer & Pembroke,
PC
915 L ST STE 1410
SACRAMENTO, CALIFORNIA 95814
srg@dwgp.com
Independent Energy
Producers Association
Brian Cragg
Attorney
Downey Brand LLP
455 Market Street
Suite 1500
San Francisco, CALIFORNIA 94105
bcragg@downeybrand.com

Information Technology
Industry Council
Rachel Ross
Vice President, Energy Policy
700 K ST NW FL 6
WASHINGTON, DISTRICT OF
COLUMBIA 20001
rross@itic.org

PDF page 28

- 17 -
Party
Primary Person or Counsel of Record
to be Served
Other Contact to be Served
Infrastructure Masons,
Inc.
Steven Shparber
Mintz, Levin, Cohn, Ferris, Glovsky and
Popeo,
P.C.
555 12TH ST NW STE 1100
WASHINGTON, DISTRICT OF
COLUMBIA 20004
sshparber@mintz.com
Omar Bustami
Mintz, Levin, Cohn, Ferris, Glovsky and
Popeo,
P.C.
3580 Carmel Mountain Road
Suite 300
San Diego, CALIFORNIA 92130
OBustami@mintz.com

Institute for Progress
Ben Schifman
Institute for Progress
Institute for Progress
1255 Union St NE
Washington, DISTRICT OF COLUMBIA
20002
ben@ifp.org

Invenergy Solar
Development North
America LLC
Tyler O'Connor
Crowell & Moring LLP
600 5TH ST NW
WASHINGTON, DISTRICT OF
COLUMBIA 20001
toconnor@crowell.com
Nicole Luckey
Senior Vice President, Regulat
Invenergy LLC
1 S WACKER DR STE 1800
CHICAGO, ILLINOIS 60606
nluckey@invenergy.com
William Borders, ESQ
Chief Compliance Officer
Invenergy LLC
One South Wacker Drive
Suite 1500
Chicago, ILLINOIS 60606
ferccompliance@invenergy.com

PDF page 29

- 18 -
Party
Primary Person or Counsel of Record
to be Served
Other Contact to be Served
Invenergy Thermal
Development Holdings
LLC
Tyler O'Connor
Crowell & Moring LLP
600 5TH ST NW
WASHINGTON, DISTRICT OF
COLUMBIA 20001
toconnor@crowell.com
Nicole Luckey
Senior Vice President, Regulat
Invenergy LLC
1 S WACKER DR STE 1800
CHICAGO, ILLINOIS 60606
nluckey@invenergy.com
William Borders, ESQ
Chief Compliance Officer
Invenergy LLC
One South Wacker Drive
Suite 1500
Chicago, ILLINOIS 60606
ferccompliance@invenergy.com
Invenergy Wind
Development North
America LLC
Tyler O'Connor
Crowell & Moring LLP
600 5TH ST NW
WASHINGTON, DISTRICT OF
COLUMBIA 20001
toconnor@crowell.com
Nicole Luckey
Senior Vice President, Regulat
Invenergy LLC
1 S WACKER DR STE 1800
CHICAGO, ILLINOIS 60606
nluckey@invenergy.com
William Borders, ESQ
Chief Compliance Officer
Invenergy LLC
One South Wacker Drive
Suite 1500
Chicago, ILLINOIS 60606
ferccompliance@invenergy.com
LS Power Development,
LLC
Marjorie Philips
VP, Wholesale Market Policy
LS Power Development, LLC
250 W 55TH ST FL 31
NEW YORK, NEW YORK 10019
mphilips@lspower.com
Daniel Pierpont
Vice President
LS Power Development, LLC
250 W 55TH ST FL 31
NEW YORK, NEW YORK 10019
dpierpont@lspower.com
LS Power Grid
California, LLC
Terry Harvill
Vice President, Transmission R
16150 MAIN CIRCLE DR STE 310
CHESTERFIELD, MISSOURI 63017
Tharvill@lspower.com
Mark Milburn
Vice President
400 Chesterfield Center
Suite 110
Chesterfield, MISSOURI 63017
mmilburn@lspower.com
Luminary Strategies,
LLC
Arushi Sharma Frank
Founder & Principal, Luminary
Luminary Strategies, LLC
3 TINGEY SQ SE
WASHINGTON, DISTRICT OF
COLUMBIA 20003
arushisharmafrank@gmail.com

PDF page 30

- 19 -
Party
Primary Person or Counsel of Record
to be Served
Other Contact to be Served
Mainspring Energy
Brian Kauffman
Director, Wholesale Market Dev
Mainspring Energy
3601 HAVEN AVE
MENLO PARK, CALIFORNIA 94025
brian.kauffman@mainspringenergy.com

Microsoft Corporation
Jeffery Riles
Director of Energy Markets
One Microsoft Way
Redmond, WASHINGTON 98052
jeffriles@microsoft.com
Jordan Weiszhaar
Regulatory Strategy
Microsoft Corporation
1 MICROSOFT WAY
REDMOND, WASHINGTON 98052
jordanw@microsoft.com
Reese Rogers
Microsoft Corporation
1 MICROSOFT WAY
REDMOND, WASHINGTON 98052
reeserogers@microsoft.com
Neelesh Nerurkar
Director, AI and Energy Policy
Microsoft Corporation
901 K ST NW FL 5
WASHINGTON, DISTRICT OF
COLUMBIA 20001
nnerurkar@microsoft.com

Middle River Power
LLC
Tina Chase
4350 EXECUTIVE DR STE 320
SAN DIEGO, CALIFORNIA 92121
tchase@mrpgenco.com
Joseph Dubinski
1 North Franklin Street
Suite 2600
Chicago, ILLINOIS 60606
jdubinski@mrpgenco.com
Madison Hernandez-Barber
Middle River Power
Middle River Power LLC
1 N FRANKLIN ST STE 2600
CHICAGO, ILLINOIS 60606
mhernandez-barber@mrpgenco.com
Nuo Tang
ntang@mrpgenco.com

PDF page 31

- 20 -
Party
Primary Person or Counsel of Record
to be Served
Other Contact to be Served
ModernElectric Inc.
Chino Lex
Founder/ Chief Executive Offi
ModernElectric Inc.
43 Dore Street
San Francisco, CALIFORNIA 94103
chino@modernelectric.co

Modesto Irrigation
District
Martin Caballero
Modesto Irrigation District
P.O. Box 4060
Modesto, CALIFORNIA 95352
martin.caballero@mid.org
Sean Neal
Attorney
Duncan, Weinberg, Genzer & Pembroke PC

915 L Street
Suite 1410
Sacramento, CALIFORNIA 95814
smn@dwgp.com
Paige Punzalan
Duncan Weinberg Genzer & Pembroke, PC

915 L Street, Suite 1410
SACRAMENTO, CALIFORNIA 95814
plp@dwgp.com
Salena R Garcia
Administrative Support Special
Duncan Weinberg Genzer & Pembroke, PC

915 L ST STE 1410
SACRAMENTO, CALIFORNIA 95814
srg@dwgp.com
Morongo Transmission
LLC
Kris Salmon
CFO
12700 PUMARRA RD
BANNING, CALIFORNIA 92220
ksalmon@morongo-nsn.gov
Steven Hunt
1850 Parkway Place
Suite 800
Marietta, GEORGIA 30067
steven.hunt@gdsassociates.com
National Association of
Regulatory Utility
Commissioners
Kimberly Duffley
Senior Dir. of Energy Policy a
National Association of Regulatory Utility Commissioners

1101 Vermont Ave, NW
Suite 200
WASHINGTON, DISTRICT OF
COLUMBIA 20005
kduffley@naruc.org
James Ramsay
General Counsel
1101 Vermont Ave NW
Suite 200
Washington, DISTRICT OF COLUMBIA
20005
jramsay@naruc.org

PDF page 32

- 21 -
Party
Primary Person or Counsel of Record
to be Served
Other Contact to be Served
National Grid Plc
Amber Thornhill
Director, FERC, ISO Relations
National Grid
801 Pennsylvania Ave., N.W
Suite 801
WASHINGTON, DISTRICT OF
COLUMBIA 20004
Amber.Thornhill@nationalgrid.com

NATURAL GAS
SUPPLY
ASSOCIATION
Patricia Jagtiani
Executive Vice President
NATURAL GAS SUPPLY
ASSOCIATION
1620 I Street NW, Suite 700
Washington, DISTRICT OF COLUMBIA
20006
pjagtiani@ngsa.org
Casey Gold
Regulatory Coordinator
NGSA
1620 I Street NW
Suite 700
Washington, DISTRICT OF COLUMBIA
20006
casey.gold@ngsa.org
Natural Resources
Defense Council
Hilary Firestone
Natural Resources Defense Council
1314 2ND ST
SANTA MONICA, CALIFORNIA 90401
hfirestone@nrdc.org

PDF page 33

- 22 -
Party
Primary Person or Counsel of Record
to be Served
Other Contact to be Served
Northern California
Power Agency
Lisa Dowden
Senior Counsel
Spiegel & McDiarmid LLP
1818 N Street, NW
8th Floor
WASHINGTON, DISTRICT OF
COLUMBIA 20036
Lisa.Dowden@spiegelmcd.com
Jeffrey M. Bayne
Spiegel & McDiarmid LLP
1818 N Street, NW, 8th Floor
Washington, DISTRICT OF COLUMBIA
20036
jeffrey.bayne@spiegelmcd.com
Amanda C. Drennen
Attorney
Spiegel & McDiarmid LLP
1818 N Street, NW
8th Floor
WASHINGTON, DISTRICT OF
COLUMBIA 20036
amanda.drennen@spiegelmcd.com
Samuel B. Whillans
Spiegel & McDiarmid LLP
1818 N ST NW
8TH Floor
WASHINGTON, DISTRICT OF
COLUMBIA 20036
samuel.whillans@spiegelmcd.com
E Service
Spiegel & McDiarmid LLP
1818 N Street NW
8th Floor
Washington, DISTRICT OF COLUMBIA
20036
eservice@spiegelmcd.com
Tony Zimmer
General Manager
Northern California Power Agency
651 COMMERCE DR
ROSEVILLE, CALIFORNIA 95678
tony.zimmer@ncpa.com
Jane Luckhardt
General Counsel
Northern California Power Agency
651 Commerce Drive
Roseville, CALIFORNIA 95678
jane.luckhardt@ncpa.com

PDF page 34

- 23 -
Party
Primary Person or Counsel of Record
to be Served
Other Contact to be Served
NRG Business
Marketing LLC
Neal Fitch
Sr. Director, Regulatory Affai
NRG Energy, Inc.
804 CARNEGIE CTR
PRINCETON, NEW JERSEY 08540
neal.fitch@nrg.com
Cortney Slager
VP & Assistant General Counsel
NRG Companies
804 Carnegie Center
Princeton, NEW JERSEY 08540
cortney.slager@nrg.com
Jennifer Hsia
Assistant General Counsel
NRG Energy
804 Carnegie Center Dr.
Princeton, NEW JERSEY 08540
Jennifer.Hsia@nrg.com
Brianna Anderson
Regulatory Counsel
NRG Energy, Inc.
804 CARNEGIE CTR
PRINCETON, NEW JERSEY 08540
BRIANNA.ANDERSON@NRG.COM

NVIDIA Corporation
Mario Loyola
Director of Government Affairs
NVIDIA Corporation
2788 SAN TOMAS EXPY
SANTA CLARA, CALIFORNIA 95051
mloyola@nvidia.com

Oracle America, Inc.
Madeline Fleisher
Oracle America, Inc.
2300 Oracle Way
Austin, TEXAS 78741
madeline.fleisher@oracle.com

Pacific Gas and Electric
Company
Igor Grinberg
Principal Regulatory Analyst
3301 CROW CANYON RD
SAN RAMON, CALIFORNIA 94583
igor.grinberg@pge.com
Keith T Sampson, ESQ
Senior Counsel
Law Department
Post Office Box 1018
Oakland, CALIFORNIA 94604-1018
keith.sampson@pge.com
Pattern Renewables 2
LP
Robert Daileader
Nixon Peabody LLP
799 9th Street NW
Suite 500
Washington, DISTRICT OF COLUMBIA
20001
rdaileader@nixonpeabody.com
Cameron Yourkowski
Dir., Regulatory & Market Affa
Pattern Energy Group Inc.
1088 Sansome Street
SAN FRANCISCO, CALIFORNIA
94111
cameron.yourkowski@patternenergy.com

PDF page 35

- 24 -
Party
Primary Person or Counsel of Record
to be Served
Other Contact to be Served
PUBLIC CITIZEN, INC Tyson Slocum
Energy Program Director
PUBLIC CITIZEN, INC
215 PENNSYLVANIA AVE SE
WASHINGTON, DISTRICT OF
COLUMBIA 20003
tslocum@citizen.org

Quantum HPC
Infrastructure, LLC
Stephen Snyder
Attorney
Womble Bond Dickinson (US) LLP
2001 K ST NW
SUITE 400 SOUTH
WASHINGTON, DISTRICT OF
COLUMBIA 20006
steve.snyder@wbd-us.com

Rowan Digital
Infrastructure

Tyler Petersen
Rowan Digital Infrastructure
1400 16TH ST STE 330
DENVER, COLORADO 80202
tpetersen@rowan.digital
RWE Americas, LLC
Paul Varnado
Assistant General Counsel
RWE Americas, LLC
353 N. Clark Street
30th Floor
Chicago, ILLINOIS 60614
paul.varnado@rwe.com
Tomas J Rodriguez
Counsel II
RWE Clean Energy, LLC
353 N CLARK ST FL 30
CHICAGO, ILLINOIS 60654
tomas.rodriguez@rwe.com
San Diego Gas &
Electric Company
Adam Currey
8315 CENTURY PARK CT BLDG 3
SAN DIEGO, CALIFORNIA 92123
acurrey@sdge.com
Ross R Fulton
Senior Counsel
8330 Century Park Court
San Diego, CALIFORNIA 92123
rfulton@sdge.com
Sierra Club
Jonah Baskin
Sierra Club
50 F ST NW FL 8
WASHINGTON, DISTRICT OF
COLUMBIA 20001
jonah.baskin@sierraclub.org

PDF page 36

- 25 -
Six Cities CA
Margaret McNaul
Attorney
Thompson Coburn LLP
1909 K Street, N.W.
Suite 600
Washington, DISTRICT OF COLUMBIA
20006
mmcnaul@thompsoncoburn.com
Rebecca L. Shelton
Attorney
Thompson Coburn LLP
1909 K Street NW
Suite 600
Washington, DISTRICT OF COLUMBIA
20006
rshelton@thompsoncoburn.com
Jenna E. Cliatt
Attorney
Thompson Coburn LLP
1909 K Street NW
Suite 600
Washington, DISTRICT OF COLUMBIA
20006
jcliatt@thompsoncoburn.com
Carrie A Thompson
Principal Integrated Resources
City of Anaheim, California
201 S ANAHEIM BLVD STE 802
ANAHEIM, CALIFORNIA 92805
cathompson@anaheim.net
Nicholas T Burki
Integrated Resources Planner I
ANAHEIM PUBLIC UTILITIES
201 S. Anaheim Blvd.
Suite 802
Anaheim, CALIFORNIA 92805
Nburki@anaheim.net
Richard Torres
729 N. Azusa Avenue
Azusa, CALIFORNIA 91702
rtorres@azusaca.gov
Jim Steffens
City of Banning, California
176 East Lincoln
BANNING, CALIFORNIA 92220
jsteffens@banningca.gov
Kinda Salloum
650 N. La Cadena Blvd
Colton, CALIFORNIA 92324
ksalloum@coltonca.gov
Kelly Nguyen
City of Pasadena Water and Power
Departme
100 N. Garfield Avenue
PASADENA, CALIFORNIA 91101
kellynguyen@cityofpasadena.net

PDF page 37

- 26 -
Party
Primary Person or Counsel of Record
to be Served
Other Contact to be Served
Susan Wilson
Assistant City Attorney
City of Riverside, California
3901 ORANGE ST
RIVERSIDE, CALIFORNIA 92501
swilson@riversideca.gov
Scott Lesch
3901 Orange Street
Riverside, CALIFORNIA 92501
slesch@riversideca.gov
Cindi Cohen
CITY OF RIVERSIDE PUBLIC UTIL
DEPT
3901 Orange Street
Riverside, CALIFORNIA 92501
ccohen@riversideca.gov
Solar Energy Industries
Association
Melissa Alfano
Manager of Regulatory Affairs
Solar Energy Industries Association
1425 K Street, N.W., Suite 1000
Washington, DISTRICT OF COLUMBIA
20005
malfano@seia.org

Southern California
Edison Company
FERC Case Administration
2244 WALNUT GROVE AVE
ROSEMEAD, CALIFORNIA 91770
ferccaseadmin@sce.com
Andrea Tozer
Director and Managing Attorney
PO Box 800
Rosemead, CALIFORNIA 91770
Andrea.Tozer@sce.com

PDF page 38

- 27 -
Party
Primary Person or Counsel of Record
to be Served
Other Contact to be Served
Southwest Public Power
Agency, Inc.
Stephen Pearson
Spiegel & McDiarmid LLP
1818 N Street, NW
8th Floor
WASHINGTON, DISTRICT OF
COLUMBIA 20036
steve.pearson@spiegelmcd.com
Lisa Dowden
Senior Counsel
Spiegel & McDiarmid LLP
1818 N Street, NW
8th Floor
WASHINGTON, DISTRICT OF
COLUMBIA 20036
Lisa.Dowden@spiegelmcd.com
Lauren L. Springett
Spiegel & McDiarmid LLP
1818 N Street, NW
8th Floor
WASHINGTON, DISTRICT OF
COLUMBIA 20036
lauren.springett@spiegelmcd.com
E Service
Spiegel & McDiarmid LLP
1818 N Street NW
8th Floor
Washington, DISTRICT OF COLUMBIA
20036
eservice@spiegelmcd.com
Frank A McRae
General Manager
Southwest Public Power Agency (SPPA)
160 N PASADENA STE 101
MESA, ARIZONA 85201
generalmanager@sppa.biz
Dennis L Delaney
INDIVIDUAL
160 North Pasadena
Mesa, ARIZONA 85201
dld@krsaline.com
Startrans IO, L.L.C.
Edwin Kichline
700 6TH ST NW STE 700
WASHINGTON, DISTRICT OF
COLUMBIA 20001
edwinkichline@eversheds-sutherland.com
Joseph C. Hall, ESQ
700 Sixth Street, NW
Ste. 700
Washington, DISTRICT OF COLUMBIA
20001
joehall@eversheds-sutherland.com

PDF page 39

- 28 -
Party
Primary Person or Counsel of Record
to be Served
Other Contact to be Served
State Water Contractors
Jonathan Young
1121 L ST STE 1050
SACRAMENTO, CALIFORNIA 95814
jyoung@swc.org
Bhaveeta Mody
Duncan, Weinberg, Genzer & Pembroke
PC
1667 K Street, N.W.
Suite 700
WASHINGTON, DISTRICT OF
COLUMBIA 20006
bkm@dwgp.com
Sean Neal
Attorney
Duncan, Weinberg, Genzer & Pembroke
PC
915 L Street
Suite 1410
Sacramento, CALIFORNIA 95814
smn@dwgp.com
Sylwia Dakowicz
Duncan Weinberg Genzer & Pembroke,
PC
915 L Street
Suite 1410
Sacramento, CALIFORNIA 95814
sd@dwgp.com
Kimberly Letran
Legal Assistant
Duncan Weinberg Genzer & Pembroke,
PC
1667 K ST NW STE 700
WASHINGTON, DISTRICT OF
COLUMBIA 20006
kml@dwgp.com
Stream U.S. Data
Centers, L.L.C.
Kent Watson
2001 ROSS AVE
DALLAS, TEXAS 75201
kwatson@stream-dc.com

SunZia Transmission,
LLC
Robert Daileader
Nixon Peabody LLP
799 9th Street NW
Suite 500
Washington, DISTRICT OF COLUMBIA
20001
rdaileader@nixonpeabody.com
Angela Leon
Manager, Regulatory Compliance
1088 Sansome Street
San Francisco, CALIFORNIA 94111
Regulatory@patternenergy.com
SunZia Wind North
LLC
Robert Daileader
Nixon Peabody LLP
799 9th Street NW
Suite 500
Washington, DISTRICT OF COLUMBIA
20001
rdaileader@nixonpeabody.com
Cameron Yourkowski
Dir., Regulatory & Market Affa
Pattern Energy Group Inc.
1088 Sansome Street
SAN FRANCISCO, CALIFORNIA
94111
cameron.yourkowski@patternenergy.com

PDF page 40

- 29 -
Party
Primary Person or Counsel of Record
to be Served
Other Contact to be Served
SunZia Wind South
LLC
Robert Daileader
Nixon Peabody LLP
799 9th Street NW
Suite 500
Washington, DISTRICT OF COLUMBIA
20001
rdaileader@nixonpeabody.com
Cameron Yourkowski
Dir., Regulatory & Market Affa
Pattern Energy Group Inc.
1088 Sansome Street
SAN FRANCISCO, CALIFORNIA
94111
cameron.yourkowski@patternenergy.com
Sustainable FERC
Project
Kelsie Gomanie
NRDC/FERC Project
1300 MONROE ST APT 202
DENVER, COLORADO 80206
kgomanie@nrdc.org

Trans Bay Cable LLC
William Lavarco
Senior FERC Counsel
801 Pennsylvania Ave., NW
Suite 220
Washington, DISTRICT OF COLUMBIA
20004
william.lavarco@nee.com
Lenneal Gardner
Regulatory and Business Manage
PO BOX 666
PITTSBURG, CALIFORNIA 94565
lenneal.gardner@transbaycable.com

PDF page 41

- 30 -
Party
Primary Person or Counsel of Record
to be Served
Other Contact to be Served
Transmission Agency of
Northern California
Michael Postar
Attorney
Duncan, Weinberg, Genzer & Pembroke
PC
1667 K Street, NW
Suite 700
Washington, DISTRICT OF COLUMBIA
20006
mrp@dwgp.com
Bhaveeta Mody
Duncan, Weinberg, Genzer & Pembroke
PC
1667 K Street, N.W.
Suite 700
WASHINGTON, DISTRICT OF
COLUMBIA 20006
bkm@dwgp.com
Sylwia Dakowicz
Duncan Weinberg Genzer & Pembroke,
PC
915 L Street
Suite 1410
Sacramento, CALIFORNIA 95814
sd@dwgp.com
Nina Wu
Duncan, Weinberg, Genzer & Pembroke,
P.C.
1667 K Street, NW
Suite 700
WASHINGTON, DISTRICT OF
COLUMBIA 20006
nzw@dwgp.com
Julie L Smith
Legal Assistant
Duncan, Weinberg, Genzer & Pembroke,
P.C.
1667 K Street, N.W., Suite 700
Washington, DISTRICT OF COLUMBIA
20006
JLS@dwgp.com
Valley Electric
Association, Inc.
Gabriel De Guzman
PO Box 237
Pahrump, NEVADA 89041
gdeguzman@vea.coop
Stephan Brad Van Cleve
2321 Fairview Avenue East, #3
Seattle, WASHINGTON 98102
Multnomah
bvc@dvclaw.com
Verrus LLC
Gabriel Tabak
Head of Energy Policy
Verrus LLC
918 N RENGSTORFF AVE
MOUNTAIN VIEW, CALIFORNIA
94043
gabe@verrusdata.com

Viridon Path 15 LLC
Chad Newhouse
208 E EUCLID AVE
PROSPECT HEIGHTS, ILLINOIS 60070
chad@viridon.com
Veronica Gomez
208 E EUCLID AVE
PROSPECT HEIGHTS, ILLINOIS 60070
veronica@viridon.com

PDF page 42

- 31 -
Party
Primary Person or Counsel of Record
to be Served
Other Contact to be Served
Vistra Corp.
J. Arnold Quinn
INDIVIDUAL
325 7th Street, N.W
Suite 520
Washington, DISTRICT OF COLUMBIA
20004
arnie.quinn@vistracorp.com
Andrew Weinstein
Director of ISO-NE Markets
Vistra Corp.
325 7th Street, NW
WASHINGTON, DISTRICT OF
COLUMBIA 20004
andrew.weinstein@vistracorp.com
Nicholas Gladd
Wilson Sonsini Goodrich & Rosati, P.C.
201 Washington St.
Suite 2000
Boston, MASSACHUSETTS 02108
ngladd@wsgr.com
Sarah Greenberg
Wilson Sonsini Goodrich & Rosati
1700 K ST NW FL 5
WASHINGTON, DISTRICT OF
COLUMBIA 200
sgreenberg@wsgr.com
Rachel Neuburger
Wilson Sonsini Goodrich & Rosati
1700 K ST NW FL 5
WASHINGTON, DISTRICT OF
COLUMBIA 200
rneuburger@wsgr.com
Voltus, Inc.
Kimaya Abreu
Voltus
Voltus, Inc.
2443 Fillmore Street
#380-3427
San Francisco, CALIFORNIA 94115
kabreu@voltus.co

WATT Coalition
Julia Selker
Grid Strategies LLC
WATT Coalition
9207 KIRKDALE RD
BETHESDA, MARYLAND 20817
jselker@gridstrategiesllc.com

Western Area Power
Administration
Steven Sanders
Strategic Electric Industry
Upper Great Plains Region
2900 4th Ave North, Room 600
Billings, MONTANA 59101-5800
sanders@wapa.gov
Evan B. Bekkedahl
Attorney
Office of General Counsel
12155 W. Alameda Parkway
Lakewood, COLORADO 80228
bekkedahl@wapa.gov
Williams Companies,
The
Danielle Bertoldi
Director, Government Affairs
Williams Companies, The
555 13TH ST NW STE 440W
WASHINGTON, DISTRICT OF
COLUMBIA 20004
danielle.bertoldi@williams.com

PDF page 43

- 32 -
Party
Primary Person or Counsel of Record
to be Served
Other Contact to be Served
WIRES
Larry Gasteiger
Executive Director
529 14TH ST NW STE 1280
WASHINGTON, DISTRICT OF
COLUMBIA 20045
lgasteiger@exec.wiresgroup.com
Pauline Foley
Contractor
WIRES
529 14TH ST NW STE 1280
WASHINGTON, DISTRICT OF
COLUMBIA 20045
pfoley@wiresgroup.com