Valley Electric asks FERC to rescind the CAISO show cause order as to it
Valley Electric Association (VEA), an electric cooperative in the CAISO area that says it is not a public utility under section 201(f), asks FERC to rescind the June 18, 2026 show cause order as to VEA. It also conditionally asks for more time to respond.
Asks FERC to: Rescind the show cause order as to VEA. If FERC has not acted by November 16, 2026, extend VEA's response time until thirty days after FERC rules on the motion.
Asks FERC to remove VEA from the E-10 CAISO show cause proceeding rather than answer its directives. FERC's order said it would rescind at a non-public utility's request.
E-10 CAISO: Show cause or propose tariff changes in 60 days (p. 5)
Key points
- VEA asks FERC to rescind the show cause order as to VEA, citing the Commission's statement that it would do so at a non-public utility's request.
asks the Commission to rescind its June 18, 2026 show cause order as to VEA, as the Commission has said it will do at a non-public utility’s request. PDF p. 1
- VEA says it is an electric cooperative and not a public utility under section 201(f) of the Federal Power Act.
VEA is an electric cooperative that is not a public utility under Section 201(f) of the Federal Power Act PDF p. 2
- VEA says any large load in its territory would connect to the 230 kV system of GridLiance West, a public utility that remains a respondent.
Any large load seeking service in VEA’s territory would, either directly or through VEA, interconnect to the 230 kV system of GridLiance West LLC (“GLW”), a public utility that remains a respondent in this proceeding, rather than to VEA’s 138 kV facilities. PDF p. 3
- If FERC has not acted by November 16, 2026, VEA conditionally asks for a brief extension of its time to respond until the Commission rules.
If the Commission has not acted on this motion by November 16, 2026, VEA conditionally requests, pursuant to Rule 2008, a brief extension of its time to respond to the Show Cause Order until the Commission rules. PDF p. 3
- VEA reports that it conferred with CAISO, which supports the motion.
VEA has conferred with the CAISO in advance of this filing and is authorized to state that the CAISO supports this motion. PDF p. 7
- VEA concludes a section 205 filing is not warranted for it.
VEA has therefore concluded that a Section 205 filing is not warranted PDF p. 8
Contents · 12 sections
- I. COMMUNICATIONS
- II. DESCRIPTION OF VEA
- III. BACKGROUND
- IV. JUSTIFICATION FOR RESCISSION
- A. VEA Is Exempt From the Commission’s Jurisdiction Under FPA Section 201(f)
- B. VEA Will Continue to Coordinate with the CAISO and Remains Subject to the
- C. VEA’s Participation in the Joint PTOs’ Request for Abeyance Does Not Alter Its
- D. Large Loads in VEA’s Territory Would Interconnect to GLW’s 230 kV System,
- V. CONDITIONAL REQUEST FOR EXTENSION OF TIME AND WAIVER OF
- VI. CONCLUSION
- C. Anthony Braun
- C. Anthony Braun
Topics in the text: Filing procedure
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Filing procedure
VEA is a non-public utility under Section 201(f) of the Federal Power Act and asks the Commission to rescind its June 18, 2026 show cause order as to VEA, as the Commission has said it will do at a non-public utility’s request.1 If the Commission has not acted by November 16, 2026, VEA asks that…Read this passage
I. COMMUNICATIONS
printed heading
COMMUNICATIONS Pursuant to Rule 203(b)(3), VEA requests that all communications and service in this proceeding be directed to the following persons:5 Brad Van Cleve Davison Van Cleve, P.C. 4675 W.Read this passage
II. DESCRIPTION OF VEA
printed heading
DESCRIPTION OF VEA VEA is a rural electric distribution cooperative based in Pahrump, Nevada, with a service territory in southern Nevada and a small portion in California.Read this passage
III. BACKGROUND
printed heading · Topic match: Filing procedure
On August 3, VEA joined fourteen other CAISO Participating TOs (collectively, the “Joint PTOs”) in a Request for Abeyance asking the Commission to extend each Joint PTO’s deadline to respond to the Show Cause Order to November 16, 2026.10 The Commission’s August 14 Order granted both forms of…Read this passage
IV. JUSTIFICATION FOR RESCISSION
printed heading
IV.Read this passage
A. VEA Is Exempt From the Commission’s Jurisdiction Under FPA Section 201(f)
printed heading
VEA Is Exempt From the Commission’s Jurisdiction Under FPA Section 201(f) Section 201(f) excludes from Part II of the FPA “an electric cooperative that receives financing under the Rural Electrification Act of 1936 . . . or that sells less than 4,000,000 megawatt hours of electricity per year.”13…Read this passage
B. VEA Will Continue to Coordinate with the CAISO and Remains Subject to the
printed heading
EL26-71-000, at 4 (filed July 31, 2026) (“Six Cities Motion”). 15 August 14 Order at PP 5, 7. 16 Show Cause Order at P 2 n.9. - 6 - responding to the Show Cause Order, to the extent the CAISO requests its assistance and with respect to the load interconnection provisions of its TO Tariff.Read this passage
C. VEA’s Participation in the Joint PTOs’ Request for Abeyance Does Not Alter Its
printed heading · Topic match: Filing procedure
The Joint PTOs explained that many of the Commission’s concerns “can only be resolved with complementary or, at a minimum, non-conflicting tariff provisions among the CAISO Tariff and the various TO Tariffs,” and that their requests “reflect a coordinated regional effort consistent with Commission…Read this passage
D. Large Loads in VEA’s Territory Would Interconnect to GLW’s 230 kV System,
printed heading
Large Loads in VEA’s Territory Would Interconnect to GLW’s 230 kV System, Which Remains Before the Commission The Show Cause Order addresses large loads, which the Commission described as new commercial or industrial customers with a peak load of 50 MW or greater that interconnect to the…Read this passage
V. CONDITIONAL REQUEST FOR EXTENSION OF TIME AND WAIVER OF
printed heading · Topic match: Filing procedure
Accordingly, if the Commission has not acted on this motion by November 16, 2026, VEA requests that its time to respond to the Show Cause Order be extended until thirty days after the Commission acts on this motion.Read this passage
VI. CONCLUSION
printed heading
CONCLUSION WHEREFORE, VEA respectfully requests that the Commission (1) rescind the Show Cause Order as against VEA as a non-public utility and amend the caption accordingly; (2) if the Commission has not acted by November 16, 2026, extend VEA’s time to respond to the Show Cause Order as requested…Read this passage
CERTIFICATE OF SERVICE
printed heading
Teco Ave.; Suite 230 Las Vegas, NV 89118 bvc@dvclaw.com Attorney for Valley Electric Association, Inc. - 2 - SERVICE LIST Docket No.Read this passage
C. Anthony Braun
printed heading
Anthony Braun Braun Blaising & Wynne, P.C. 555 Capitol Mall Suite 570 Sacramento, CALIFORNIA 95814 braun@braunlegal.com Jessica Melms Braun Blaising & Wynne, P.C. 2600 Capitol Avenue Suite 400 Sacramento, CALIFORNIA 95816 melms@braunlegal.com Base Power Company Andrew Hosea Associate General…Read this passage
C. Anthony Braun
printed heading
Hammond California Public Utilities Commission 505 Van Ness Avenue San Francisco, CALIFORNIA 94102 christine.hammond@cpuc.ca.gov Camus Energy Anthony Harrison VP,Policy & Strategic Partners Camus Energy 1821 S Bascom Ave Suite 515 Campbell, CALIFORNIA 95008 anthony@camus.energy Capital Power…Read this passage