ER26-3380-000 · 2026-10-23 · FERC

Notice Addressing Motion to Hold Proceeding in Abeyance: EL26-108 initial briefs moved to January 11, 2027 and reply briefs to January 26, 2027

FERC's Secretary extends the paper hearing brief deadlines in the PJM backstop procurement dockets after PJM's abeyance motion, moving initial briefs to January 11, 2027 and reply briefs to January 26, 2027.

Moves the briefing schedule in PJM's separate backstop procurement paper hearing, which concerns capacity for new large loads, the subject of the E-7 adequacy report.

E-7 PJM: 30-day report on serving large loads with adequate generation (p. 8)

Key points

  1. Initial briefs in EL26-108 move from November 13, 2026 to January 11, 2027 and reply briefs from December 3, 2026 to January 26, 2027.
    the deadline for submission of initial briefs in Docket No. EL26-108-000 is extended from November 13, 2026 to 5pm on January 11, 2027, and the deadline for reply briefs is extended from December 3, 2026 to 5pm on January 26, 2027. Source text

Read topic-matched comments in ER26-3380

Topics in the text: Filing procedure

What the document says

Unpaginated filing

FERC moves EL26-108 initial briefs to January 11, 2027 and reply briefs to January 26.

the deadline for submission of initial briefs in Docket No. EL26-108-000 is extended from November 13, 2026 to 5pm on January 11, 2027 Source text

Unpaginated filing

FERC moves EL26-108 initial briefs to January 11, 2027 and reply briefs to January 26.

the deadline for reply briefs is extended from December 3, 2026 to 5pm on January 26, 2027 Source text

Unpaginated filing

Northern Virginia Electric Cooperative supported PJM's abeyance motion.

On October 14, 2026, Northern Virginia Electric Cooperative, Inc., filed an answer supporting PJM’s motion. Source text

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Filing procedure

ER26-3380-000 EL26-108-000 NOTICE ADDRESSING MOTION TO HOLD PROCEEDING IN ABEYANCE (October 23, 2026) On October 13, 2026, pursuant to Rule 212 of the Commission’s Rules of Practice and Procedure,[fn:2] PJM Interconnection, L.L.C. (PJM) filed a motion to hold the paper hearing proceedings and the…
Read this passage Filed comments: Filing procedure

Footnotes

Word notes

Footnotes [fn:2] 18 C.F.R. § 385.212 (2025). [fn:3] PJM Motion at 1 (citing PJM Interconnection, L.L.C., 196 FERC ¶ 61,245 (2026)). header1 (Word template) - 1 - header2 (Word template) Docket Nos.
Read this passage