Order Instituting Proceeding Under Section 206 of the Federal Power Act and Consolidating with Other Proceedings re PJM Interconnection, L.L.C. et al. v.…
Text extracted from the eLibrary original (SHA-256 02683595b969240a…). Download the original from the official source.
Contents · 2 sections
Read topic-matched comments in EL25-49
Topics in the text: Connecting load and generation · Reliability and curtailment · Cost allocation
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Connecting load and generation
As discussed below, based on the combined records of the technical conference and the Constellation complaint proceeding, we find that PJM’s Tariff appears to be unjust, unreasonable, unduly discriminatory or preferential.Read this passage Filed comments: Connecting load and generation
Background
printed heading · Topic match: Connecting load and generation
A number of commenters call for improvements in load forecasting in response to resource adequacy concerns,[fn:109] including adopting standardized forecasting practices.[fn:110] Parties note that co-located load may be especially difficult to forecast as large loads may be considering multiple…Read this passage Filed comments: Connecting load and generation
Discussion
printed heading · Topic match: Connecting load and generation
In addition, parties have raised questions about whether and how administrative or non-bypassable wholesale charges that are collected through transmission rates should be allocated to co-location arrangements.[fn:239] Given these questions, we find that the existing Tariff may be unjust,…Read this passage Filed comments: Connecting load and generation
Footnotes
Word notes · Topic match: Connecting load and generation
The Network Customer’s Network Load shall include all load (including losses, Non-Dispatched Charging Energy, and Load Serving Charging Energy) served by the output of any Network Resources designated by the Network Customer.Read this passage Filed comments: Connecting load and generation