EL25-49-000 · 2025-03-24 · NextEra Energy Transmission MidAtlantic, Inc.
Answer of NextEra Energy Transmission MidAtlantic, Inc. to the Order Instituting Proceeding Under Section 206 of the Federal Power Act and Consolidating…
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C.
Allegheny Electric Cooperative, Inc.
American Transmission Systems, Incorporated Atlantic City Electric Company
Baltimore Gas and Electric Company
Delmarva Power & Light Company
Duke Energy Ohio, Inc.
Duke Energy Kentucky, Inc.
East Kentucky Power Cooperative, Inc.
Essential Power Rock Springs, LLC
Hudson Transmission Partners, LLC
Jersey Central Power & Light Company
Mid-Atlantic Interstate Transmission, LLC Neptune Regional Transmission System, LLC Old Dominion Electric Cooperative
PECO Energy Company
PPL Electric Utilities Corporation
Potomac Electric Power Company
Public Service Electric and Gas Company
Rockland Electric Company
Trans-Allegheny Interstate Line Company
Transource West Virginia, LLC
UGI Utilities, Inc.
Monongahela Power Company
The Potomac Edison Company
Commonwealth Edison Company
Commonwealth Edison Company of Indiana, Inc. The Dayton Power and Light Company
AEP Appalachian Transmission Company, Inc. AEP Indiana Michigan Transmission Company, Inc. AEP Kentucky Transmission Company, Inc.
AEP Ohio Transmission Company, Inc.
AEP West Virginia Transmission Company, Inc. Appalachian Power Company
Indiana Michigan Power Company
Kentucky Power Company
Kingsport Power Company
Ohio Power Company
Wheeling Power Company
Duquesne Light Company
Virginia Electric and Power Company
Linden VFT, LLC
Docket Nos.
EL25-49-000
PDF page 2
2
City of Cleveland, Department of Public Utilities, Division
of Cleveland Public Power
City of Hamilton, OH
Southern Maryland Electric Cooperative, Inc.
Ohio Valley Electric Corporation
AMP Transmission, LLC
Silver Run Electric, LLC
NextEra Energy Transmission MidAtlantic Indiana, Inc.
Wabash Valley Power Association, Inc.
Keystone Appalachian Transmission Company
Large Loads Co-Located at Generating Facilities
Constellation Energy Generation, LLC
v.
PJM Interconnection, L.L.C.
AD24-11-000
EL25-20-000
(Consolidated)
ANSWER OF NEXTERA ENERGY TRANSMISSION MIDATLANTIC, INC. TO THE
ORDER INSTITUTING PROCEEDING UNDER SECTION 206 OF THE FEDERAL
POWER ACT AND CONSOLIDATING WITH OTHER PROCEEDINGS
Pursuant to Rule 2131 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (“Commission”), NextEra Energy Transmission MidAtlantic, Inc. (“NEET MidAtlantic”) hereby submits this answer (“Answer”) to the Commission Order Instituting Proceeding Under Section 206 of the Federal Power Act (“FPA”) and Consolidating with Other Proceedings (“Show Cause Order”) directing PJM Interconnection, L.L.C. (“PJM”) and PJM Transmission Owners (collectively, “TOs,” and individually, each a “TO”) to either:
(1) show why the existing PJM Open Access Transmission Tariff, the PJM Amended and Restated Operating Agreement, and the Reliability and Assurance Agreement Among Load Serving Entities in PJM (“Tariff”) remains just and reasonable and not unduly discriminatory or preferential without provisions addressing with sufficient clarity or consistency the rates, terms, and conditions of service that apply to co-located load arrangements; or (2) explain what changes to the Tariff would remedy the identified concerns if the Commission were to determine that the Tariff has become unjust and unreasonable or unduly discriminatory or preferential and, therefore, proceeds to establish a replacement Tariff.2 Specifically, NEET MidAtlantic submits this Answer to show why NEET MidAtlantic presently takes no position on the issue of whether the PJM Tariff is just and reasonable and not unduly discriminatory or preferential as it relates to provisions addressing with sufficient clarity or consistency the rates, terms, and conditions of
1 18 C.F.R. §§ 385.213 (2024).
2 PJM Interconnection, L.L.C., 190 FERC ¶ 61,115, at PP 2, 87 (2025).
PDF page 3
3
service that apply to co-location arrangements in the FPA section 206 proceeding instituted in the above-captioned dockets.
I. COMMUNICATIONS
Communications regarding this Answer should be addressed to the following individuals:
Evan Yager
President
NextEra Energy Transmission MidAtlantic,
Inc.
700 Universe Blvd
Juno Beach, FL 33408
(607) 221-8223
evan.yager@nexteraenergy.com
Elizabeth Ramey
Senior Attorney
NextEra Energy, Inc.
801 Pennsylvania Avenue NW, Suite 220
Washington, DC 20004
(202) 909-5696
elizabeth.ramey@nexteraenergy.com
II. BACKGROUND
NEET MidAtlantic was formed on July 8, 2015, as a Delaware limited liability company
under the name NextEra Energy Transmission MidAtlantic, LLC.3 NEET MidAtlantic is a
wholly owned subsidiary of NextEra Energy Transmission Holdings, LLC, and an indirect, wholly owned subsidiary of NextEra Energy Transmission, LLC.
NEET MidAtlantic was formed to develop, construct, finance, own, operate, and
maintain high-voltage electric transmission facilities within the PJM region. On October 29, 2020, NEET MidAtlantic acquired certain limited transmission facilities, consisting of approximately 40 circuit miles (or approximately 20 line miles) of 345 kV electric power transmission lines and related power line poles from Commonwealth Edison Company of
Indiana, Inc.4 NEET MidAtlantic Indiana and PJM subsequently made an FPA section 205 filing to incorporate NEET MidAtlantic Indiana’s formula rate into the PJM Tariff as Attachment H-
3 NEET MidAtlantic Indiana converted to an Illinois corporation on September 14, 2018. Subsequently, on December 18, 2019, NEET MidAtlantic Indiana, which is domesticated in Indiana, changed its name to NextEra Energy Transmission MidAtlantic Indiana, Inc. On March 13, 2024, NEET MidAtlantic Indiana, Inc. submitted revised tariff records and a notice of succession to change its name from NEET MidAtlantic Indiana to NextEra Energy MidAtlantic, Inc. See NextEra Energy Transmission MidAtlantic Indiana, Inc., Docket No. ER24-1471-000 (Apr. 12, 2024) (delegated letter order).4 No prior approval by the Commission under FPA section 203 was necessary for this transaction because the market value of these transmission assets was less than $1 million. The transaction was, however, subject to regulatory approval of the Indiana Utility Regulatory Commission. Verified Joint Petition of Commonwealth Edison Company of Indiana, Inc., NextEra Energy Transmission MidAtlantic Indiana, Inc., and Commonwealth Edison Company, Cause No. 45335 (Ind. U.R.C. Jan. 24, 2020).
PDF page 4
4
33A and H-33B and to establish NEET MidAtlantic Indiana as a PJM TO.5 To date, NEET MidAtlantic does not own substantial transmission in PJM.6
III. ANSWER
As detailed in the Background section, NEET MidAtlantic currently owns a limited segment of transmission facilities within the PJM region, comprising only approximately 40 circuit miles (20 line miles) of 345 kV electric power transmission lines and related infrastructure. NEET MidAtlantic does not serve retail load, nor does it presently have any operational or planned co-located load arrangements within PJM that would necessitate revisions to or clarifications within the PJM Tariff.
The Commission’s Show Cause Order specifically seeks explanations from PJM and the PJM TOs regarding the adequacy, clarity, consistency, and justness and reasonableness of provisions within the PJM Tariff addressing co-located load arrangements. These provisions inherently pertain to TOs or market participants directly involved in or contemplating co-located load configurations. Given NEET MidAtlantic neither currently participates in nor plans to establish such arrangements, the tariff provisions under scrutiny do not apply to its transmission facilities or operations.
Consequently, any substantive commentary or proposed modifications by NEET
MidAtlantic on the Tariff provisions concerning co-located load arrangements would not meaningfully assist the Commission in addressing the specific issues identified in the Show Cause Order.7
Accordingly, NEET MidAtlantic takes no position on the issue of whether the PJM Tariff is just and reasonable and not unduly discriminatory or preferential as it relates to provisions addressing with sufficient clarity or consistency the rates, terms, and conditions of service that apply to co-location arrangements.
5 See PJM Interconnection, L.L.C., 173 FERC ¶ 61,033 (2020) (accepting NEET MidAtlantic Indiana’s formula rate and revisions to the PJM Consolidated Transmission Owners Agreement, effective October 29, 2020).6 NEET MidAtlantic is a Designated Entity pursuant to section 1.5.8(a) of the PJM Operating Agreement, and it was recently selected to construct the MidAtlantic Resiliency Link Project. See Amended and Restated Operating Agreement of PJM Interconnection, L.L.C., Schedule 6, Section 1.5.8(a).7 While NEET MidAtlantic does not take an official position on these issues, NEET MidAtlantic does not purport to speak on behalf of any NextEra Energy, Inc. affiliates in the PJM region.
PDF page 5
5
IV. CONCLUSION
For the foregoing reasons, NEET MidAtlantic respectfully requests that the Commission accept this Answer as NEET MidAtlantic’s formal response to the Show Cause Order and the questions directed to PJM and PJM TOs therein.
Respectfully submitted,
/s/ Elizabeth Ramey
Elizabeth Ramey
Senior Attorney
NextEra Energy, Inc.
801 Pennsylvania Avenue NW, Suite 220
Washington, DC 20004
(202) 909-5696
elizabeth.ramey@nexteraenergy.com
Counsel for NextEra Energy Transmission
MidAtlantic, Inc.
Dated: March 24, 2025
PDF page 6
CERTIFICATE OF SERVICE
Pursuant to Rule 210 of the Commission’s Rules of Practice and Procedure, I hereby certify that I, on this day, have served the foregoing document upon each person designated on the official service lists compiled by the Secretary of the Commission in these proceedings. Dated at Washington, DC, this 24th day of March 2025.
/s/ Elizabeth Ramey
Elizabeth Ramey
Senior Attorney
NextEra Energy, Inc.
801 Pennsylvania Avenue NW, Suite 220
Washington, DC 20004
(202) 909-5696
elizabeth.ramey@nexteraenergy.com