Answer of NextEra Energy Transmission MidAtlantic, Inc. to the Order Instituting Proceeding Under Section 206 of the Federal Power Act and Consolidating…
Text extracted from the eLibrary original (SHA-256 2351fd8ad2832741…). Download the original from the official source.
Contents · 4 sections
Read topic-matched comments in EL25-49
Topics in the text: Connecting load and generation
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Connecting load and generation
UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C.Read this passage Filed comments: Connecting load and generation
I. COMMUNICATIONS
printed heading
COMMUNICATIONS Communications regarding this Answer should be addressed to the following individuals: Evan Yager President NextEra Energy Transmission MidAtlantic, Inc. 700 Universe Blvd Juno Beach, FL 33408 (607) 221-8223 evan.yager@nexteraenergy.com Elizabeth Ramey Senior Attorney NextEra Energy,…Read this passage
II. BACKGROUND
printed heading
BACKGROUND NEET MidAtlantic was formed on July 8, 2015, as a Delaware limited liability company under the name NextEra Energy Transmission MidAtlantic, LLC.3 NEET MidAtlantic is a wholly owned subsidiary of NextEra Energy Transmission Holdings, LLC, and an indirect, wholly owned subsidiary of…Read this passage
III. ANSWER
printed heading · Topic match: Connecting load and generation
NEET MidAtlantic does not serve retail load, nor does it presently have any operational or planned co-located load arrangements within PJM that would necessitate revisions to or clarifications within the PJM Tariff.Read this passage Filed comments: Connecting load and generation
IV. CONCLUSION
printed heading
CONCLUSION For the foregoing reasons, NEET MidAtlantic respectfully requests that the Commission accept this Answer as NEET MidAtlantic’s formal response to the Show Cause Order and the questions directed to PJM and PJM TOs therein.Read this passage
CERTIFICATE OF SERVICE
printed heading
Dated at Washington, DC, this 24th day of March 2025. /s/ Elizabeth Ramey Elizabeth Ramey Senior Attorney NextEra Energy, Inc. 801 Pennsylvania Avenue NW, Suite 220 Washington, DC 20004 (202) 909-5696 elizabeth.ramey@nexteraenergy.comRead this passage