EL25-49-000 · 2025-03-24 · Dayton Power and Light Company, The

Answer of The Dayton Power and Light Company d/b/a AES Ohio to Order Instituting Proceeding Under Section 206 of the Federal Power Act and Consolidating…

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Interconnection, L.L.C., et al.

)
Docket No. EL25-49-000

Large Loads Co-Located at Generating
Facilities
)
Docket No. AD24-11-000
Constellation Energy Generation, LLC

v.

PJM Interconnection, L.L.C.
)
Docket No. EL25-20-000
(consolidated)

ANSWER OF
THE DAYTON POWER AND LIGHT COMPANY D/B/A AES OHIO
TO ORDER INSTITUTING PROCEEDING  UNDER SECTION 206 OF THE
FEDERAL POWER ACT  AND CONSOLIDATING WITH OTHER
PROCEEDINGS

Pursuant to Rules 206 and 213 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (“FERC” or “Commission”),1 The Dayton Power and Light Company d/b/a AES Ohio (“AES Ohio”) submits this answer and attachment below providing responses to the Commission’s Order Instituting Proceeding Under Section 206 of the Federal Power Act and Consolidating with Other Proceedings, issued on February 20, 2025.2   As discussed in the  responses  below,  AES Ohio believes that a framework for co-location configurations is addressed by the PJM Tariff, and that the Tariff is just and

1 18 C.F.R. §§ 385.206, 385.213 (2024). 2 PJM Interconnection, L.L.C., 190 FERC ¶ 61,195 (2025) (“Show Cause Order”).

PDF page 2

reasonable as to service to such co-located load taken under PJM Network Integration Transmission Service or Firm Point to Point Service.3  However, other approaches may also be just and reasonable and not unduly discriminatory to the extent that they incentivize co-located load that provides reliability benefits and cost savings.  AES Ohio is open to working with PJM and stakeholders to explore alternative transmission service arrangements for certain co-located load configurations that may be appropriate to reflect specific co-located load circumstances and associated system needs. If alternative arrangements are considered, co-located load should pay for its use of the PJM Transmission System in a manner that avoids unjust and unreasonable outcomes and that holds other transmission customers harmless. AES Ohio respectfully thanks the Commission for seeking input on this important and highly impactful topic. Respectfully submitted,

/s/ William M. Rappolt

William M. Rappolt
Assistant General Counsel, FERC
AES US Services LLC
4300 Wilson Blvd
Arlington, VA 22203
Tel: 571-533-9018
Email: william.rappolt@aes.com

Counsel for The Dayton Power and Light
Company d/b/a AES Ohio
Dated: March 24, 2025

3 As noted below, for many of specific questions asked by the Commission, AES Ohio generally agrees with the response provided by the Indicated TOs in response to show cause order and filed today in this proceeding.

PDF page 3

Attachment A

a. General
i. Do you agree with the jurisdictional principles outlined in section VI.A and should the Commission reach any other conclusions

regarding jurisdiction in a final order it may issue in this
proceeding?  Why or why not?

AES Ohio generally agrees with the Indicated TOs response.

ii. Does the Tariff sufficiently address co-location arrangements with respect to each issue listed in this order?  Please include specific

tariff provisions or other governing documents that may apply;

AES Ohio believes that a framework for co-location is addressed by the PJM Tariff, and that the Tariff is just and reasonable as to service to co-located load taken under PJM Network Integration Transmission Service or Firm Point to Point Service.  However, recognizing that co-location is rapidly developing and evolving, AES Ohio is open to working with PJM and stakeholders to explore alternative transmission service arrangements for certain co-located load configurations that may be appropriate to reflect specific co-located load circumstances and associated system needs. In certain circumstances, co-located large loads may benefit the grid by providing reliability benefits, decreasing congestion costs or limiting transmission upgrades.  In such cases, co-location could be incentivized by appropriately allocating costs, and allowing such load to share in the benefits, of the arrangement.  However, in all cases, co located load must pay for its use of the PJM Transmission System in a manner that avoids unjust and unreasonable outcomes and that holds other AES Ohio transmission customers harmless.

iii. If the Tariff does not sufficiently address co-location
arrangements, how should the Tariff be modified to do so?  As part
of your answer, address whether portions of the Guidance
Document may serve as a just and reasonable and not unduly
discriminatory or preferential replacement rate.  Alternatively,
address whether existing rules in the Tariff may or should be
modified to address co-location arrangements;

See response to a.ii above.

PDF page 4

iv. Parties may also address how co-located loads are similar to or
disparate from other types of arrangements where load and
generation share the same point of interconnection (such as Behind
the Meter Generation as defined in PJM’s Tariff or non-retail
behind the meter generation) and should consider how any
proposed replacement rate would interact with these other
arrangements.

As explained by PJM in the Guidance Document, the PJM Tariff allows for generation to be treated as being “behind the meter” when such generation is co-located with a load and meets the specific defined criteria in the PJM Tariff.  AES Ohio agrees with PJM’s explanation of (1) how such “Behind the Meter Generation” interacts with the co-located load for the purposes of energy netting and (2) the restrictions placed on such “Behind the Meter Generation” with respect to that generation’s participation in the PJM market. AES Ohio does not view “Behind the Meter Generation” as disparate to other co-location arrangements, but rather as one of the arrangements under which co-location may occur in PJM.  To the extent that parties wish to expand or revisit the definition of “Behind the Meter Generation” with respect to current or future co-location configurations, AES Ohio believes that these discussions could be considered through the PJM stakeholder process, subject to the requirement that such additional configurations do not unduly discriminate against other transmission customers.  See response to a.ii.

b. Transmission Service

i. Please explain whether and to what extent different configurations
of co-located load rely on or otherwise use the transmission system
to receive power, directly or indirectly, from the co-located
generator;

Unless it is physically islanded without any connection to the PJM Transmission System, co-located is connected to, uses, and benefits from the PJM Transmission System.  In these cases, and as noted in response to a.ii above, co-located load should pay an appropriate share of system costs. However, there may be a range of potentially appropriate cost allocation frameworks.

PDF page 5

ii. Please explain whether and to what extent different co-location configurations impose costs on the transmission system or increase transmission costs allocated to other parties.  How can those costs be approximated, given that certain co-location configurations may change power flows on the grid and necessitate upgrades to the

transmission system?  Retail loads typically take service from
wholesale entities that pay for Network Integration Transmission
Service that allocates these costs; co-located loads may not.
Network Loads pay directly for Network Integration Transmission
Service.  How should PJM estimate the effects that different
configurations of co-located load have on the transmission system? Should these costs be passed through to co-location arrangements

in some way, and, if so, how?

AES Ohio generally agrees with the Indicated TOs response.  See responses to b.i and a.ii above.

iii. Please explain whether co-location arrangements are or should be required to take Network Integration Transmission Service or

Point-to-Point Transmission Service; or whether a more tailored
new category of transmission service is warranted.  Please also
address any cost allocation implications of your position on this issue;

AES Ohio generally agrees with the Indicated TOs response with respect to the current options available to load customers in PJM (i.e. Network Integration Transmission Service or Point to Point Transmission Service).  However, as noted in its responses above, co-located large loads may bring benefits to the system that could be incentivized through one or more alternative transmission service arrangements, and AES Ohio is open to working with stakeholders and regulators to explore such alternatives, provided that any such alternative results in a just and reasonable outcome that remains equitable to all current and future transmission customers.  See response to a.ii.

iv. What changes to the rates, terms, and conditions of Network
Integration Transmission Service or Point-to-Point Transmission
Service or, alternatively, what new form of transmission service(s)

PDF page 6

may be necessary for different configurations of co-location to ensure that the Tariff is consistent with cost causation principles and the beneficiary pays principle?

AES Ohio generally agrees with the Indicated TOs response. See response to a.ii.  As indicated above, AES Ohio will continue to work collaboratively with stakeholders.

v. Parties may also wish to address how to determine which co- located load configurations should be required to take Network Integration Transmission Service or Point-to-Point Transmission Service or a new form of transmission service (i.e., whether generalized policies or tests, such as a multi-factor test, to be applied case-by-case, may be appropriate), as well as the magnitude (i.e., how the service taken by co-located load compares to service by other types of load).  For example, if a co-located generator is synchronized to the grid but the load can be configured to be wholly isolated from the grid in the event the co- located generator trips offline, what technical and operational factors should determine whether the co-location arrangement still relies on the transmission system in ways that warrant a requirement that the co-located load take Network Integration Transmission Service or Point-to-Point Transmission Service or a new form of transmission service?  Are there potential co-located load configurations for which tailored approaches may be appropriate?

AES Ohio generally agrees with the Indicated TOs response. As indicated above and consistent with the Indicated TOs response, AES Ohio will continue to work collaboratively with stakeholders to determine whether enhancements to the PJM Tariff would be appropriate.  See response to a.ii.

vi. With respect to the Guidance Document, please explain what it means to be “electrically connected and synchronized to the PJM Transmission System when consuming power” and how that implicates the use of Network Integration Transmission Service or

PDF page 7

Point-to-Point Transmission Service or a new form of transmission
service;

AES Ohio generally agrees with the Indicated TOs response.

vii. What operational or commercial factors of a co-location
arrangement would result in a co-located load not needing to take
any form of transmission service, including what types of special
protection schemes or backup arrangements may be necessary to
ensure the co-located load never takes any form of transmission
service?

AES Ohio generally agrees with the Indicated TOs response.  So long as a co-located load is interconnected to the transmission system, it will be required to take some form of transmission service. However, different configurations may result in different forms of service.  As noted in responses above, AES Ohio is open to working with stakeholders to determine whether a form of service other than full Network Integration Transmission Service or Firm Point to Point Service could be appropriate for certain configurations.

c. Ancillary or other wholesale services
i. Please explain whether and to what extent different configurations of co-location arrangements rely on or benefit from ancillary

services or black start services and, if so, provide specific details about the type of service and how the co-location arrangement

relies on it.  To what extent are these benefits distinct from the
benefits that other Network Integration Transmission Service and
Point-to-Point Transmission Service customers derive from
ancillary services?

AES Ohio generally agrees with the Indicated TOs response.  Co-located load connected to the PJM Transmission System may use the same ancillary services as all other load connected to the system. However, AES Ohio is open to working with stakeholders to determine what might constitute an acceptable showing that a particular configuration receives, or does not receive, co-location benefits.

PDF page 8

ii. Please explain whether and to what extent co-location
arrangements impose costs related to ancillary services or black
start services or increase the costs for such services allocated to other parties and how those costs could be approximated;

AES Ohio generally agrees with the Indicated TOs response.

iii. Please explain whether and to what extent co-location
arrangements use, benefit from, provide, or contribute to the need for transmission system services in a manner that does not fit into a pre-existing category of ancillary services or black start services, and, if so, should new categories of services be created to

accommodate that use?  Alternatively, please explain whether an
alternative mechanism of cost allocation for pre-existing ancillary services would be more appropriate;

So long as it is connected to the transmission system (i.e. not physically islanded), co- located load uses and benefits both from the transmission system and from services provided and delivered by that system just like any other load on the system.  However, co-located load could also provide benefits to the transmission system. Approaches other than the existing tariff may be just and reasonable and not unduly discriminatory to the extent that they incentivize co-located load that provides reliability benefits and cost savings.  See response to a.ii.

iv. What changes to rates, terms, and conditions of ancillary services, including ancillary services procured in PJM’s markets, are

necessary for different configurations of co-location arrangements to ensure that the Tariff is consistent with cost causation principles and the beneficiary pays principle?

AES Ohio generally agrees with the Indicated TOs response.

PDF page 9

v. Please explain how PJM should determine which co-located load configurations take ancillary services or black start services (i.e., whether generalized policies or tests, such as a multi-factor test, to be applied case-by-case may be appropriate), as well as the amount of such service (i.e., how the service taken by co-located load compares to service taken by other types of load);

All co-located load that is directly physically connected to the system takes ancillary and black start services.  If co-located load continues to take NITS or PTP Service, the existing rules under the PJM Tariff will apply

d. Interconnection Procedures and Cost Allocation
i. Does the necessary study process adequately address potential impacts caused by a co-location arrangement or is an additional study or new study process warranted, e.g., a system impact study or generator deactivation study?  PJM should provide the details regarding the geographic scope of the existing necessary study process, what is studied, and how the results are reported, including what opportunities stakeholders, the interconnected transmission owner, or the PJM IMM have to review the results, if any;

AES Ohio generally agrees with the Indicated TOs response.

ii. Please explain whether PJM’s necessary study process allows a co- location arrangement to demonstrate its capability to flexibly adjust its withdrawals from or injections to the transmission system (e.g., by using secondary backup generation or by curtailing on-site load), and reflect this capability in the operating assumptions PJM considers when estimating the co-location arrangement’s impacts on the transmission system?  If not, would it be appropriate to establish a new or revised study process that allows for such a demonstration?

AES Ohio generally agrees with the Indicated TOs response.

PDF page 10

iii. What changes to interconnection procedures and agreements may be necessary to ensure that PJM identifies the reliability impact to the transmission system of load co-locating with existing

generation including the need for dynamic response models?

AES Ohio generally agrees with the Indicated TOs response.

iv. To what extent does a co-location arrangement raise potentially distinct cost-allocation issues relative to a deactivating generator that causes the need for transmission upgrades?  What principles should the Commission apply to allocate the costs of any

transmission upgrades needed to mitigate the impacts of co-
locating load?  What steps should PJM take to ensure these costs are transparent to all parties?

Section V of the PJM Tariff addresses how PJM studies the reliability impacts associated with potential generator deactivations.  AES Ohio’s understanding is that, pursuant to the PJM Tariff, if the generator changes its ISA to enable it to operate in a co-located load arrangement, then any system upgrades must be paid for by the existing removed generator in order to avoid cost subsidization by existing transmission customers.  This is different than if a generator actually retires and shuts down, as any necessary system reinforcements resulting from shut down are paid by transmission customers.

v. Are changes needed to how PJM allocates the costs of any
transmission upgrades needed to mitigate the transmission system impacts of co-locating load, if any, including whether the costs of those upgrades can ever be allocated to a party other than the co- located generator, co-located load, and/or co-location

arrangement?

AES Ohio generally agrees with the Indicated TOs response.

PDF page 11

vi. Are changes to the pro forma interconnection-related agreements necessary to accommodate the addition of co-located load to existing generation?

AES Ohio generally agrees with the Indicated TOs response.

vii. Please explain whether changes to interconnection procedures and agreements are necessary to accommodate new generation interconnecting with co-located load, including whether the existing queue process is sufficient for such arrangements?

AES Ohio generally agrees with the Indicated TOs response.

viii. Please explain whether or not it would be appropriate to establish an interconnection study process outside of PJM’s interconnection queue process for newly interconnecting co-location arrangements that do not exchange power with the transmission system and do not require network upgrades?

AES Ohio generally agrees with the Indicated TOs response.

ix. A generator with a co-located load that is not a party to a transmission service agreement is arguably distinguishable from other generators.  To the extent co-located arrangements create costs, or benefit from bulk power system services, but the generator and load are not exposed to these costs because of their contractual relationship, should PJM modify the Tariff and related agreements to allocate those costs to the generator directly?

AES Ohio does not believe that there is any need to modify the PJM Tariff to change the incidence of transmission service and facilities costs from load to generation.

e. PJM Capacity Market, Reliability, and Resource Adequacy
i. What changes to PJM’s capacity market rules are necessary to ensure that the Tariff specifies how co-located generation and/or load participates in the capacity market in a way that reflects the

PDF page 12

potentially unique physical and operational characteristics of the co-location arrangement (e.g., the presence of secondary backup generation, the capability to curtail on-site load or other operational flexibilities, among others) and is otherwise just, reasonable, and not unduly discriminatory or preferential?

AES Ohio generally agrees with the Indicated TOs response.

ii. What Tariff change or changes to the interconnection service agreement are necessary to ensure that PJM and the interconnected transmission owner have sufficient visibility into the co-located load configuration?

AES Ohio generally agrees with the Indicated TOs response.

iii. Please explain whether the existing Tariff rules are sufficient to ensure resource adequacy if increasing numbers of large existing generators choose to co-locate with load;

AES Ohio generally agrees with the Indicated TOs response.

iv. What deactivation or interconnection modification studies should PJM undertake to ensure resource adequacy and/or protect reliability should an existing generator seek to enter into a co- location arrangement?  If PJM finds that the co-location would cause reliability standards violations, what remediation techniques would be appropriate (e.g., reliability must-run contracts, delaying the co-location arrangement until the reliability violations are addressed, etc.)?

AES Ohio generally agrees with the Indicated TOs response.

v. What changes are necessary, if any, to other PJM planning processes to better plan for and address the resource adequacy and reliability impacts of co-location arrangements, including, for example, whether or not the frequency of such processes might be changed?  Similarly, should PJM consider changes to load

PDF page 13

forecasting methods, informational postings, or the reserve margin
study process to better plan for and address the resource adequacy
and reliability impacts of co-location arrangements?

AES Ohio generally agrees with the Indicated TOs response.  However, to the extent, new rules are developed through the PJM stakeholder process associated with co-located load arrangements, such modifications should be taken into account in the PJM planning process.  AES Ohio also believes that should consider whether forecast frequency  and load addition certainty are adequate considering the pace of large load additions.

vi. Under what circumstances can PJM direct the operators of co-
location arrangements to shed such load if deemed necessary to
preserve system reliability during a declared emergency?

AES Ohio generally agrees with the Indicated TOs response.  However, to the extent, new rules are developed through the PJM stakeholder process associated with co-located load arrangements, such modifications should be taken into account in the relevant NERC and PJM standards.   PJM should also be required to advise stakeholders whether they reasonably expect to serve all load including co-located loads reliability particularly in periods of rapid load growth.

f. Other
i. Are any changes to PJM’s energy or ancillary services market rules necessary to address co-location arrangements?

See responses above.

ii. Please discuss whether back-up service can provide benefits to
customers or otherwise help minimize system costs, including with
specific examples or best practices, if possible;

AES Ohio generally agrees with the Indicated TOs response.

PDF page 14

iii. Parties may also choose to address how co-location arrangements may provide benefits, including potentially reducing required transmission upgrades to interconnect large loads, reducing congestion, or providing operational flexibility during system peaks or emergencies?

As noted above, the co-location of load may, in some cases, reduce the need for additional transmission system upgrades, with benefits flowing to existing transmission customers who would otherwise pay for such upgrades.

iv. Parties may also address whether, and if so, how, the Tariff should be modified to best accommodate or encourage co-location arrangements to be constructed in such a way as to minimize total system costs or otherwise provide certain benefits, including protections for existing customers and allocation of costs consistent with the cost-causation principle;

See responses above.

v. What Tariff provisions, if any, are necessary to ensure clarity regarding the aspects of service to co-located load and generation facilities that may be administered through the Tariff versus state jurisdictional retail tariffs?

No changes are necessary.

vi. We also encourage parties to address any national security implications associated with co-location arrangements, including with respect to the specific issues discussed in this show cause order, and what actions, if any, the Commission should take in response.

AES Ohio believes that certainty is critical in order to foster the national security goals of the United States and the Commission associated with the development of AI.  As noted above, once that certainty is established, AES Ohio is open to working through the

PDF page 15

stakeholder process to encourage and incentivize co-location arrangements that benefit the grid and provide more reliable service.

vii. Finally, for generation units paid for originally by consumers in base rates prior to restructuring, is it fair and/or just and reasonable if these units are taken out of the system’s supply stack and

devoted exclusively to serving co-location arrangements with one
or a few large customers?

In general, the continued obligation, if any, of generation to serve classes of end-use customers to pay for that generation is a matter of state jurisdiction and concern.

PDF page 16

CERTIFICATE OF SERVICE
I hereby certify that on March 24, 2025, I have served the forgoing document upon each person designated in the official list compiled by the Secretary in this proceeding.

/s/ William M Rappolt

William M. Rappolt