EL25-49-000 · 2025-03-24 · Exelon Corporation, American Electric Power Corporation and 17 others
Answer of the Indicated PJM Transmission Owners to the Order Instituting the Proceeding Under Section 206 of the Federal Power Act and Consolidating with…
PDF page 1
1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C., et al.
)
Docket No. EL25-49-000
Large Loads Co-Located at Generating
Facilities
)
Docket No. AD24-11-000
Constellation Energy Generation, LLC
v. PJM Interconnection, L.L.C.
)
Docket No. EL25-20-000
(consolidated)
ANSWER OF THE INDICATED PJM TRANSMISSION OWNERS
TO THE ORDER INSTITUTING THE PROCEEDING
UNDER SECTION 206 OF THE FEDERAL POWER ACT
AND CONSOLIDATING WITH OTHER PROCEEDINGS
Pursuant to Rules 206 and 213 of the Rules of Practice and Procedure of the Federal
Energy Regulatory Commission (“FERC” or “Commission”),1 the Indicated PJM Transmission Owners, comprised of the majority of the named respondents and inclusive of investor-owned utilities, municipalities, and cooperatives (hereinafter, “Indicated TOs”)2 submit this unified
1 18 C.F.R. §§ 385.206, 385.213.2 The Indicated PJM Transmission Owners include: American Electric Power Service Corporation, on behalf of Appalachian Power Company, Indiana Michigan Power Company, Kentucky Power Company, Kingsport Power Company, Ohio Power Company, Wheeling Power Company, AEP Appalachian Transmission Company, Inc., AEP Indiana Michigan Transmission Company, Inc., AEP Kentucky Transmission Company, Inc., AEP Ohio Transmission Company, Inc., and AEP West Virginia Transmission Company, Inc.; AMP Transmission, LLC; City of Cleveland, Department of Public Utilities, Division of Cleveland Public Power; City of Hamilton, OH; Dominion Energy Services, Inc. on behalf of Virginia Electric and Power Company d/b/a Dominion Energy Virginia; Duke Energy Corporation on behalf of its affiliates Duke Energy Ohio, Inc., Duke Energy Kentucky, Inc., and Duke Energy Business Services LLC; Duquesne Light Company; East Kentucky Power Cooperative; Exelon Corporation, on behalf of Atlantic City Electric Company, Baltimore Gas and Electric Company, Commonwealth Edison Company, Commonwealth Edison Company of Indiana, Inc., Delmarva Power & Light Company, PECO Energy Company, and Potomac Electric Power Company; FirstEnergy Service Company, as agent for its affiliates American Transmission Systems, Incorporated, Jersey Central Power & Light Company, Mid-Atlantic Interstate Transmission LLC, Keystone Appalachian Transmission Company, The Potomac Edison Company, Monongahela Power Company and Trans-Allegheny Interstate Line Company (collectively, the “FirstEnergy Transmission Companies”); Old Dominion Electric Cooperative; PPL Electric Utilities Corporation; Rockland Electric Company; (cont'd)
PDF page 2
2
Answer to the Commission’s Order Instituting Proceeding Under Section 206 of the Federal Power Act3 and Consolidating with Other Proceedings, issued on February 20, 2025.4 The Indicated TOs support co-location and appreciate the Commission’s leadership in addressing this issue. It is vital to our national economy and energy security to ensure that the rules of the road are clear with respect to the interconnection, service, and cost allocation for co-located arrangements.
Co-located load can and does fit within the current constructs for providing transmission service under the Commission’s pro forma open access transmission tariff (“OATT”) and PJM Interconnection, L.L.C.’s (“PJM”) Open Access Transmission Tariff (“PJM Tariff”). The existing PJM Tariff provisions are just and reasonable. The Indicated TOs appreciate that further clarification of how those existing provisions apply to co-located load arrangements could be beneficial for all parties involved in those arrangements and the industry as a whole. Thus, the Indicated TOs support the Commission ruling, as part of its review in this proceeding, that the existing PJM Tariff and its existing two forms of transmission service—Network Integration Transmission Service (“Network Service”) and Point-to-Point Transmission Service (“Point-to- Point Service”)5—encompass and apply to these arrangements.
Southern Maryland Electric Cooperative, Inc.; UGI Utilities Inc; and Wabash Valley Power Association, Inc.
3 16 U.S.C. § 824e. 4 PJM Interconnection, L.L.C., 190 FERC ¶ 61,195 (2025) (“Show Cause Order”). 5 All capitalized terms not otherwise defined herein shall have the meaning set forth in the PJM Tariff, Amended and Restated Operating Agreement of PJM Interconnection, L.L.C. and/or Reliability Assurance Agreement Among Load Serving Entities in the PJM Region (“RAA”).
PDF page 3
3
I. EXECUTIVE SUMMARY
The Indicated TOs agree with the recommendation of PJM that co-located end-use loads should be treated as load in front of the meter and designated as Network Load.6 Co-located load should be treated as load in front of the meter and designated as Network Load because it will ensure that such loads are appropriately studied, charged, and factored in operationally by PJM and transmission owners. Doing otherwise would undercut reliability and exacerbate affordability concerns. This approach offers the most reliability benefits and a cost allocation framework that addresses charges for use of, and reliance on, the transmission system. Otherwise, a customer that co-locates avoids “wires charges”—the fixed costs of the poles, wires, transformers, and substations that comprise the transmission and distribution network. These avoided costs are then subsidized by other customers, allowing co-location customers a free ride. Beneficiaries of the transmission system must pay their share to avoid inappropriately shifting costs to other customers.
PJM’s Independent Market Monitor (“IMM”) has correctly submitted that “it is simply not possible to be off the grid if you are interconnected to the grid.”7 The North American Electric Reliability Corporation (“NERC”) recognized in its 2024 Long-Term Reliability Assessment (“2024 LTRA”) that, in PJM, “[t]he trends in demand growth and resource additions create resource adequacy and system planning challenges for PJM as it carefully manages generator deactivation requests from the aging fossil and nuclear fleet.”8 PJM is experiencing
6 See PJM, PJM Guidance on Co-Located Load, at 1 (originally issued Mar. 22, 2024 and updated Apr. 17, 2024), https://www.pjm.com/-/media/DotCom/markets-ops/rpm/rpm-auction-info/pjm-guidance-on-co-located-load.ashx (“PJM continues to recommend that all co-located load be served from the PJM Transmission System as PJM Network Load with applicable firm transmission service (e.g., Regional Network Integration Transmission Service (NITS) under PJM Tariff, Part III).”) (“PJM Guidance on Co-Located Load”).7 IMM Answer at 4, Docket No. EL25-20 (Dec. 20, 2024).8 NERC, 2024 LTRA, at 16 (Dec. 2024), (cont'd)
PDF page 4
4
increased load growth.9 NERC has also explained that there are reliability challenges that attend this demand growth:
PJM’s 2023 Load Forecast Report addressed the impact of industry
changes that are reshaping system hourly loads. As a result, the
level and timing of coincident peak and non-coincident peak
demands across PJM have begun to shift. Solar-power penetration,
expected impacts of EVs, state electrification programs, home
battery storage, and a significant increase in data center loads are
markedly increasing the complexity of PJM’s load forecasting
process. Driven by discrete and localized load growth, like Data
Center Alley in Loudoun County, Virginia, in 2022, PJM and
stakeholders conducted a review of data center load growth and
identified growth rates of over 300% in some instances. As a result,
the 2023 PJM Load Forecast Report incorporates adjustments to
specific zones for data center load growth.10
The foregoing underscores the importance of ensuring that when there are co-location arrangements that must rely on the transmission system, and receive system benefits, for any period of time, the loads should be located and treated just like load in front of the meter and designated as Network Load so that their demand is transparent and known, so that they can be charged the costs commensurate with the benefits they are receiving, and to ensure PJM and transmission owners are adequately studying the load to ensure effective system planning. The concept of placing end-use load near generation, and vice versa, is not new. As industry analysts have recognized, new large loads located at generating facilities are seeking ways to interconnect to the PJM system faster than current process timelines for addressing the generation and transmission needs of the system. The Indicated TOs recognize that FERC, PJM,
https://www.nerc.com/pa/RAPA/ra/Reliability%20Assessments%20DL/NERC_Long%20Term%20Reliability%20 Assessment_2024.pdf.
9 See id. at 92 (“PJM is experiencing large growth in data centers that are in turn driving higher demand forecasts. Loudoun County, Virginia, in the PJM assessment area, is home to ‘Data Center Alley,’ the largest concentration of data centers in the world. Electrification in transportation, heating, and industrial sectors is also spurring demand growth.”).10 Id. at 93.
PDF page 5
5
and stakeholders are working diligently and are in the process of implementing queue reforms and proposals to address bringing needed capacity online to serve the increased demand. Co-location can offer a valuable option for hyperscalers to address transmission capacity constraints and to spur economic growth. The contractual arrangement between a generator and co-located load also has the potential to provide generation assets an alternative to retirement. However, co-location must be done in a responsible and fair manner to ensure configurations do not threaten the reliability and security of the grid,11 and co-location should not result in other cost-shifting that requires customers to pay costs caused by or for the benefit of co-location customers. If co-located load is interconnected to the transmission system, it is unequivocally using and benefitting from the transmission system and therefore must pay for its share of wholesale transmission service and other essential grid services.
This is the case regardless of whether the load contracts for power directly from a generator connected to the PJM transmission system. The transmission system must be planned and built to support every MW of load on the system, including co-located load. Co-located load depends on and uses the grid. As stated above, if the framework for cost allocation for the transmission system does not reflect co-located load’s use of the system, then such co-located load will get a free ride, and costs will be shifted to and borne by other customers. Consequently, the Commission should confirm that the existing PJM Tariff provisions regarding Network Service and Point-to-Point Service are sufficiently inclusive to cover the treatment of co-located load.
11 Should behind-the-meter co-location configurations be permitted even when such configurations depend on the transmission system, there will be reliability and resource adequacy risks that will follow. As the Commission recognized in its Show Cause Order, “[t]he risk that co-located loads will not be reflected in resource adequacy planning mechanisms with sufficient forward notice is particularly concerning given how long it takes to add new generation capacity or upgrade transmission facilities.” Show Cause Order at P 85.
PDF page 6
6
That said, as the Commission has acknowledged, co-located load arrangements are becoming increasingly common in PJM,12 in part due to variations to the Commission’s pro forma OATT that are specific to PJM. Thus, the time is ripe to underscore and clarify the applicability of the existing types of PJM transmission service to co-location arrangements to provide certainty to participants in those arrangements and other stakeholders, ensure that the Commission’s principles for open access and non-discriminatory transmission service persist, and that beneficiaries pay for the services they receive.
In the Show Cause Order, the Commission also instructed PJM and the Indicated TOs to file responses to a list of questions, together with supporting evidence and analysis.13 Thus, along with the fundamental principles and arguments raised herein, the Indicated TOs submit answers to the questions in Attachment A of this filing.14
II. BACKGROUND
A. Procedural Overview
The Show Cause Order is the culmination of several proceedings addressing the issue of co-location, both in specific circumstances and on an industry-wide basis. The Commission consolidated this new proceeding in Docket No. EL25-49-000 with Docket Nos. AD24-11-000 (the co-location technical conference) and EL25-20-000 (the “Complaint”).15 While the co- location phenomenon is not limited to a single region, the Show Cause Order is specific and limited to PJM. In its Show Cause Order, the Commission directed the respondents to:
12 Show Cause Order at P 3.13 See id. at P 88.14 Because the dockets have been consolidated, the answers submitted by Exelon, PPL Electric Utilities, AEP, Dominion Energy Services, and others, on December 12, 2024, including the testimony appended thereto, and January 7, 2025, in response to the Technical Conference and Complaint, are already part of the record here.15 Show Cause Order at P 65.
PDF page 7
7
(1) show cause as to why the [Open Access Transmission
Tariff], the Amended and Restated Operating Agreement of PJM,
and Reliability Assurance Agreement Among Load Serving Entities
in the PJM Region [(collectively, the “PJM Tariff”)] remains just
and reasonable and not unduly discriminatory or preferential
without provisions addressing with sufficient clarity or consistency
the rates, terms, and conditions of service that apply to co-location
arrangements; or
(2) explain what changes to the Tariff would remedy the
identified concerns if the Commission were to determine that the
Tariff has in fact become unjust and unreasonable or unduly
discriminatory or preferential and, therefore, proceeds to establish a
replacement Tariff.16
B. Co-location of Load
Co-located load is network or point-to-point load that has contractual arrangements to be served by an adjacent generation resource that is physically interconnected to and synchronized with the transmission and/or distribution grid. Indeed, it must be interconnected to the grid.17 Co-located load uses and depends on the grid, causing changing flows on the grid from second to second. There is an alternative arrangement where a load and accompanying generation never use the transmission or distribution system—they are islanded—but neither the Show Cause Order nor Commission jurisdiction extend to islanded non-interconnected arrangements. Load cannot be both connected to the transmission and/or distribution grid and “fully isolated,” in the manner certain generation and large load interests have asserted.1816 Id. at P 2.17 FERC adopts the definition of a co-located load arrangement used in PJM’s Guidance Document for purposes of the Show Cause Order: “A co-located load configuration refers to end-use customer load that is physically connected to the facilities of an existing or planned Customer Facility on the Interconnection Customer’s side of the Point of Interconnection (‘POI’) to the PJM Transmission System (co-located Customer Facility).” Show Cause Order at P 3 n.4. This definition obscures the engineering and economic truth that the load relies upon the functioning grid and grid services whichever side of the meter it is located on. As explained below, the Indicated PJM TOs support that the preferred treatment of the load is in front of the meter to ensure reliability, transparency, and appropriate cost allocation.18 See infra note 11. See, also, e.g., Atlantic City Electric Co., et al., Docket Nos. ER24-2888-000, et al., Motion to Intervene and Protest of MachH2 LLC at 3 (Oct. 2, 2024) (“Requiring hydrogen projects that rely on PJM- (cont'd)
PDF page 8
8
Throughout the proceedings leading up to this Show Cause Order, several parties argued
that co-located load could be “fully isolated” by connecting with their own generation and
therefore not relying on the transmission grid.19 Connecting the load near generation with which it has a contractual arrangement for the supply of electricity, however, does not isolate that load from the grid. It continues to use services provided by the grid and the arrangement continues to rely on the grid connection for the generator to operate. As long as the load remains connected to the grid, including through facilities also connecting a generator to the grid, the load would still be able to be served from the transmission system, and therefore, the transmission system must be planned and built to account for the load. The fact that the load is not constant does not reduce the capital investment or operation and maintenance costs that are incurred to ensure that the system is available to the customer. The same applies to generators connected to the
distribution system.
sanctioned co-location arrangements to pay the transmission owner for a transmission system they are not using will add costs to already tight clean hydrogen economics, making it less likely these hubs will blossom, contrary to the goals of the DOE’s clean hydrogen programs.”); Docket Nos. ER24-2888-000, et al., Protest of the PJM Industrial Custom Coalition at 9–11 (Oct. 2, 2024) (arguing that Exelon’s gross-load-basis proposal would not charge network customers based on their “actual use” of the transmission system); Pre-Technical Conference Comments of the Clean Energy Buyers Association at 21 n.50, Docket No. AD24-11-000 (Oct. 25, 2024) (“As Constellation explains in a related docket, load can be fully isolated from the grid such that it ‘does not rely on the grid’s ancillary services . . . .’” (quoting Docket No. ER24-2172, Answer of Constellation Energy Generation at 5–6 (Oct. 9, 2024))); Soluna Holdings, Inc., Post-Conference Comments at 2, Docket No. AD24-11-000 (Dec. 1, 2024) (“We have also observed instances where generators have successfully completed studies to ensure fully isolated co- located loads cannot draw power from the grid.”).
19 See, e.g., Constellation Complaint at 4, Docket No. EL25-20 (Nov. 22, 2024) (“One longstanding option that has been available to any load since the beginning of open access has been to connect directly to a generator either fully independent of the network grid or with a reduced reliance on the grid.”); Constellation Answer at 5, Docket No. EL25-20 (Dec. 24, 2024) (“Since the beginning of open access, load has been able to connect directly to a generator either fully independent of the network grid or with a reduced reliance on the grid.”); id. at 20 (“The Commission should also reject Exelon’s factually incorrect claims, repeated from other dockets, that Fully Isolated Co-Located Load is impossible and always relies on the grid . . . .” (footnotes omitted)); id. (suggesting it is a “faulty premise that the Fully Isolated Co-Located Load is taking transmission service”); PJM Interconnection, L.L.C., Docket No. ER24-2172-001, Answer of Susquehanna Nuclear, LLC at 3 (Oct. 22, 2024) (“[T]he record here demonstrates that load can in fact be fully-isolated behind-the-meter and not considered Network Load.”).
PDF page 9
9
Indeed, any characterization of co-located load as “fully isolated” is false and misleading unless the load is not connected to either the transmission or distribution system. If loads were “fully isolated” from the grid, then both the generation and the load would be islanded from the grid, and the PJM Tariff would not apply to them at all. No interconnection under the PJM Tariff process would be needed. The Indicated TOs consider all the arrangements being contemplated or requested as being interconnected with and synchronized with the transmission and/or distribution grid and thus not “fully isolated.”
Although the existing PJM Tariff already accommodates co-located load, the
Commission may have an interest in providing further clarity. If so, a definition of “co-located load” could be added to the PJM Tariff that clarifies the expectations and obligations associated with such load. Specifically, the Indicated TOs suggest that the following definition could be added to the PJM Tariff:
“Co-located Load” shall mean load that has contractual
arrangements to be served by an adjacent generation resource that is
physically interconnected to and synchronized with the transmission
or distribution grid. Co-located Load is either Network Load or load
being served using Point-to-Point Transmission Service, as
applicable. Such adjacent generation resource shall not meet the
definition of Behind The Meter Generation. Arrangements for Co-
located Load must have separate metering for load consumption and
generator output as required under PJM Tariff, Part III.
This proposed definition is consistent with the provisions of the existing PJM Tariff but would provide additional clarity to those directly impacted by co-located load arrangements. At the same time, this proposed language would ensure that PJM and its transmission owners have adequate visibility of the loads affecting the transmission system for planning and reliability purposes.
PDF page 10
10
III. DISCUSSION
A. Classification of Co-located Load as Network Load Is Just and Reasonable.
The PJM Tariff, in its current form, allows for co-location of load and generation on
terms that are just, reasonable, and not unduly discriminatory or preferential. The PJM Tariff allows end-use load and generation to co-locate expeditiously and on terms that are also fair to all other users of the grid and commensurate with cost causation principles. To allow this, the PJM Tariff, consistent with the pro forma OATT, provides for two types of transmission service to be used in accommodating co-location arrangements: Network Service and Point-to-Point Service. Both long-standing types of transmission service recognize that those that benefit from the transmission system must contribute to its costs.
The rate design in PJM, incorporated into the PJM Tariff, permits owners to recover, on a postage stamp basis without consideration of the distance between load and generation, the embedded costs of their respective portions of the transmission grid from network customers.20 As the Commission has explained, “PJM recovers the full revenue requirements of existing facilities (embedded costs) through its firm transmission rates.”21
This concept of embedded costs of the transmission grid and associated cost
responsibility of load based on fairness principles predates Order No. 888,22 FERC’s landmark
20 See, e.g., Pennsylvania-New Jersey-Maryland Interconnection, et al., 81 FERC ¶ 61,257 (1997) (adopting PJM pricing proposal to allow recovery of embedded transmission revenue requirement from network customers), corrected by 82 FERC ¶ 61,103 (1998), and clarified in part by 92 FERC ¶ 61,282 (2000), and review granted in part, vacated in part by 295 F.3d 1 (D.C. Cir. 2002); PJM Tariff, Section 34.1 (providing for payment by network customers of load ratio share of embedded cost of their zone); PJM Tariff, Attachments H-1, H-1A, H-2, H-2A, H-3, H-3D, H-7, H-7A, H-9, H-9A, H-13, and H-13A (establishing network revenue requirements for each of the Exelon Utilities based on the embedded costs of their respective transmission systems).21 PJM Interconnection L.L.C., 139 FERC ¶ 61,243, at P 78 n.105 (2012). 22 See also Promoting Wholesale Competition Through Open Access Non-Discriminatory Transmission Servs. by Pub. Utils.; Recovery of Stranded Costs by Pub. Utils. and Transmitting Utils., Order No. 888, FERC Stats. & Regs. ¶ 31,036, at 31,707 (1996) (cross-referenced at 75 FERC ¶ 61,080), order on reh’g, Order No. 888-A, FERC Stats. & Regs. ¶ 31,048 (cross-referenced at 78 FERC ¶ 61,220), order on reh’g, Order No. 888-B, 81 FERC ¶ 61,248 (cont'd)
PDF page 11
11
open access transmission order, which was “issued in 1996 with the stated purpose of
‘Promoting Wholesale Competition Through Open Access Non–Discriminatory Transmission
Services by Public Utilities.’”23 In a 1994 order directing Florida Power & Light Company to provide network transmission service to Florida Municipal Power Authority, the Commission explained that Florida Municipal Power Authority could not simply reduce its network service transmission cost obligations based on hourly economic dispatch decisions. The Commission stated:
Since Florida Power must plan its transmission system to meet load,
not based on FMPA’s actual hourly or yearly demands, its
compensation for the network transmission service should not be
driven by FMPA’s hourly economic dispatch decisions. Since
FMPA wants to be able to use the transmission system exactly as
freely as does Florida Power, it must pay a rate that reflects that
equality. It must share the costs of the system on the same basis as
does Florida Power—on the basis of its load.24
The Commission solidified this concept in its pro forma definition of “Network Load,” which does not allow a Network Customer to designate only part of the load at a discrete Point of Delivery as Network Load unless arrangements for Point-to-Point Service are made.25 The Commission summed up the transmission service choices in Order No. 888-A: “The bottom line is that all potential transmission customers, including those with generation behind the meter,
(1997), order on reh’g, Order No. 888-C, 82 FERC ¶ 61,046 (1998), aff’d in relevant part sub nom. Transmission Access Pol’y Study Grp. v. FERC, 225 F.3d 667 (D.C. Cir. 2000), aff’d sub nom. New York v. FERC, 535 U.S. 1 (2002).
23 New York v. FERC, 535 U.S. 1, 5 (2002).
24 FMPA v. FPL, 67 FERC ¶ 61,167 at 61,482 (1994).25 See Order No. 888, FERC Stats. & Regs. ¶ 31,036 at Appendix D (Apr. 24, 1996) (defining “Network Load” as: “The load that a Network Customer designates for Network Integration Transmission Service under Part III of the Tariff. The Network Customer's Network Load shall include all load served by the output of any Network Resources designated by the Network Customer. A Network Customer may elect to designate less than its total load as Network Load but may not designate only part of the load at a discrete Point of Delivery. Where an Eligible Customer has elected not to designate a particular load at discrete points of delivery as Network Load, the Eligible Customer is responsible for making separate arrangements under Part II of the Tariff for any Point-To-Point Transmission Service that may be necessary for such non-designated load.”).
PDF page 12
12
must choose between network integration transmission service or point-to-point transmission service.”26 It is with these physical realities and legal principles in mind that the Commission must assess the PJM Tariff.
The existing PJM Tariff is just and reasonable. With that said, the Indicated TOs remain open to and anticipate the potential for further discussion regarding possible changes to tariffs to expressly specify that co-located load must be served by the existing forms of transmission service—Network Service or Point-to-Point Service—while recognizing the evolving co-location configuration landscape.
B. Co-Located Load Benefits From Essential Services Provided Using the Grid.
In addition to FERC-jurisdictional transmission charges, PJM also assesses service charges to users of the grid for essential reliability services, such as ancillary services. As PJM acknowledged, there is no question that “[a]lthough co-located load is located behind the [point of interconnection], it still is electrically connected and synchronized to the PJM Transmission System when consuming power and therefore benefits from the use of the Transmission System and Ancillary Services.”27 The same is true even when the co-located load is only connected to the distribution system, because ancillary services are required by both the transmission and distribution system operators to maintain the integrity and stability of the transmission and distribution system, as well as the power quality.28 In other words, co-located load cannot receive the benefits of such essential reliability services without the physical and synchronous interconnection to the transmission (and/or distribution) system. These services are fundamental
26 Order No. 888-A, FERC Stats. & Regs. ¶ 31,048, at 30,260 (Mar. 4, 1997).27 PJM Guidance on Co-Located Load at 1.28 Union of the Electricity Industry, Ancillary Services Unbundling Electricity Products – an Emerging Market, at 9 (Feb. 2004), https://pierrepinson.com/31761/Literature/Eurelectric2004-ancillaryservices.pdf.
PDF page 13
13
to maintaining reliable operation of the grid. Assignment of ancillary services to co-located load should be treated like any other load. Because the co-located load is interconnected with the grid and relies on the grid, PJM’s Tariff remains just and reasonable. The PJM Tariff currently requires no amendment or alteration for this class of customers, and there is no basis for the Commission to act under FPA section 206. However, as previously noted, the Indicated TOs remain open to and anticipate the potential for further discussion regarding possible changes to tariffs.
It is undeniable that the synchronized configurations associated with co-located load benefit from essential reliability services provided by the regional PJM grid.29 By way of example: load served by a nuclear unit necessarily depends on a grid interconnection because the nuclear unit is not permitted by its license to operate without a robust grid interconnection.30 Further, load that is co-located with a nuclear unit depends on services such as load following, voltage support, black start, and other ancillary services that will be and can only be delivered over the grid.31 Nuclear units cannot move their output up and down from moment to moment to match variations in the load, and because the nuclear units cannot provide these services, they must instead be provided through connection to the grid.32 That is, remote generators increase and decrease their output in synchrony with the co-located load, and power flows on the grid likewise move in synchrony with the co-located demand. Those services are used every hour,
29 See, e.g., Declaration of David Weaver, PE at P 17, Attachment 1 to Exelon Comments, Docket No. EL25-20 (Dec. 12, 2024) (“Weaver Decl.”) (explaining that because nuclear units are unable to provide black start services, co-located load must rely on those services from other resources in PJM that are connected to the grid in order to come back online); id. at P 19 (explaining that the co-located load will most of the time take service that is dependent “on a strong interconnection with the grid that is supported by reactive power, operating reserves, and black start”).30 See id. at PP 11–12.31 See id. at PP 14–19.32 See id. at PP 14, 18.
PDF page 14
14
not just when the generator fails or the load exceeds the output of the connected unit. Moreover, in a recently submitted co-location arrangement and in the arrangements proposed and discussed in the Complaint, the co-located load depended upon another nuclear unit at the same facility for its backup supply of real power—which is to say, a PJM capacity resource that is interconnected with, serves, and relies entirely upon the grid.33 The proposed backup arrangement, including any “replacement capacity” mechanism, depends upon the delivery of energy from other locations on the network through PJM’s transmission system.34
Because these arrangements irrefutably rely on the transmission grid, there can be no need for some new kind of service for these arrangements. The PJM Tariff already has mechanisms that lay out how transmission users connect loads—those mechanisms work. Any proposed tariff changes to be considered by the Indicated TOs as part of a separate process would be for the sake of clarification that the existing service categories and requirements apply to co-located load; the fundamental principles established by the PJM Tariff cover co-location arrangements.
C. All Load, Including Co-located Load, Is Used to Plan the Transmission
System.
As explained above, the existing PJM Tariff can accommodate co-location arrangements. Any end-use load, co-located or otherwise, can request retail service from the retail utility, connect its facility, and receive service under the applicable retail rates.35 All of PJM’s load growth has happened through those established tariff mechanisms, and all that load growth was
33 See Constellation Complaint and Application, Docket No. ER24-2172.34 See Weaver Decl. at PP 21–24.35 Depending upon the jurisdiction, states often limit who can serve retail.
PDF page 15
15
accommodated through PJM’s requirement that it serve its customers through either Network Service or Point-to-Point Service.36
The PJM Reliability Assurance Agreement (“RAA”) sets forth the basic obligations of Load Serving Entities in PJM and defines such entities to include any entity lawfully serving end-use load in the region. Specifically,
“Load Serving Entity” or “LSE” shall mean any entity (or the duly
designated agent of such an entity), including a load aggregator or
power marketer, (i) serving end-users within the PJM Region, and
(ii) that has been granted the authority or has an obligation pursuant to state or local law, regulation or franchise to sell electric energy to end-users located within the PJM Region.37
LSEs are required to become parties to the RAA, as that agreement provides that “every entity which is or will become a Load Serving Entity within the PJM Region is to become and remain a Party to this Agreement.”38 The RAA also provides that:
Each Party shall cooperate with the other Parties in the coordinated
planning and operation of their owned or contracted for Capacity
Resources to obtain a degree of reliability consistent with the
Reliability Principles and Standards. In furtherance of such
cooperation each Party shall:
…
(c) provide or arrange for Network Transmission Service or Firm
Point-to-Point Transmission Service for service to the projected load of the Party . . . .39
Taken together, these provisions mean that any entity that is serving an end-use load, such as a generator supplying co-located load (or if the generator is selling to a middleman that is serving
36 See PJM Tariff at Parts II and III.37 RAA, Definition of Load Serving Entity.38 RAA, Art. 2.39 RAA, Art. 9.1.
PDF page 16
16
the load, then the middleman), becomes an LSE, and is responsible for ensuring that its load is taking Network Service or Point-to-Point Service.
The PJM Tariff spells out the process for accommodating new load for Network or Point- to-Point Customers, and for adding new loads for existing Network Customers. Section 31.1 of the PJM Tariff requires that Network Loads are to be specified in the Service Agreement. Sections 31.2 and 31.3 provide the procedures for identifying new Network Loads that will be served by the Network Customer.40 If, and to the extent that, a study is required of the request, section 32 of the PJM Tariff details that process. And, because loads may change after commencement of service, section 31.5 provides the process by which to report changing loads.41 Those provisions apply to, and work for, co-located load just as for any other end-use load.
If co-located load is interconnected to the transmission system, it is using the
transmission system and must pay for its share of wholesale transmission service. For wholesale transmission service in PJM, the allocation of these wholesale charges should continue to be based on the FERC-approved cost allocation methodologies employed today. Specifically, if a customer has the option, capability, or is requesting such capability to serve their full load from the PJM Transmission System, then the full load amount should be included in the LSE’s total load used to determine its share of total system costs, even if they choose not to use that full suite of services at times. No free ridership should be enabled for grid-connected customers. They are
40 A “Network Service User” “mean[s] an entity using Network Transmission Service.” PJM Tariff, Definitions. “Network Transmission Service” “mean[s] transmission service provided pursuant to the rates, terms and conditions set forth in Tariff, Part III, or transmission service comparable to such service that is provided to a Load Serving Entity that is also a Transmission Owner.” PJM Tariff, Definitions.41 While Point-to-Point Service would ordinarily not make sense for serving load within PJM, the provisions for requesting such service are likewise clear and spelled out in the PJM Tariff. For example, the Application process is spelled out in Section 17 of the PJM Tariff, and the study procedure is spelled out in Section 19 of the PJM Tariff. Of course, Point-to-Point Service does not accommodate load growth—it allows only a specified reservation.
PDF page 17
17
paying to use the transmission system and for the transmission system to be available to them when needed. The fact that their load may not be constant does not reduce the possible need for investment in the transmission system or operation and maintenance costs that transmission owners incur to ensure that the system is available to them and that they receive reliable service. PJM should not treat co-located load differently simply because of its contract drafting or placement of the meter. Because all loads physically connected to and synchronized with the transmission system benefit from the transmission system, any attempt to isolate or piecemeal wholesale transmission services to quantify costs would be discriminatory because it would disregard the interconnected nature of the transmission system.
D. Creating A New, Non-Paying Category of Service Under the PJM Tariff
Would Be Preferential and Unduly Discriminatory and Allow Co-Located
Load to Avoid Paying for Transmission Service.
The current PJM Tariff is just and reasonable with respect to co-location; as such, no changes to the existing tariff are necessary because it accommodates any kind of co-location arrangement. Allowing a work-around for co-located load, which effectively gives that class of grid users drastically reduced rates (or no charge at all) for use of the grid, is impermissible.42 No reasoned basis has thus far been articulated for why the existing rates are unjust or unreasonable.
Further, as previously explained, the PJM Tariff comports with the holding of Order No. 888 that established and defined two basic types of transmission service provided by transmission owner/operators: Network Service and Point-to-Point Service. This holding remains good law, and the Commission has in recent years continued to reject requests that some
42 16 U.S.C. § 824d(b) (“No public utility shall, with respect to any transmission or sale subject to the jurisdiction of the Commission, (1) make or grant any undue preference or advantage to any person or subject any person to any undue prejudice or disadvantage, or (2) maintain any unreasonable difference in rates, charges, service, facilities, or in any other respect, either as between localities or as between classes of service.”).
PDF page 18
18
loads should somehow be treated as special third categories, not required to take transmission service,43 and should continue to do so here.
A new, special non-paying treatment for co-located load would undermine the very premise of open access, which is the fundamental principle by which the Commission regulates the transmission system. That is, under Order No. 888 and open access transmission tariffs to date, all users of the grid pay costs commensurate with benefits, in the same way as the transmission owners themselves must pay when transmitting power to loads that they serve. There is no justification for creating a new class of cost-free load that would not share in the costs of the grid. Far from being unjust and unreasonable, the existing PJM Tariff, which requires that all load pay for using the grid, complies with, and enforces the mandates of Order No. 888 and the Federal Power Act.
A fundamental ratemaking principle establishes that “the costs assessed against a party must bear some resemblance ‘to the burdens imposed or benefits drawn by that party.’”44 The PJM Tariff complies with these cost allocation requirements and appropriately accounts for the cost of the benefits drawn by such load from use of the grid and grid services. But allowing co- located loads to evade ordinary and established tariff charges for grid usage by carving out this load from Network Service or Point-to-Point Service would violate these principles. As explained in answers to the Complaint,45 carving a 480 MW co-located load in the Commonwealth Edison territory (which hosts multiple nuclear units) out from Network Service
43 See, e.g., Nat’l R.R. Passenger Corp. v. PPL Elec. Utils. Corp. et al., 171 FERC ¶ 61,237, order on reh’g, 173 FERC ¶ 61,043 (2020). 44 Pub. Serv. Elec. & Gas Co. v. FERC, 989 F.3d 10, 13 (D.C. Cir. 2021) (“PSE&G”) (quoting Midwest ISO Transmission Owners v. FERC, 373 F.3d 1361, 1368–69 (D.C. Cir. 2004)).45 Exelon Comments, Docket No. EL25-20, at 25–26 (Dec. 12, 2024). The underlying calculations are explained in the Reed/Powers Declaration, which is Attachment 2 to those Exelon Comments, and detailed at Attachment A to the Reed Powers Declaration.
PDF page 19
19
would avoid approximately $121 million in annual charges, leading to a 1.53% increase in representative residential customer bills, or about $25.57 annually, compared to a similar load customer who paid its share of the costs of the grid.
• A 1 GW co-located load in the Commonwealth Edison territory would avoid approximately $253 million in annual charges, resulting in a 3.19% increase in representative residential customer bills or about $45.16 annually.
• Similarly, a 480 MW co-located load in the PECO territory (which is the home of the Limerick nuclear facility) would avoid approximately $43 million in annual charges, leading to a 0.96% increase in representative residential customer bills, or about $23.16 annually.
• A 1 GW co-located load in the PECO territory would avoid approximately $89 million in annual charges, resulting in a 1.99% increase in representative residential customer bills or about $48.26 annually.
• Finally, a 480 MW co-located load in the Southern Maryland Electric Cooperative (“SMECO”) territory (where the Calvert Cliffs nuclear facility is located) would avoid just over $53 million in annual charges, leading to an 11.10% increase in representative residential customer bills, over $208 annually. A 1 GW co-located load in the SMECO territory would avoid approximately $112 million in annual charges, resulting in a 23.11% increase in representative residential customer bills or about $433.72 annually.
These are costs that the co-located load would avoid paying if the PJM Tariff is altered to allow such arrangements to evade grid charges. The inevitable result would be that the co- located load’s share of the grid expenses would be unlawfully shouldered by all the other customers who would be required to make up the difference.46
The PJM Tariff applies, and will continue to apply, to all who seek transmission service in PJM, and it ensures that all customers pay their fair share of the transmission network from which they benefit. Co-location configurations can be accommodated under the current PJM
46 PJM compensates Transmission Owners for use of the grid using the load-ratio share method—that is, each Network Customer pays its load ratio share, and the sum of the payments reimburses the Transmission Owner for the full cost of the grid. If Co-Located Load is not designated as the load of a Network Customer, the load ratio share for all other customers will be higher. There is an automatic cost shift to other customers.
PDF page 20
20
Tariff. Entities are entitled to request retail service from a local distribution company or sign up as a Network Customer in PJM (or have the LDC act as Network Customer), and their load will be served like every other user of the system, and they will pay the same costs that every other user pays.
IV. CONCLUSION
For the reasons stated above, the Indicated TOs respectfully request that the Commission reaffirm the justness and reasonableness of the current, non-discriminatory—and functional— PJM Tariff, because PJM’s Tariff already accommodates co-location arrangements through the two types of service specified in the PJM Tariff: Network Service and Point-to-Point Service.
Respectfully submitted,
/s/ William Sauer
William Sauer
Vice President, Federal Regulatory Affairs
Exelon Corporation
701 Ninth St. N.W.
Washington, DC 20001
Telephone: 202-868-7499
Email: william.sauer@exeloncorp.com
/s/ Max Minzner
Max Minzner
Vice President and Deputy General Counsel
Exelon Corporation
701 Ninth St. N.W.
Washington, DC 20001
Telephone: 202-934-4740
Email: max.minzner@exeloncorp.com
On behalf of Exelon Corporation
/s/ Stacey Burbure
Stacey Burbure
Vice President FERC, RTO Strategy & Policy
American Electric Power Service Corporation
1 Riverside Plaza
Columbus, OH 43215
Telephone: 614-716-2502
Email: slburbure@aep.com
/s/ Lisa G. McAlister
Lisa G. McAlister
AMP Transmission, LLC
1111 Schrock Road, Suite 100
Columbus, Ohio 43229
Telephone: 614-540-6400
Email: lmcalister@amppartners.org
On behalf of American Electric Power
Service Corporation
On behalf of AMP Transmission, LLC
PDF page 21
21
/s/ Martin J. Keane
Martin J. Keane
Director of Public Utilities
Cleveland Public Power
1300 Lakeside Ave.
Cleveland, OH 44114
Telephone: 216-664-2444 ext. 75604
Email: martin_keane@clevelandwater.com
/s/Debra D. Roby
Debra D. Roby
Washington Energy Law LLP
900 17th Street N.W., Suite 500-A
Washington, D.C. 20006
Telephone: 703-785-9270
Email: droby@washingtonenergylaw.com
On behalf of City of Cleveland, Department of Public Utilities, Division of Cleveland Public Power
On behalf of the City of Hamilton, OH
/s/ Wesley Walker
Wesley Walker
Senior Assistant General Counsel
Dominion Energy Services, Inc.
120 Tredegar Street
Richmond, VA 23219
Telephone: 804-819-2345
Email: wesley.walker@dominionenergy.com
/s/ Molly Suda
Molly Suda
Associate General Counsel
Annelise Rickert
Federal Government Affairs Director
Duke Energy Corporation
1301 Pennsylvania Ave NW, Suite 200
Washington, DC 20004
Telephone: 202-824-8011
Email: molly.suda@duke-energy.com
Annelise.rickert@duke-energy.com
On behalf of Dominion Energy
On behalf of Duke Energy
/s/ Michael Brechlin
Michael Brechlin
PA Bar # 335424
Duquesne Light Company
411 7th Ave
Pittsburgh, PA 15219
Telephone: 412-393-6431
Email: mbrechlin@duqlight.com
/s/ Amanda P. Parker
Amanda P. Parker
Attorney
FirstEnergy Service Company
76 South Main Street
Akron, OH 44308
Telephone: (330) 384-4592
Email: aparker@firstenergycorp.com
On behalf of Duquesne Light Company
On behalf of The FirstEnergy Transmission Companies
PDF page 22
22
/s/ Denise R. Foster Cronin
Denise R. Foster Cronin
Vice President, Federal and RTO Regulatory Affairs
East Kentucky Power Cooperative, Inc. 4775 Lexington Road, P.O. Box 707
Winchester, KY 40392-0707
Telephone: 859-745-9615
Email: denise.cronin@ekpc.coop
/s/ Daniel E. Frank
Daniel E. Frank
Kelly Cuthbertson
Eversheds Sutherland (US) LLP
700 Sixth St., N.W., Suite 700
Washington, DC 20001-3980
Telephone: 202-383-0100
Email:
danielfrank@eversheds-sutherland.com kellycuthbertson@eversheds-sutherland.com
On Behalf of East Kentucky Power
Cooperative, Inc.
/s/ Adrienne E. Clair
Adrienne E. Clair
Thompson Coburn LLP
1909 K Street, N.W., Suite 600
Washington, D.C. 20006-1167
Telephone: 202-585-6900
Email: aclair@thompsoncoburn.com
/s/ Steve Nadel
Steven M. Nadel
Senior Counsel
PPL Services Corp.
645 Hamilton Street, Suite 601
Allentown, PA 18101
Telephone: 610-774-4775
Email: SMNadel@pplweb.com
On behalf of Old Dominion Electric Cooperative
On behalf of PPL Electric Utilities Corp.
/s/David Burns
David Burns
Senior Manager,
FERC Policy & Regulatory Affairs
Consolidated Edison Company of New York, Inc.
4 Irving Place
New York, NY 10003
Telephone: 571-678-9152
Email: burnsd@coned.com
/s/Joshua Kirstein
Joshua A. Kirstein
Senior Attorney
Law Department
Consolidated Edison Company of New York, Inc.
4 Irving Place, 18th Floor
New York, NY 10003
Telephone: 929-656-5971
Email: kirsteinj@coned.com
On behalf of Rockland Electric Company
PDF page 23
23
/s/ Damon L. Krieger
Damon L. Krieger
Group Vice President, Legal, Strategy, and Sustainability, and Deputy General Counsel Southern Maryland Electric Cooperative, Inc. 15035 Burnt Store Road
P.O. Box 1937
Hughesville, Maryland 20637-1937
Telephone: 301-274-4323
Email: Damon.Krieger@SMECO.coop
/s/ Jeremy L. Fetty
Jeremy L. Fetty
Parr Richey
251 N. Illinois, Suite 1800
Indianapolis, Indiana 46204
Telephone: 317-269-2500
Email: j_fetty@wvpa.com
On behalf of Southern Maryland Electric Cooperative
On behalf of Wabash Valley Power
Association, Inc.
/s/ Lindsay Berkstresser
Lindsay Berkstresser
Counsel – Energy & Regulatory
UGI Corporation
500 North Gulph Road
King of Prussia, PA 19406
Telephone: 717-504-9925
Email: berkstresserl@ugicorp.com
/s/ Richard P. Bonnifield
Richard P. Bonnifield
Husch Blackwell
1801 Pennsylvania Avenue, NW,
Suite 1000
Washington, DC 20006-3606
Telephone: 202-243-8844
Email:
richard.bonnifield@huschblackwell.com
On behalf of UGI Utilities Inc.
March 24, 2025
PDF page 24
ATTACHMENT A
PDF page 25
1
a. General
i. Do you agree with the jurisdictional principles outlined in section VI.A
and should the Commission reach any other conclusions regarding
jurisdiction in a final order it may issue in this proceeding? Why or why
not?
The Indicated TOs generally agree with the jurisdictional principles as outlined by the Commission in section VI.A of the Show Cause Order. The Federal Power Act (“FPA”) provides the Commission with jurisdiction over the wholesale sale of electricity in interstate commerce and over the rates, terms, and conditions of service of the transmission of electricity in interstate commerce, including the physical interconnection of wholesale generators. FERC has jurisdiction to determine allocation of wholesale regional costs to transmission zones. The FPA preserves state jurisdiction over the regulation of end-use sales (i.e., retail sales), including to load that is co- located at generating stations, and the connection of that end-use load to the electric system. Additionally, Section 212(h) of the FPA1 affirmatively prohibits the Commission from requiring retail wheeling.
The Indicated TOs believe that the Show Cause Order is helpful in rearticulating important guiding principles in this context. In particular, the Commission clearly confirmed that states have exclusive jurisdiction over retail sales, which means the states decide which entities are legally permitted to provide electricity to retail customers and how the costs of providing wholesale power are recovered from retail customers.2 What this means is that FERC can set a transmission rate that Network Customers serving all Network Load must pay for services and associated charges, but how a state chooses to assign and allocate the recovery of the cost of that charge between individual retail customers or among classes of end-use load may vary, as long as there is no cost- trapping. For example, some states may have non-bypassable charges that are direct pass-throughs based on load.
Large load customers can continue to co-locate and contract for power directly from generators where state laws and regulations addressing retail electric service allow.3 A few key things flow
1 16 U.S.C. § 824k(h).
2 The Indicated TOs note that the Organization of PJM States, Inc. also agrees with this principle. See Organization of PJM States, Inc., Post Technical Conference Comments of the Organization of PJM States, Inc., Docket No. AD24-11-000, at 4–5 (Dec. 9, 2024) (“Finally, FERC should confirm that the sale between co-located generation and load is a retail transaction subject to state jurisdiction. The Federal Power Act gives the Commission jurisdiction to regulate the transmission of electricity in interstate commerce. There is no regulatory gap. Sales of electricity from a generator to an end use customer in intrastate commerce are subject to state jurisdiction.” (footnote omitted)).3 Cf. New York v. FERC, 535 U.S. 1, 23 (2002) (explaining that “the legislative history [of the FPA] demonstrates Congress’ interest in retaining state jurisdiction over retail sales”).
PDF page 26
2
from this jurisdictional foundation and guidance the Commission has provided in this and other decisions:
• First, state jurisdiction must be recognized and respected. Consistent with basic principles articulated by the Commission in the Show Cause Order, transmission service for co- location arrangements must be applied to customers taking service under a state jurisdictional rate filed by an electric distribution company (EDC)/load serving entity (LSE) and approved by the state regulator.
• Second, it is important and necessary to implement retail metering of the end-use load at all times. No matter the terms of the Commission-jurisdictional rates, the end-use load is definitionally taking retail service, and the load data necessary for the administration and application of retail rates must be collected by the LSE and made available.
The Indicated TOs would welcome the Commission reaffirming that PJM generator interconnection procedures apply to the interconnection of and service to generation, including generation at which load is co-located, but not to the load itself, and the interconnection of that load is a matter of state, not federal, jurisdiction.
In addition, consistent with the jurisdictional principles as outlined by the Commission in section VI.A of the Show Cause Order, otherwise lawful state law rate structures are not federally preempted by any PJM Tariff language.
Further, the Commission and PJM should affirm that co-located loads that are physically interconnected to and synchronized with the PJM transmission system are utilizing the transmission system, which is not to say that the loads would be charged directly—such charges are instead charged to the Network Customer (or where appropriate Point-to-Point Customer) who will either be the Load Serving Entity or will in turn pass the charges on to the Load Serving Entity. Co-located loads that utilize essential reliability services require use of the transmission system that is subject to FERC’s jurisdiction. Only when a facility is disconnected from the grid and fully islanded is it not using or benefitting from the transmission system.
ii. Does the Tariff sufficiently address co-location arrangements with respect to each issue listed in this order? Please include specific tariff provisions or other governing documents that may apply;
The current PJM Tariff addresses and encompasses co-location arrangements, including the interconnection of generators where load is co-located and transmission service provided is to co- located load. Under the PJM Tariff, all load in PJM must be designed as Network Load and be served by a Network Customer paying Network Integration Transmission Service (Network Service) rates or, as and when appropriate, take and arrange for Point-to-Point Transmission
PDF page 27
3
Service (Point-to-Point Service). This construct is reflected in the PJM Reliability Assurance Agreement (RAA).4 These rules have been consistently applied since Order No. 888. Because these requirements apply to co-located load just like all other load on the system, the PJM Tariff addresses these arrangements.5 Designation of co-located load as PJM Network Load ensures that this load pays its fair share of transmission costs and essential reliability services. This is equitable and consistent with cost causation principles and the current tariff framework in which load pays for the transmission system. Further, it ensures consistent application of just and reasonable rates and protects against undue discrimination. Just like all other customers using the transmission system, interconnected co-located load must pay for all the services it receives.
The Indicated TOs, however, acknowledge that the level and growth in the interest of co-located load has been accompanied by questions, posed by customers and others, about the services co- located load uses and the rates that are applicable to co-location arrangements. The Indicated TOs have also benefited from hearing from many of these customers over the past several months and their primary interest appears to be in obtaining necessary certainty that can help the ultimate goal of speed to market. With direction from the Commission, the Indicated TOs are open to working with PJM and other stakeholders to incorporate appropriate PJM Tariff revisions to expressly specify that co-located load must be served by the existing forms of transmission service— Network Service or Point-to-Point Service. Any such change to the existing just and reasonable PJM Tariff—and the fundamental Network Load provisions it contains—must not inadvertently or deliberately suggest a new third class of service.
iii. If the Tariff does not sufficiently address co-location arrangements, how should the Tariff be modified to do so? As part of your answer, address
whether portions of the Guidance Document may serve as a just and
reasonable and not unduly discriminatory or preferential replacement rate.
Alternatively, address whether existing rules in the Tariff may or should
be modified to address co-location arrangements;
The core ratemaking principle at issue here—that co-located load, like all load in PJM, must be included in Network Load using Network Service or be a Point-to-Point Service customer—is already reflected in the PJM Tariff and longstanding Commission policy. Thus, no changes to the existing PJM Tariff are needed.
4 See Definition of Load Serving Entity; Article 2 (requiring all LSE’s to be party to agreement); Article 9.1 (requiring all LSEs to arrange for Network or Point-to-Point Service).5 See PJM Tariff, Sections 31.1, 31.2, 31.3 and 31.5 (addressing designation of loads for Network Customers and procedures to address new loads and load growth); Sections 17 and 19 (addressing designation of receipt points for Point-to-Point Customers and study procedures).
PDF page 28
4
iv. Parties may also address how co-located loads are similar to or disparate
from other types of arrangements where load and generation share the
same point of interconnection (such as Behind the Meter Generation as
defined in PJM’s Tariff or non-retail behind the meter generation) and
should consider how any proposed replacement rate would interact with
these other arrangements.
The PJM Tariff recognizes that, under defined circumstances, limited generation can be treated as being “behind the meter” of the load and that the load served by this Behind the Meter Generation (BTMG) is entitled to a reduction in their billing determinants for Network Transmission Service, based on the net load on the system.6 Of note, the PJM Tariff definition of BTMG applies to arrangements that “deliver[] energy to load without using the Transmission System” and thus would be inapplicable to all co-located load that is Network Load. Further, the PJM Tariff provisions relating to BTMG7 provide for an adjustment to the billing determinants for “Network Customers”—those provisions are unavailable for entities that are not Network Customers.8 That does not, of course, affect the treatment of the arrangement, or the measurement of the load, for state retail ratemaking purposes. That is not within the jurisdiction of the Commission.
b. Transmission Service
i. Please explain whether and to what extent different configurations of co-
located load rely on or otherwise use the transmission system to receive
power, directly or indirectly, from the co-located generator;
Co-located load that is physically interconnected with and synchronized to the grid uses the transmission system. Neither the fact that co-located load is geographically near a generator, nor its agreement to buy energy from the co-located generator, changes that, legally or physically. This is a straight-forward, engineering-based decision. End-use load can only fully avoid use of, reliance on, and benefit from the grid if the load is truly physically islanded without any connection to the transmission or distribution system at any time.
6 Non-Retail BTMG must operate at its full output during the first ten occurrences of Maximum Generation Emergency conditions each year in the zone where the unit is located, providing a significant contribution to grid reliability when it is needed most. PJM Tariff, Schedule 15. Additionally, the total amount of Non-Retail BTMG in the PJM Region is capped in any specific year and sets a maximum ceiling of 3,000 MW (unless increased through a section 205 filing), providing PJM the opportunity to ensure that Non-Retail BTMG does not detrimentally affect system operations. To be entitled to a reduction in their billing determinants for Network Transmission Service, co- located Customer Facilities would have to demonstrate that they meet each of the eligibility requirements.
7 PJM Tariff, section 34.2 (all Network Customers) and 34.3 (certain further provisions relating to Non-Retail Behind the Meter Generation).
8 The provisions would also be inapplicable to loads that are served by a contractual intermediary, rather than being served directly by a generator. In such a situation, the generator is just an upstream supplier.
PDF page 29
5
Co-located load that is connected to the grid also takes advantage of essential reliability services, such as ancillary services, including black start, regulation, and reserves, has the potential to draw real or reactive power from the grid at any time, and relies on and benefits from its connection to the transmission system at all times. Essential reliability services require use of the transmission system to deliver those services. If such co-located load arrangement does not need essential reliability services, then it would not need to interconnect to the transmission system altogether. Indeed, without that connection and the facilities that make it up, the co-location arrangement could not exist. Therefore, since co-located load is connected to the transmission system, it should pay for its share of the embedded costs of the grid.
ii. Please explain whether and to what extent different co-location
configurations impose costs on the transmission system or increase
transmission costs allocated to other parties. How can those costs be
approximated, given that certain co-location configurations may change
power flows on the grid and necessitate upgrades to the transmission
system? Retail loads typically take service from wholesale entities that
pay for Network Integration Transmission Service that allocates these
costs; co-located loads may not. Network Loads pay directly for Network
Integration Transmission Service. How should PJM estimate the effects
that different configurations of co-located load have on the transmission
system? Should these costs be passed through to co-location arrangements
in some way, and, if so, how?
In general, service to loads in PJM is paid for on an embedded cost basis. PJM’s rate design, incorporated into the PJM Tariff, permits transmission owners to recover, on a postage stamp basis without consideration of the distance between load and generation, the embedded costs of their respective portions of the transmission grid from network customers.9 As the Commission has explained, “PJM recovers the full revenue requirements of existing facilities (embedded costs) through its firm transmission rates.”10
If co-located load is interconnected to the transmission system, it is using the transmission system and must pay for its share of wholesale transmission service. For wholesale transmission service
9 See, e.g., Pennsylvania-New Jersey-Maryland Interconnection, et al., 81 FERC ¶ 61,257 (1997) (adopting PJM pricing proposal to allow recovery of embedded transmission revenue requirement from network customers), corrected by 82 FERC ¶ 61,103 (1998), and clarified in part by 92 FERC ¶ 61,282 (2000), and review granted in part, vacated in part by 295 F.3d 1 (D.C. Cir. 2002); PJM Tariff, Section 34.1 (providing for payment by network customers of load ratio share of embedded cost of their zone); PJM Tariff, Attachments H-1, H-1A, H-2, H-2A, H-3, H-3D, H-7, H-7A, H-9, H-9A, H-13, and H-13A (establishing network revenue requirements for each of the Exelon Utilities based on the embedded costs of their respective transmission systems).10 PJM Interconnection L.L.C., 139 FERC ¶ 61,243 at P 78 n.105 (2012).
PDF page 30
6
in PJM, the allocation of these wholesale charges should continue to be based on the FERC- approved cost allocation methodologies employed today.
Specifically, if a customer has the option, capability, or is requesting such capability to serve their full load from the PJM Transmission System, then the full load amount should be included in the LSEs’ total load used for determining its share of total system costs, even if they choose not to utilize that full suite of services at times. No free ridership should be enabled for grid connected customers. They are paying for the transmission system to be available to them. The fact that their load may not be constant does not reduce the possible need for investment in the transmission system or O&M costs that transmission owners incur to ensure that the system is available to them and that they receive reliable service. In fact, intermittent or switched loads can increase burdens and associated costs for the system.
The addition of co-located load, like other load additions, can require system upgrades, including to transmission and distribution facilities. PJM Transmission Owners are required to plan their transmission systems to ensure that energy can be delivered to all network customers on the system, including the LSEs responsible for all end-use load. 11 This ensures compliance with the requirements, imposed by the states, not PJM, that the end-use load itself must be served. In general, transmission upgrades required for a co-located load will be similar or the same as those required for an equivalent load addition close to, but not co-located with, the relevant generator, with the only real distinction between the two loads being the placement of a meter. The costs of these transmission upgrades are typically recovered from all load on the system via the Network Service rate. As explained above, retail sales, including to load that is co-located at generating stations, is regulated by the states, rather than the Commission.
Because co-located loads or their LSEs are required under the current PJM Tariff to take either Network Service or Point-to-Point Service, co-located load customers must pay for the costs of those and all other transmission upgrades along with all other customers. PJM should not treat co- located load differently simply because of its contract drafting or placement of the meter. Because all loads physically connected to and synchronized with the transmission system benefit from the transmission system, any attempt to isolate or piecemeal wholesale transmission services to quantify costs would be discriminatory since it would disregard the interconnected nature of the transmission system. Allowing co-located load to avoid paying network service charges would
11 PJM Tariff, Part III, Section 28.2 (stating, “[t]he Transmission Provider shall include the Network Customer’s Network Load in the Transmission System planning and the Transmission Owners shall, consistent with the terms and conditions of the Tariff, the Operating Agreement, and Good Utility Practice, endeavor to construct and place into service sufficient transfer capability to deliver the Network Customer’s Network Resources to serve its Network Load on a basis comparable to the delivery of each Transmission Owner’s own generating and purchased resources to its Native Load Customers”).
PDF page 31
7
provide that load with the benefits of the network while leaving others to shoulder the burden of paying for the transmission system.
iii. Please explain whether co-location arrangements are or should be
required to take Network Integration Transmission Service or Point-to-
Point Transmission Service; or whether a more tailored new category of
transmission service is warranted. Please also address any cost
allocation implications of your position on this issue;
No new category of service is required or warranted in the PJM Region. Under existing Commission policy and under the currently effective PJM Tariff, load is served either as a Network Service or as Point-to-Point Service customer.12 Co-located load simply needs to take service under one of those two frameworks as well as retail service under an appropriate state- jurisdictional tariff. There has been no allegation in any of the related proceedings leading up to the Commission’s Show Cause Order that the current regime requiring one of those two specified services has impaired any load’s ability to secure service safely, reliably, and at reasonable cost, or that service had been unobtainable as a result of the PJM Tariff’s longstanding requirements. There have been allegations that efforts to request service outside of the PJM Tariff provisions were thwarted,13 but such allegations do not contend that the PJM Tariff provisions, which require that requests proceed through a Network Customer or through Point-to-Point Service, failed. As stated above in the answer to question b.ii., any alteration to the current PJM Tariff that would allow co-located load to avoid paying network service charges would provide that load with the benefits of the network while leaving others to shoulder the burden of paying for the transmission system.
iv. What changes to the rates, terms, and conditions of Network Integration
Transmission Service or Point-to-Point Transmission Service or,
alternatively, what new form of transmission service(s) may be necessary
for different configurations of co-location to ensure that the Tariff is
consistent with cost causation principles and the beneficiary pays
principle?
Network Service and Point-to-Point Service in the PJM Region meet the needs of co-located customers. The existing rules are adequate to provide safe, reliable service at just and reasonable rates. Those that have argued for an alternative form of service appear to do so primarily out of
12 See discussion and RAA cites in Response ii above.13 See Complaint at 9 (“PJM has implemented practices that substantially affect rates, terms and conditions applicable to generation interconnection to the grid and wholesale market participation that are outside the Tariff and can be changed by PJM without notice at any time.”).
PDF page 32
8
concern about the charges associated with the existing rules—not because the existing rules are inadequate to provide safe, reliable service at just and reasonable rates. The Commission has previously rejected attempts to create new forms of service for those who claim to use the grid in a lesser fashion than others—nothing has changed.14
Having said this, the Indicated TOs are open to working collaboratively with PJM—and with their retail customers, state regulators, and other stakeholders—to consider clarifications to the PJM Tariff to expressly specify that co-located load must be served by the existing forms of transmission service—Network Service or Point-to-Point Service. The Indicated TOs would further commit to working with PJM to revise its Manuals and Guidance to address details of how the entities serving co-located load would satisfy Network Service and PTP requirements in a manner that also respects equitable principles and state jurisdiction over retail rates.
v. Parties may also wish to address how to determine which co-located load
configurations should be required to take Network Integration
Transmission Service or Point-to-Point Transmission Service or a new
form of transmission service (i.e., whether generalized policies or tests,
such as a multi-factor test, to be applied case-by-case, may be
appropriate), as well as the magnitude (i.e., how the service taken by co-
located load compares to service by other types of load). For example, if a co-located generator is synchronized to the grid but the load can be
configured to be wholly isolated from the grid in the event the co-located
generator trips offline, what technical and operational factors should
determine whether the co-location arrangement still relies on the
transmission system in ways that warrant a requirement that the co-located
load take Network Integration Transmission Service or Point-to-Point
Transmission Service or a new form of transmission service? Are there
potential co-located load configurations for which tailored approaches
may be appropriate?
Under existing Commission policy and under the PJM Tariff, load is served either by Network Service or Point-to-Point Service. Those rules apply to co-located load regardless of whether the co-located load is “in front of” or “behind” the generator’s interconnection because the co-located load remains connected to and reliant on the grid, takes grid services, and benefits from the grid. A new category of service is not warranted. Co-located load that is physically connected to and synchronized with the grid benefit from their interconnection to the network and the essential reliability services provided by the network. Indeed, those customers demand interconnection—
14 See, e.g., Nat’l R.R. Passenger Corp. v. PPL Elec. Utils. Corp. et al., 171 FERC ¶ 61,237, order on reh’g, 173 FERC ¶ 61,043 (2020).
PDF page 33
9
because they need it. Only in cases of true, physical disconnection, such as islanding, can the load claim not to receive benefits from the transmission network. Situations where an abnormal event or response to a Reliability, Availability and Serviceability (RAS) operation that result in the generating facility disconnecting from the grid do not equate to islanding. In such situations, if the load can continue being served from the transmission system while that generation unit is offline, it must be interconnected to the transmission system and take appropriate services. It would, therefore, not be islanded.
vi. With respect to the Guidance Document, please explain what it means to
be “electrically connected and synchronized to the PJM Transmission
System when consuming power” and how that implicates the use of
Network Integration Transmission Service or Point-to-Point Transmission
Service or a new form of transmission service;
PJM’s Commission-approved pro forma tariffs and interconnection agreements that cover terms of service for interconnection to the transmission grid require that all interconnecting customers be synchronized to the grid as a condition of service.15 This synchronization is necessary to preserve voltage stability and reliability and, as such, is foundational to safe and reliable operation of the physical facilities that comprise the transmission grid. 16 Thus, it follows that to be “electrically connected and synchronized” is a system operating condition that is separate from transmission rates. Instead, it concerns physical safety, reliability, and security of the physical facilities that are in play. Given these considerations, it has long been settled policy and law that any party that desires to interconnect to the grid must synchronize and keep its facilities synchronized to the grid at all times.
vii. What operational or commercial factors of a co-location arrangement
would result in a co-located load not needing to take any form of
transmission service, including what types of special protection schemes
or backup arrangements may be necessary to ensure the co-located load
never takes any form of transmission service?
As indicated above, the only arrangement where the end-use load does not need to take some form of transmission service is one in which the load is completely islanded and does not connect to, take service from, or rely on the transmission or distribution system in any way, for any type of
15 See, e.g., PJM Tariff, Attachment O, Appendix 2, Section 1.4.5.
16 See Reliability Standard FAC-001-0, R.2.1.12 (the Transmission Owner’s facility connection requirements shall address, but are not limited, to synchronizing of facilities) (note that the currently-effective version of FAC-001 (-4) has omitted this language); Reliability Standard EOP-005-3, R.8.4 (“Each Transmission Operator shall include within its operations training program . . . training on . . . Synchronizing (re-energized sections of the System).”).
PDF page 34
10
grid services, at any time. Even if operational protection and control technologies, such as relay switches, are used with co-located load and generation, the load still benefits from and utilizes grid services when 1) the load and generator are both connected to the system, and 2) the load is connected and the generator is disconnected from the system, even if the load is connected momentarily before it trips. For example, an RAS system operation that provides engineering and design practices to ensure reliability may fail, thrusting the full burden of the co-located load onto the grid to continue operating if the co-located generation is offline for any reason. The co-located load is relying on the grid for every moment it is connected to the transmission system, including when the system is standing by. The grid must be ready to accommodate the full burden of the load irrespective of what that load is doing at any given moment and must be planned for accordingly. Complete physical islanding from the grid is the only way to avoid taking any form of transmission service.17 Equally importantly, regardless of the load’s use of services, the entire co-location arrangement relies on the grid and grid facilities without which the generator could not operate, and the load-generation arrangement could not exist.
c. Ancillary or other wholesale services
i. Please explain whether and to what extent different configurations of co-
location arrangements rely on or benefit from ancillary services or black
start services and, if so, provide specific details about the type of service
and how the co-location arrangement relies on it. To what extent are these
benefits distinct from the benefits that other Network Integration
Transmission Service and Point-to-Point Transmission Service customers
derive from ancillary services?
Co-located load uses the same essential reliability services, such as ancillary services, as all other load on the transmission and distribution systems and receives the same benefits from those services as defined in Section 3 of Part I of the PJM Tariff and Schedules 2 through 6 of the PJM Tariff. If co-located load is interconnected to and synchronized with the transmission system, it impacts the grid and uses essential reliability services delivered by the transmission system. This fact is perhaps most readily apparent with load co-located with nuclear generation because nuclear units typically cannot provide regulation service, nor can they provide black start. Nuclear units can provide reactive power support and operating reserves, but the co-located load arrangements depend on a functioning grid that has more than the reactive power support and operating reserves provided by the nuclear unit. Because co-located load depends on essential reliability services and transmission service, co-located load depends on the transmission and/or distribution system. You
17 This situation would be entirely up to the state to decide if and how to regulate since it would not be within interstate commerce. Fed. Power Comm’n v. Florida Power & Light Co., 404 U.S. 453, 466 (1972) (“The elusive nature of electrons renders experimental evidence that might draw the fine distinctions required by this case practically unobtainable.”).
PDF page 35
11
cannot separate depending on those services, and accordingly cost allocation, from how those services are delivered.
ii. Please explain whether and to what extent co-location arrangements
impose costs related to ancillary services or black start services or increase the costs for such services allocated to other parties and how those costs
could be approximated;
Co-located load uses the same essential reliability services as all other load on the transmission and distribution system and receives the same benefits from those services. To the extent that the costs of those services are avoided by co-located load, other customers will necessarily be allocated all costs for these services.
iii. Please explain whether and to what extent co-location arrangements use,
benefit from, provide, or contribute to the need for transmission system
services in a manner that does not fit into a pre-existing category of
ancillary services or black start services, and, if so, should new categories
of services be created to accommodate that use? Alternatively, please
explain whether an alternative mechanism of cost allocation for pre-
existing ancillary services would be more appropriate;
Co-located load uses and benefits both from the transmission system physically and from services provided and delivered by that system just like all other load on the system. Co-located load’s reliance on the grid for essential reliability services is constant, as long as it is interconnected to and synchronized with the grid. These services are fundamental to maintaining reliable operation of the grid. It is not appropriate to assign portions or segments of services to co-located load.
The existing approach of cost allocation to load is appropriate for co-located load.
iv. What changes to rates, terms, and conditions of ancillary services,
including ancillary services procured in PJM’s markets, are necessary for
different configurations of co-location arrangements to ensure that the
Tariff is consistent with cost causation principles and the beneficiary pays
principle?
Changes to these rules are not necessary. If co-located load is designated as Network Load or takes Point-to-Point Service, the relevant charges for essential reliability services already apply and those are consistent with cost causation principles.
PDF page 36
12
v. Please explain how PJM should determine which co-located load
configurations take ancillary services or black start services (i.e., whether
generalized policies or tests, such as a multi-factor test, to be applied case- by-case may be appropriate), as well as the amount of such service (i.e.,
how the service taken by co-located load compares to service taken by
other types of load);
All co-located load arrangements that are interconnected to and synchronized with the PJM transmission system or the LSE/EDC’s distribution system take and/or benefit from essential reliability services, such as black start services. Co-located load, like all other load on the system, should take Network Service or Point-to-Point Service. The standard rules under the PJM Tariff will apply and no separate determination will be necessary.
d. Interconnection Procedures and Cost Allocation
i. Does the necessary study process adequately address potential impacts
caused by a co-location arrangement or is an additional study or new study
process warranted, e.g., a system impact study or generator deactivation
study? PJM should provide the details regarding the geographic scope of
the existing necessary study process, what is studied, and how the results
are reported, including what opportunities stakeholders, the interconnected
transmission owner, or the PJM IMM have to review the results, if any;
In the Show Cause Order, the Commission expressed concern “that the necessary study process may not be fully capturing the transmission system impacts of co-locating load, which could result in such arrangements not paying the costs of network upgrades that would be caused by the co- location.”18 The necessary study process, together with other studies and analysis, which include the individual TOs’ feasibility/engineering studies, are designed to ensure appropriate evaluation of, among other things, generator interconnections, modifications, and retirements and load additions. A necessary study itself evaluates the impact, if any, on the Transmission System, of planned modifications to, as relevant here, a Generating Facility.19 With respect to load addition studies, the Indicated TOs perform such studies to determine what, if any, new or upgraded system facilities are necessary to reliably support the load interconnections based on the near-term and longer-term ramp rates. Studies must show that the transmission system can serve them. With the addition of co-located load, the relevant studies are jointly performed by PJM and the individual TOs in the zones where the load is being interconnected. These Commission-jurisdictional studies are compatible with retail load addition studies and can typically be conducted in a coordinated
18 See Show Cause Order at P 79.19 See PJM Tariff, Part IX, Subpart G, Form of Necessary Studies Agreement.
PDF page 37
13
manner.20 Collectively, these existing individual processes are sufficient for studying new and modifications to existing generating facilities and new load, inclusive of co-located load, being added onto the system as Network Service or Point-to-Point Service customers. A separate interconnection study process for co-located load is not necessary or appropriate in the PJM Region.
ii. Please explain whether PJM’s necessary study process allows a co-
location arrangement to demonstrate its capability to flexibly adjust its
withdrawals from or injections to the transmission system (e.g., by using
secondary backup generation or by curtailing on-site load), and reflect this
capability in the operating assumptions PJM considers when estimating
the co-location arrangement’s impacts on the transmission system? If not,
would it be appropriate to establish a new or revised study process that
allows for such a demonstration?
The PJM necessary study process does not include this “flexibility” analysis, nor should it. Whether the end-use load and generation in a co-location arrangement has the capability to adjust its collective withdrawal or injection or the load has the ability to use secondary backup generator behind the end-use customer’s retail meter may potentially reduce that load’s need for energy from its primary generation source, but it does not guarantee how the end-use load or the generation load will operate in real time. We must plan the transmission system to serve the full co-located load amount both because we cannot be sure how it will behave operationally and because that load, independent of the association, has a right to receive retail service. Outside of response to extreme operational conditions on the transmission system, the terms and conditions under which end-use load can choose or be required to be flexible in its use of energy is a matter of state, not federal, jurisdiction. However, flexibility of the load should be captured as part of the EDC’s/LSE’s inputs into PJM’s large load forecast where it is known, assured, and can be modelled. The Indicated TOs emphasize the importance of understanding the nature and durability of any load behavioral commitments. In the absence of a state law or retail tariff allowing for a more durable commitment, any contractual commitment by end-use load to interrupt its operations or its use of retail electric service will at best be limited to the current contracting party.
iii. What changes to interconnection procedures and agreements may be
necessary to ensure that PJM identifies the reliability impact to the
transmission system of load co-locating with existing generation including
the need for dynamic response models?
20 The Indicated TOs note that while the necessary study process is useful for evaluating modifications at a Generating Facility related to a co-location arrangement, load addition studies performed by local utilities are required to determine any necessary interconnection facilities and upgrades to reliably support the co-located load interconnection.
PDF page 38
14
To the extent that an existing generation interconnection is being modified to allow that interconnection to be shared with end-use load, such a change would likely require amendments to the applicable interconnection service agreement acceptable to all parties if for no other reason than to reflect equipment changes and necessary physical and operational changes to protect the transmission system. Moreover, the addition of load may require state specific agreements between EDCs/LSEs and load customers and are typically governed by the retail tariff in the absence of customer-specific agreements. PJM and FERC should confirm that all co-located load is Network Load unless alternative arrangements are made for Point-to-Point Service. With that load being treated as Network or PTP load, existing procedures are adequate to protect the reliability of the system. TOs utilize separate procedures to study load and generation interconnections, including requesting specific modeling information. Such analysis can result in case-specific determinations. Again, a separate or unified process interconnection process for co- located load is not necessary or appropriate in the PJM Region.
iv. To what extent does a co-location arrangement raise potentially distinct
cost-allocation issues relative to a deactivating generator that causes the
need for transmission upgrades? What principles should the Commission
apply to allocate the costs of any transmission upgrades needed to mitigate
the impacts of co-locating load? What steps should PJM take to ensure
these costs are transparent to all parties?
PJM Tariff, Section V outlines the process for requesting and studying proposed generator deactivations for potential reliability impacts. There are no distinct cost-allocation issues regarding potential transmission upgrades because of a deactivating unit associated with a co- located load arrangement. Under existing rules, if the generator changes its Interconnection Service Agreement to enable it to operate in a co-located load arrangement, then any upgrades would need to be paid for by the generator. There are also no distinct reliability issues for the co- located generating unit that PJM would not already study.
The addition of new end-use load is regulated by state law in contrast to the broad Commission jurisdiction over wholesale sales and generators participating in interstate commerce. However, the costs of transmission upgrades required to serve co-located end-use load, like the costs of transmission upgrades for all end-use load customers, are recovered through transmission rates. The addition of load, including co-located load, benefits other customers because the shared embedded costs of the grid are paid by all customers, so that new load additions spread those costs more broadly when that new load takes service as a Network or PTP customer. If and to the extent there is a need for customer-specific facilities for a particular customer, issues associated with such facilities, including an assessment of the jurisdiction over the issue, are best addressed in individual
PDF page 39
15
proceedings. It would be inappropriate for the Commission to attempt to devise some general rule applicable to service to end-use customers.
The Indicated TOs believe that co-located load should be in front of the meter and treated as Network Load. If the Commission (or state) allows behind-the-meter arrangements and then the generator the load is co-located with retires, the load can potentially “appear” on the PJM transmission system very quickly. This could result in reliability impacts to the PJM transmission system.
v. Are changes needed to how PJM allocates the costs of any transmission
upgrades needed to mitigate the transmission system impacts of co-
locating load, if any, including whether the costs of those upgrades can
ever be allocated to a party other than the co-located generator, co-located
load, and/or co-location arrangement?
The current PJM Tariff correctly apportions the costs of the transmission among those who use and benefit from it. The costs of transmission upgrades as a result of new end-use load additions are shared among transmission customers. There are no special FERC-jurisdictional rules for the specific end-use load that is co-located. If and to the extent there is a need for customer specific facilities for a particular customer, issues associated with such facilities, including an assessment of the jurisdiction over the issue, are best addressed in individual proceedings. It would be inappropriate for the Commission to attempt to devise some general rule applicable to service to end-use customers.
Having said this, the Indicated TOs agree with the Commission that as this co-location space continues to rapidly evolve, the focus remains to ensure that all Commission-jurisdictional rates and charges “reflect to some degree the costs actually caused by the customer who must pay for them,” and that costs are allocated in a manner that is at least roughly commensurate with the benefits that entity receives.
vi. Are changes to the pro forma interconnection-related agreements
necessary to accommodate the addition of co-located load to existing
generation?
As noted in PJM’s Guidance Document and as summarized in a response above, existing interconnection agreements address the generation interconnection and the injection of energy onto the grid. These agreements would need to be amended with the consent of all parties to the agreement if the configuration is altered to address site specific peculiarities, which could include load at the same location. The relevant pro forma agreements were not designed for large load interconnections, and service to such load is a matter of state, not federal, jurisdiction. The relevant
PDF page 40
16
pro forma agreements should not be altered for the specific purpose of accommodating these configurations which, as both project proponents and the Commission have explained, are likely to vary significantly from configuration to configuration.
vii. Please explain whether changes to interconnection procedures and
agreements are necessary to accommodate new generation interconnecting
with co-located load, including whether the existing queue process is
sufficient for such arrangements?
The existing queue process is designed to study the interconnection of generation and is sufficient for that process. All load and, separately, all generation, that wants to connect to the grid needs to go through the established study processes to ensure the reliability of the grid, given that the generation and load can operate independently despite co-location.
viii. Please explain whether or not it would be appropriate to establish an interconnection study process outside of PJM’s interconnection queue
process for newly interconnecting co-location arrangements that do not
exchange power with the transmission system and do not require network
upgrades?
Only truly islanded systems where load does not connect to, take service from, or rely on the transmission and distribution system in any way would meet the requirement that they “do not exchange power with the transmission system and do not require network upgrades.” All other arrangements require study and potential upgrades, which are already performed by the local EDCs/LSEs/TOs, as described above.
If a customer has the option, capability, or is requesting such capability to serve their full load from the transmission system, then the full load amount should be included when studying the interconnecting co-location arrangement. Having the ability to temporarily or intermittently operate does not mean that the co-location arrangement is not “exchanging power” for purpose of the PJM interconnection study process.
ix. A generator with a co-located load that is not a party to a transmission service agreement is arguably distinguishable from other generators. To
the extent co-located arrangements create costs, or benefit from bulk
power system services, but the generator and load are not exposed to these
costs because of their contractual relationship, should PJM modify the
Tariff and related agreements to allocate those costs to the generator
directly?
PDF page 41
17
Generation and end-use load cannot enter into contractual arrangements that exempt the load from its obligations under the PJM Tariff to take service as a Network or PTP customer and to pay the costs that come with the service that it receives. Those are requirements of the applicable transmission rates. There is no need to modify the PJM Tariff to change the incidence of transmission service and facilities costs from load to generation.
e. PJM Capacity Market, Reliability, and Resource Adequacy
i. What changes to PJM’s capacity market rules are necessary to ensure that
the Tariff specifies how co-located generation and/or load participates in
the capacity market in a way that reflects the potentially unique physical
and operational characteristics of the co-location arrangement (e.g., the
presence of secondary backup generation, the capability to curtail on-site
load or other operational flexibilities, among others) and is otherwise just, reasonable, and not unduly discriminatory or preferential?
Treating co-located end-use load like all other end-use load on the system by requiring it to take Network Service or Point-to-Point Service avoids the need to modify the capacity market rules and ensures that those rules are not unduly discriminatory or preferential against any customer. To be clear, and as discussed above, the PJM RAA requires all LSEs in PJM to subject themselves to those requirements. Of course, a generator cannot both dedicate its capacity to directly serve co-located end-use load and separately offer that same capacity into the capacity market. However, the existing rules already accommodate bilateral capacity transactions between specific generating units and load customers. Those rules work for co-located load and its relationship to the co-located generator as long as the load is treated as a Network Customer. This straightforward approach to handling co-located load with regard to the capacity market has the considerable benefit of not requiring changes to PJM’s capacity market. The broader circumstances and challenges currently facing PJM’s capacity market would not benefit from further intervention and reform due to co-located load arrangements at a time when there are considerable resource adequacy concerns in the PJM footprint and there are efforts being made to advance certainty in the capacity market design.
ii. What Tariff change or changes to the interconnection service agreement
are necessary to ensure that PJM and the interconnected transmission
owner have sufficient visibility into the co-located load configuration?
In general, changes to the applicable pro forma service agreements are not appropriate. As long as co-located load is treated like all other load on the system, including as to metering and telemetry, and is a retail customer of the relevant distribution utility, the relevant state retail tariffs provide
PDF page 42
18
the appropriate visibility into the co-located load configuration, just as they do for any other load interconnection.
Interconnection agreements should include appropriate metering requirements. As stated above, co-located loads served from the transmission system under PJM Tariff, Part III, must have separate metering for load consumption and generator output.
iii. Please explain whether the existing Tariff rules are sufficient to ensure resource adequacy if increasing numbers of large existing generators
choose to co-locate with load;
Adding load located at a generator site to the system, like adding any other new load, introduces challenges to the existing resource adequacy problem. But as with other such load, existing PJM Tariff rules should be sufficient to study the impacts as long as co-located load is recognized as the load addition that it is, comparable to other new load additions to the system. Co-located load designated as Network Load will be included in the load forecasts and will receive appropriate treatment in the capacity market auctions, as discussed above.
iv. What deactivation or interconnection modification studies should PJM
undertake to ensure resource adequacy and/or protect reliability should an
existing generator seek to enter into a co-location arrangement? If PJM
finds that the co-location would cause reliability standards violations, what
remediation techniques would be appropriate (e.g., reliability must-run
contracts, delaying the co-location arrangement until the reliability
violations are addressed, etc.)?
Co-located end-use load should be studied under the relevant state jurisdictional process for new load additions and PJM’s role should be limited to the standard transmission planning process for all new load additions. Additionally, the loss of capacity from an existing generator seeking to enter into a co-location arrangement should be studied by PJM. Because the federal role in end- use load additions is limited, PJM and the Commission should not create processes in the PJM Tariff that would interfere with state jurisdiction. However, all load, and separately, all generation, that want to connect to the grid should go through the established PJM study processes to ensure the reliability of the grid. As stated above, if an existing generator proposes modifications to enable it to operate in a co-located arrangement, then any transmission upgrades related to the generator modifications would need to be paid by that generator.
v. What changes are necessary, if any, to other PJM planning processes to
better plan for and address the resource adequacy and reliability impacts
of co-location arrangements, including, for example, whether or not the
PDF page 43
19
frequency of such processes might be changed? Similarly, should PJM
consider changes to load forecasting methods, informational postings, or
the reserve margin study process to better plan for and address the
resource adequacy and reliability impacts of co-location arrangements?
All load additions create new demands for energy regardless of their location. The resource adequacy and reliability challenges exist regardless of whether end-use load is connected to the grid at a generator site or elsewhere, and regardless of whether the point of connection lies “behind” or “in front of” the generator’s meter. Changes to the planning and load forecasting processes should not be needed solely to address end-use load that is located at a generator as long as co- located load is treated like all other load on the system and takes either Network Service or Point- to-Point Service.
vi. Under what circumstances can PJM direct the operators of co-location
arrangements to shed such load if deemed necessary to preserve system
reliability during a declared emergency?
If treated as Network Load, co-located end-use load can only be shed by PJM when required under the relevant NERC and PJM standards as documented in PJM’s Manual 13 on Emergency Operations. The general terms and conditions governing service to co-located end-use load are regulated by states, which are free to offer optional or mandatory interruptible service rates.
We note that failure to meter the co-located load will lead to anomalous results. For example, if the generator trips offline without disconnecting from the transmission system, the unmetered load “appears” on the system and draws power from the grid. In an extreme case, this can create a system emergency that requires load drop—which must come from other network load that did not cause the emergency.
f. Other
i. Are any changes to PJM’s energy or ancillary services market rules
necessary to address co-location arrangements?
Other changes are not necessary. If co-located end-use load is treated like all other end-use load on the system, served through either Network Service or Point-to-Point Service, there is no gap in the existing rules.
ii. Please discuss whether back-up service can provide benefits to customers
or otherwise help minimize system costs, including with specific examples
or best practices, if possible;
PDF page 44
20
In general, having reliable backup generation can benefit any end-use load by providing alternative sources of power in times of system emergency. That capability can also benefit other end-use load customers if it can and is used for their benefit as well. However, the presence of on-site backup generation does not exempt load from paying the costs of transmission service, because it still benefits from the transmission system. It does not matter whether that load is co-located with generation. Notably, nuclear units must be interconnected with the transmission grid to operate, so any backup service provided by a nuclear unit is dependent on continued grid operation to function at all.
iii. Parties may also choose to address how co-location arrangements may
provide benefits, including potentially reducing required transmission
upgrades to interconnect large loads, reducing congestion, or providing
operational flexibility during system peaks or emergencies?
A study is necessary to determine, on a case-by-case basis, whether co-located load generally would result in a reduction of required transmission upgrades, reduction in congestion, or provide operational flexibility during system peaks or emergencies. Thus, although the Indicated TOs recognize that there could be some instances in which co-location of load, like other load, may provide benefits to the transmission system, that cannot be determined until after full studies are completed.
iv. Parties may also address whether, and if so, how, the Tariff should be
modified to best accommodate or encourage co-location arrangements to
be constructed in such a way as to minimize total system costs or
otherwise provide certain benefits, including protections for existing
customers and allocation of costs consistent with the cost-causation
principle;
No federal tariff changes are needed to promote co-location because the current PJM Tariff and state regulatory regimes can and do accommodate reliable and economic co-located configurations under existing rules. If there is a hurdle to locating end-use load at generation sites, that hurdle is not the lack of a rate discount, but of confusion over the applicability of the established tariffs. The best way to ensure cost-effective co-location is to maintain consistent rules: treat co-located load as any other load on the system. The Indicated TOs also note that states may choose to promote co-location arrangements through, for example, appropriate distribution tariffs or tax incentives—whether the states choose to do so is not within FERC’s jurisdiction or control.
v. What Tariff provisions, if any, are necessary to ensure clarity regarding
the aspects of service to co-located load and generation facilities that may
be administered through the Tariff versus state jurisdictional retail tariffs?
PDF page 45
21
Consistent with existing precedent, the Commission might clarify that generator interconnection agreements do not themselves provide for or confer the right to serve end-use retail load or the right of new load to take retail service at a specific point or under particular rates; instead, such services are regulated under state law. Potential customers could benefit from clarification by the Commission that co-located load is Network Load and must be included in the load of either a Network Customer or arranged for Point-to-Point Service. Alternatively, the Indicated TOs are open to working with PJM and other stakeholders to incorporate appropriate PJM Tariff revisions to expressly specify that co-located load must be served by the existing forms of transmission service—Network Service or Point-to-Point Service.
vi. We also encourage parties to address any national security implications
associated with co-location arrangements, including with respect to the
specific issues discussed in this show cause order, and what actions, if
any, the Commission should take in response.
Allowing co-location arrangements to move forward rapidly and without regulatory ambiguity is the best way to achieve the national security goals of this Commission and this administration. The most straightforward way to accomplish that goal is simply to recognize that co-located load is Network Load like all other load on the system and should pay for Network Service like all other customers. A clear statement from this Commission that the existing rules work, and that co- located load can be served under existing rules is the fastest path to data center interconnections needed to win the artificial intelligence (AI) race. In contrast, development of new forms of service, and efforts to mesh those new forms of service with the existing rules, will certainly get bogged down in extended litigation that will impede efforts to develop AI.
Any delays associated with interconnection of co-located load experienced thus far have not been because the rates do not provide for artificial exemption of the arrangements from transmission rates, but because of efforts to dispute the applicability of those rates. Importantly, this does not preclude PJM and the PJM TOs from considering and pursuing beneficial enhancements as the business areas surrounding co-location continue to evolve. As previously noted, the Indicated TOs are attempting to consider potential beneficial enhancements collectively and with PJM, consistent with existing rights and responsibilities.
vii. Finally, for generation units paid for originally by consumers in base rates prior to restructuring, is it fair and/or just and reasonable if these units are taken out of the system’s supply stack and devoted exclusively to serving
co-location arrangements with one or a few large customers?
PDF page 46
22
There are two issues here: generation costs and transmission costs. In general, the continued obligation, if any, of generation to serve classes of end-use customers who pay for that generation is a matter of state jurisdiction and concern. Transmission costs are certainly a matter of FERC concern. The addition of end-use load, including co-located load, at established cost-based rates typically benefits other customers with respect to transmission costs, because the shared embedded costs of the grid are paid by all customers, so that new load additions spread those costs more broadly. Treating co-located end-use load like all other load additions by requiring them to take either Network Service or Point-to-Point Service ensures that other customers are protected. In contrast, creating a new class of service where transmission costs are not paid, particularly one that exempts those customers for either paying for services or simply for reliance on the shared system, does not ensure equitable treatment of other customers on the system.
PDF page 47
CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person designated on the official service list in the above captioned dockets. Dated at Chicago, IL this 24th day of March, 2025.
/s/ Geneva Kennedy
Geneva Kennedy
Exelon Corporation