EL25-49-000 · 2025-03-24 · Exelon Corporation, American Electric Power Corporation and 17 others

Answer of the Indicated PJM Transmission Owners to the Order Instituting the Proceeding Under Section 206 of the Federal Power Act and Consolidating with…

Text extracted from the eLibrary original (SHA-256 9afc8dfeed3325c8…). Download the original from the official source.

Contents · 11 sections
  1. I. EXECUTIVE SUMMARY p. 3
  2. II. BACKGROUND p. 6
  3. A. Procedural Overview p. 6
  4. B. Co-location of Load p. 7
  5. III. DISCUSSION p. 10
  6. A. Classification of Co-located Load as Network Load Is Just and Reasonable. p. 10
  7. B. Co-Located Load Benefits From Essential Services Provided Using the Grid. p. 12
  8. C. All Load, Including Co-located Load, Is Used to Plan the Transmission p. 14
  9. D. Creating A New, Non-Paying Category of Service Under the PJM Tariff p. 17
  10. IV. CONCLUSION p. 20
  11. ATTACHMENT A p. 24

Read topic-matched comments in EL25-49

Topics in the text: Connecting load and generation · Cost allocation · Retail and wholesale authority

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text · Topic match: Connecting load and generation

Southern Maryland Electric Cooperative, Inc.; UGI Utilities Inc; and Wabash Valley Power Association, Inc. 3 16 U.S.C. § 824e. 4 PJM Interconnection, L.L.C., 190 FERC ¶ 61,195 (2025) (“Show Cause Order”). 5 All capitalized terms not otherwise defined herein shall have the meaning set forth in the…
Read this passage Filed comments: Connecting load and generation

I. EXECUTIVE SUMMARY

printed heading · Topic match: Connecting load and generation

PJM’s Independent Market Monitor (“IMM”) has correctly submitted that “it is simply not possible to be off the grid if you are interconnected to the grid.”7 The North American Electric Reliability Corporation (“NERC”) recognized in its 2024 Long-Term Reliability Assessment (“2024 LTRA”) that, in…
Read this passage Filed comments: Connecting load and generation

II. BACKGROUND

printed heading

II.
Read this passage

A. Procedural Overview

printed heading

Procedural Overview The Show Cause Order is the culmination of several proceedings addressing the issue of co-location, both in specific circumstances and on an industry-wide basis.
Read this passage

B. Co-location of Load

printed heading · Topic match: Connecting load and generation

Indeed, it must be interconnected to the grid.17 Co-located load uses and depends on the grid, causing changing flows on the grid from second to second.
Read this passage Filed comments: Connecting load and generation

III. DISCUSSION

printed heading

III.
Read this passage

A. Classification of Co-located Load as Network Load Is Just and Reasonable.

printed heading · Topic match: Connecting load and generation

With that said, the Indicated TOs remain open to and anticipate the potential for further discussion regarding possible changes to tariffs to expressly specify that co-located load must be served by the existing forms of transmission service—Network Service or Point-to-Point Service—while…
Read this passage Filed comments: Connecting load and generation

B. Co-Located Load Benefits From Essential Services Provided Using the Grid.

printed heading · Topic match: Connecting load and generation

EL25-20 (Dec. 12, 2024) (“Weaver Decl.”) (explaining that because nuclear units are unable to provide black start services, co-located load must rely on those services from other resources in PJM that are connected to the grid in order to come back online); id. at P 19 (explaining that the…
Read this passage Filed comments: Connecting load and generation

C. All Load, Including Co-located Load, Is Used to Plan the Transmission

printed heading · Topic match: Connecting load and generation

In furtherance of such cooperation each Party shall: . . . . (c) provide or arrange for Network Transmission Service or Firm Point-to-Point Transmission Service for service to the projected load of the Party . . . .39 Taken together, these provisions mean that any entity that is serving an end-use…
Read this passage Filed comments: Connecting load and generation

D. Creating A New, Non-Paying Category of Service Under the PJM Tariff

printed heading · Topic match: Connecting load and generation

A fundamental ratemaking principle establishes that “the costs assessed against a party must bear some resemblance ‘to the burdens imposed or benefits drawn by that party.’”44 The PJM Tariff complies with these cost allocation requirements and appropriately accounts for the cost of the benefits…
Read this passage Filed comments: Connecting load and generation

IV. CONCLUSION

printed heading

CONCLUSION For the reasons stated above, the Indicated TOs respectfully request that the Commission reaffirm the justness and reasonableness of the current, non-discriminatory—and functional— PJM Tariff, because PJM’s Tariff already accommodates co-location arrangements through the two types of…
Read this passage

ATTACHMENT A

printed heading · Topic match: Connecting load and generation

FERC, 535 U.S. 1, 23 (2002) (explaining that “the legislative history [of the FPA] demonstrates Congress’ interest in retaining state jurisdiction over retail sales”). 2 from this jurisdictional foundation and guidance the Commission has provided in this and other decisions: • First, state…
Read this passage Filed comments: Connecting load and generation

CERTIFICATE OF SERVICE

printed heading

Dated at Chicago, IL this 24th day of March, 2025. /s/ Geneva Kennedy Geneva Kennedy Exelon Corporation