EL25-49-000 · 2025-03-24 · Public Service Electric and Gas Company
Response of Public Service Electric and Gas Company to Show Cause Order issued on 02/20/2025
PDF page 1
UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
)
PJM Interconnection, LLC et al.
)
)
Docket Nos. EL25-49
Large Loads Co-Located at Generating
Facilities
)
)
AD24-11
Constellation Energy Generation, LLC
v. PJM Interconnection, L.L.C.
)
)
)
EL25-20
(Consolidated)
)
RESPONSE OF
PUBLIC SERVICE ELECTRIC AND GAS COMPANY
TO THE ORDER TO SHOW CAUSE
Data centers have vast importance for economic development and national security in the United States. To foster data center development and to maintain U.S. leadership in this transformative industry, the Commission should act expeditiously to reduce any regulatory barriers that may hinder their development. As relevant to this proceeding, data centers should have the option to select a configuration that best fits their particular circumstances and needs – whether this is in front of the meter or a co-location arrangement. While there has been significant litigation regarding co-location arrangements in recent months, the fact is that co-locating load with generation is not something new, but has been available in PJM for over two decades based on the Commission’s recognition that locating load in close proximity to generation resources will reduce system costs and benefit customers. Within the Public Service Electric and Gas Company (“PSE&G”) service territory and elsewhere in PJM, there are numerous customers, such as universities, industrial customers, pharmaceutical companies, and rooftop solar customers, that have behind the meter generation (“BTMG”) resources to
PDF page 2
2
meet their load requirements. Because such BTMG customers have reduced their use of the transmission system, under the PJM Tariff, they have been allocated costs based on their actual use of the system consistent with cost causation principles. There is no justification to treat behind the meter load any differently than BTMG, and the Commission should ensure that there is no undue discrimination in the treatment of co- located arrangements. Both should pay (and in the case of BTMG customers continue to pay) based only on actual usage of the transmission system.
PSE&G submits this Response to the Commission’s February 20, 2025 Order
Instituting Proceeding under Section 206 of the Federal Power Act and Consolidating with Other Proceedings (the “Show Cause Order”).1 In our Response,2 PSE&G proposes a principle-based approach to address the Commission’s issues and concerns and suggest a path forward to obtain timely and needed clarity with respect to co-located load rules that
(i) aligns with the Commission’s cost causation principles; (ii) does not adversely impact existing BTMG customers on PSE&G’s system and across the various PJM Transmission Owner systems in PJM; and (iii) preserves co-location as a viable option to support data center development in New Jersey and elsewhere in PJM, appropriately recognizing the benefits of locating data centers close to generation – whether behind the meter or in front of the meter – to reduce transmission system usage and the need for new transmission infrastructure, the costs of which are ultimately borne by customers.
1 PJM Interconnection, L.L.C., et al., 190 FERC ¶ 61,115 (2025).2 PSE&G is not responding to all of the questions posed in the Show Cause Order. Instead, as directed by the Commission, PSE&G is principally responding to issues relating to transmission cost allocation and transmission rate design, which fall within the filing rights of the PJM Transmission Owners under the Consolidated Transmission Operating Agreement (CTOA). See, e.g., CTOA Section 7.3 (provisions regarding PJM Transmission Owners’ filing rights over transmission rates and rate design under FPA Section 205).
PDF page 3
3
In the Show Cause Order, the Commission established an accelerated schedule, stating that it intends to issue a decision within three months. Just last week, Chairman Mark C. Christie reaffirmed the Commission’s commitment to an expeditious resolution of this proceeding stating: “we want to act quickly on this issue,” and that the Commission intends to “conduct and complete this important proceeding expeditiously, so we can provide clarity and certainty to all, from consumers to investors to load- serving utilities and independent generators.”3 PSE&G respectfully urges the Commission to effectuate a prompt resolution of this co-location proceeding, as expeditiously arriving at clear co-location rules is essential to allow states like New Jersey and data center customers to move forward with their development plans.
I. EXECUTIVE SUMMARY
Over the past nine months, there has been significant controversy and litigation before the Commission relating to co-location load arrangements. The Commission, however, recognized that co-location load arrangements are not new but are “becoming increasingly common in PJM.”4 The principal controversy before the Commission boils down to a basic transmission ratemaking question – specifically do co-located load arrangements use or benefit from the transmission system, and if so, what level of
3 See, e.g., March 18, 2025 Letter from Office of the Chairman, Mark C. Christie, responding to October 2, 2024 Letter from Governor Josh Shapiro, Docket Nos. EL25-49, EL24-149, ER24- 2172, and ER24-2888 et al. (emphasis added). In a March 18, 2025 Letter, Chairman Christie made a similar commitment in response to an October 31, 2024 letter from Governor Glenn Youngkin in Docket No. AD24-11.4 Show Cause Order at P 3. See also Id. P 65 (stating that “the surge of interest in co-location arrangements in PJM has put before the Commission several significant and novel issues.”).
PDF page 4
4
transmission or ancillary charges should be imposed to comport with the Federal Power Act’s “just and reasonable” standard and cost causation principles.
There are now six dockets pending before the Commission relating to co-located load. In November 2024, the Commission rejected one FPA Section 205 filing that sets forth a proposal under which the fully isolated co-located load would have paid no transmission or ancillary charges.5 In February 2025, the Commission rejected another FPA Section 205 filing proposing that all located load arrangements pay full network integration transmission service (“NITS”) and ancillary service charges on a gross load basis.6 It appears that the Commission was not satisfied that neither of the two Section 205 filings (representing opposite ends of the transmission pricing spectrum) passed muster under the just and reasonable standard and cost causation principles. In issuing the Show Cause Order, the Commission is effectively sending PJM and the PJM Transmission Owners back to the “drawing board” to develop a clear solution that reflects the co-located load’s use of the transmission system based on the specific configuration employed and to develop appropriate charges reflecting the degree of usage. In so doing, the Commission is not acting on a blank slate. Instead, informed by the extensive briefings and the robust records in the various dockets, the Commission provided certain findings and observations, as discussed herein, that should provide guideposts for this proceeding. Significantly, the Commission also recognized that any remedy or replacement rate adopted in this proceeding could impact existing customers throughout PJM with BTMG
5 PJM Interconnection, L.L.C., 189 FERC ¶ 61,078 (2024) (rejecting the amended ISA for failing to meet the requisite burden of proof).6 Atlantic City Electric Co., et al., 190 FERC ¶ 61,109 (2025) (rejecting the Section 205 filings for exceeding the filing entities’ filing rights under the CTOA).
PDF page 5
5
and has asked for ways to address this problem. Certain key principles should inform the next steps in this proceeding.
First, the Show Cause Order appropriately recognizes that (i) there are different co-location load configurations available; (ii) their use or impact on the power grid is different; and (iii) any transmission charges should reflect actual use of the grid.7 Accordingly, it logically follows that transmission charges, if imposed, must be based on usage of the power grid and should not be imposed on a blanket, one-size-fits-all basis. To comply with cost causation principles, which courts have described as adding “flesh to the bare statutory bones of the just and reasonable requirement” under the Federal Power Act,8 any charges imposed must reflect the use or benefit of the specific co-located load arrangement. A transmission pricing methodology that reflects cost causation would also provide the appropriate incentives for data centers to locate in close proximity to generation resources to reduce transmission costs.
Second, from a technical, engineering perspective, there is no material difference between co-located loads and other types of arrangements where load and generation share the same point of interconnection, such as BTMG.9 As discussed in Section III.B of this Response and illustrated in Figure 1, co-located load arrangements and BTMG arrangements result in the same reduced use or impact on the transmission grid.
7 See, e.g., Show Cause Order at P 77 (questioning whether Network Integration Transmission Service is the appropriate transmission service for all co-location arrangements or that such service would be consistent with cost causation principle.).8 See Old Dominion Electric Cooperative v. FERC, et al., 898 F.3d 1254, 1255 (D.C. Cir. 2018) (citing K N Energy v. FERC, 968 F.2d 1295, 1300 (D.C. Cir. 1992)).9 See Show Cause Order, P 88, Section General, Question (iv) (asking whether “co-located loads are similar to or disparate from other types of arrangements where load and generation share the same point of interconnection, such as Behind the Meter Generation (BTMG) as defined in PJM’s Tariff.”).
PDF page 6
6
Accordingly, in imposing transmission charges, if any, that would apply to co-located loads, the Commission should be mindful that there are many existing customers throughout PSE&G’s service territory as well as across the PJM footprint who have BTMG to meet a portion of their load requirements and have been allowed to net their BTMG against their network load for purposes of transmission cost allocation for more than twenty years. The Commission should allow existing BTMG customers to continue to net and should take no action that would disadvantage these existing customers. At the same time, however, to comply with the requirement under the Federal Power Act that rates may not be “unjust and unreasonable or unduly discriminatory or preferential,”10 the Commission should treat behind the meter load customers and BTMG customers in the same manner. One path forward is to allow BTM load customers to net so that they only pay for what they use, just as BTMG customers are allowed to net. Applying a transmission pricing approach that ignores actual use or impact on the transmission system would violate cost causation principles and treat these two classes of customers differently, resulting in harm to both classes of customers. Third, both the Commission and the states have recognized that data centers are vital to the U.S. economy and national security. To maintain US leadership in this critical industry, regulatory flexibility is needed to encourage and keep data center development in the United States. The Commission’s decision in this proceeding is an important one, and the Commission should avoid picking sides with respect to co-located configurations vs. front of the meter arrangements. In many instances, as noted, co-location – and the associated geographic proximity between the data center and the generator in this
10 18 U.S.C. 824e.
PDF page 7
7
arrangement – will reduce the need for new transmission infrastructure, resulting in affordability benefits for customers. Co-location represents an efficient use of the transmission system by reducing the need for upgrades, and the Commission should not impose policies that discourage this option.
II. BACKGROUND
A. Description of PSE&G
PSE&G is a regulated electric and gas utility and owns 1,600 circuit miles of electric transmission lines within the PJM region. PSE&G also has 2.4 million electric customers in its franchised service territory and an obligation to reliably serve those customers. Many customers on the PSE&G system are large load customers, such as universities, government agencies, manufacturers, and pharmaceutical companies, who rely on solar, cogeneration, reciprocating engine, gas turbine generation, combined heat and power (“CHP”), and other types of generation resources on a behind the meter basis to meet all or some of their power needs. In fact, according to the New Jersey Board of Public Utilities’ (“NJBPU”) Office of Clean Energy, there are currently over 200,000 behind the meter solar projects in New Jersey.11 Of this number, there are approximately 90,000 behind-the-meter solar installations in PSE&G’s service territory. For 23 consecutive years, PSE&G has won reliability awards in the Mid-Atlantic region and has a proven record of providing reliable and affordable service to customers.1211https://njcleanenergy.com/renewable-energy/project-activity-reports/project-activity- reports.12 PSE&G has an affiliate that has an ownership interest in approximately 3,800 MW of reliable, baseload carbon-free nuclear generation.
PDF page 8
8
B. The Show Cause Order
The Show Cause Order found based on the records of both the technical
conference and the Constellation complaint proceeding, the existing PJM Tariff “appears to be unjust and unreasonable or unduly discriminatory or preferential because it does not contain provisions addressing with sufficient clarity or consistency the rates, terms, and conditions that apply to co-location arrangements.”13 The Commission directed PJM and the PJM Transmission to respond to a number of issues and concerns raised in the Show Cause Order.
Throughout the Show Cause Order, the Commission pointed out that there are different co-location arrangements that use or impact the transmission system in different ways. The Commission provided two examples of co-location arrangements: (1) a network load that co-locates with a generator that is not a grid resource “that either serves the load as an off-grid back-up or that reduces the Network Load’s consumption during peak hours,” and (2) a fully isolated co-located load configuration.14 The Commission then stressed the importance of determining “which wholesale services, if any, would be necessary for that arrangement, and the appropriate charges for those services.”15 In this respect, the Commission recognized that existing customers with onsite or BTMG may be affected and asked parties to explain how “co-located loads are similar to or disparate from other types of arrangements where load and generation share the same
13 Show Cause Order at PP 2, 74, 78. See also Show Cause Order at P 3 (adopting PJM’s definition of co-located load “as a configuration through which end-use customer load is physically connected to the facilities of an existing or planned generation unit.”14 Show Cause Order at P 76.15 Show Cause Order at P 74 (emphasis added). See also Show Cause Order at P 76 (stating that different configurations will have different impacts on the transmission system).
PDF page 9
9
point of interconnection (such as Behind the Meter Generation as defined in the PJM Tariff or non-retail behind the meter generation) and should consider how any proposed replacement rate would interact with these other arrangements.”16
III. RESPONSE
A. The Commission Recognizes The Variety of Co-Located
Configurations And Should Establish Transmission and Ancillary
Service Charges For Co-Located Customers Based On Actual Use
Consistent With Cost Causation Principles17
In the Show Cause Order, the Commission found that the current PJM Tariff does not have a “process for determining what transmission service different co-located configurations must take, including what costs, if any, should be allocated to co-location arrangements.”18 Importantly, throughout the Show Cause Order, Commission repeatedly emphasized that there are “various configurations” available for co-location load arrangements and importantly, depending upon the specific co-location arrangements employed, they are likely to use or benefit from the transmission system in different ways depending on how it is configured and moreover, those configurations will themselves likely have different impacts on the transmission system.”19 For example, the Commission pointed out that, under its regulations, “transmission service” is defined to include a variety of transmission products, such as “network, point-to-point service,
16 Show Cause at P 88, Section a (General) Question iv. The Commission also explained that unlike the technical conference in Docket No. AD24-11, which focused on large co-located loads, in the Show Cause Order, the Commission did “not similarly limit this proceeding to co-located loads of a certain size.” Id. at P 3, n.5.17 This section responds to the Commission’s briefing questions set forth at P 88, Section b (Transmission Service, Questions (i), (ii) and Section c (Ancillary Services), Questions (i), (iv).18 Show Cause at P 78.19 Id. at P 74.
PDF page 10
10
ancillary service, other methods of electric transmission, or the interconnection with jurisdictional transmission facilities.”20 Importantly, the Commission stressed that different co-location arrangements are likely to use or benefit from the transmission system differently, stating as follows:
The record demonstrates that different co-location arrangements are
likely to use or benefit from the transmission system in different ways depending on how they are configured and, moreover, that those
different configurations will themselves likely have different impacts on the transmission system. For example, Network Load may co-locate with a generator that is not a grid resource and that either serves the load as an off-grid backup or that reduces the Network Load’s consumption during
peak hours.21
It is telling that the Commission acknowledged that while PJM’s preference is that “large loads be in front of the meter and designated as PJM Network Load,” the Commission stated that the PJM Tariff does not appear to require this service.22 Moreover, the Commission expressed skepticism that this is the appropriate type of transmission service that should be required of all co-located configurations, stating: “there is no clear record before us that Network Integration Transmission Service is the appropriate transmission service for all co-location arrangements or that such service would be consistent with the cost causation principle (i.e., that Network Integration Transmission Service appropriately aligns costs and benefits in a manner that is roughly commensurate) for such arrangements.”2320 Id. at P 76.21 Id. (Emphasis added).22 Id. at P 77.23 Show Cause Order at P 78 (emphasis added).
PDF page 11
11
The Show Cause Order’s findings and observations align with the technical realities associated with various co-location arrangements. For example, the data center load could be structured on a front of the meter basis with the co-located generator providing primary power and with back-up power coming from the grid; or the data center load could be fully isolated behind the meter with system protection facilities in place to ensure that there is no flow of power from the grid to the load.
In determining what transmission service charges, if any, should be imposed in the context of different co-located configurations, the Commission should simply apply well- established cost causation principles that courts have recognized as informing the just and reasonable standard. 24 A bedrock ratemaking principle is that all FERC-jurisdictional rates and charges must “reflect to some degree the costs actually caused by the customer who must pay for them,” and that costs must be allocated in a manner that is “at least commensurate with the benefits that entity receives.”25 Under this principle, which has been the foundation of the Commission’s transmission pricing policies, transmission charges to be assessed based on a party’s “actual use” of the transmission system. Commission precedent in the co-location context teaches that in circumstances in which certain customers “rely to a lesser degree on the PJM integrated transmission system” than others, the transmission charges must reflect the parties’ actual use of the transmission system because this would ensure that “PJM allocates its transmission charges to those
24 See, e.g., Old Dominion Electric Cooperative v. FERC, et al., 898 F.3d 1254, 1255 (D.C. Cir. 2018).
25 See Show Cause Order at P 74 (citing Ill. Com. Comm’n v. FERC, 576 F.3d 470, 476 (7th Cir. 2009)).
PDF page 12
12
using the system on peak and helps to ensure that customers have the incentives to curtail load during peak periods.”26
Courts and the Commission has applied this basic ratemaking principle in
numerous cases. For instance, the Court of Appeals for D.C. Circuit stated, “[f]or decades, the Commission and the courts have understood the [just and reasonable] requirement to incorporate a cost-causation principle – the rates charged for electricity should reflect the costs of providing it.”27 The D.C. Circuit explained the cost-causation principle requires a comparison of the “costs assessed against a party to the burdens imposed or benefits drawn by that party.”28 Additionally, the court stressed that “the cost- causation principle, by allocating project costs consistent with project benefits, creates the best incentives for PJM member utilities themselves to agree on when to invest their scarce resources in transmission improvements.”29
On the same day that the Commission issued the Show Cause Order, the
Commission issued another order rejecting tariff revisions proposing to charge all co- located load based on a gross load basis.30 It is clear that in the Show Cause Order, the Commission is looking for a more fine-tuned or calibrated cost allocation methodology that aligns with cost-causation and that a blanket, catch-all approach is untenable under
26 See e.g., Occidental Chem. Corp. v. PJM Interconnection, L.L.C., et al., 101 FERC ¶ 61,005 (2002), order on compliance filing and reh’g, 102 FERC ¶ 61,275 at P 2 (2003), order on compliance filing and reh’g, 104 FERC ¶ 61,142 (2003), order on reh’g, 105 FERC ¶ 61,348 (2003).27 See Old Dominion Electric Cooperative v. FERC, et al., 898 F.3d 1254, 1255 (D.C. Cir. 2018) (reversing a FERC cost allocation decision finding that it “involves a wholesale departure from the cost-causation principle.”).28 Id.29 Id. at 1263.30 Atlantic City Electric Co., et al., 190 FERC ¶ 61,109 (2025).
PDF page 13
13
the just and reasonable standard. The Show Cause Order emphasizes that the “record demonstrates that different co-location arrangements are likely to use or benefit from the transmission system in different ways depending on how they are configured and, moreover, that those different configurations will themselves likely have different impacts on the transmission system.”31 This is the heart of the Commission’s concerns in the Show Cause Order.
In moving forward, the Commission must continue to be guided by and apply the above-articulated cost causation principles. Specifically, to the extent that co-located customers cause transmission owners to incur costs to serve these customers, the customers should pay for such services. But cost responsibility must match actual cost incurrence. If, for example, a particular co-located arrangement uses the grid as a back-up source, then the co-load customers should pay for that type of usage.
An approach that aligns with cost causation principles is one that treats all co- located customers as NITS customers with netting rules applied. Indeed, this is the current construct for BTMG customers under the PJM Tariff. Customers all across the PJM system, such as universities, hospitals, refineries, rooftop solar, are allowed to net BTMG out of their transmission charges reflecting the fact that when they are generating behind the meter, they are not using the system.32 There is no reason to treat behind the meter load any differently than BTMG. As discussed below, from an engineering and physics perspective, there is no difference between behind the meter load and BTMG. Courts and Commission precedents teach that that it is unduly discriminatory and
31 Order at P 76.32 Section 34.2 of the PJM Tariff states: “The daily load of a Network Customer does not include load served by operating Behind the Meter Generation.”
PDF page 14
14
unlawful to treat similarly-situated parties differently.33 The Commission should ensure that there is no undue discrimination in the treatment of co-located arrangements.
B. The Commission Should Recognize That There Are Many Customers
With BTMG And Any Remedy or Replacement Rate Adopted In This
Proceeding Must Not Adversely Impact Those Customers34
In the Show Cause Order, the Commission recognized that there are a number of customers in PJM that have BTMG, and asked the parties to “address how co-located loads are similar to or disparate from other types of arrangements where load and generation share the same point of interconnection (such as Behind the Meter Generation as defined in the PJM Tariff or non-retail behind the meter generation) and should consider how any proposed replacement rate would affect the existing arrangements.”35 Co-located loads are very similar to load and generation that share the same point of interconnection, such as large load customers with BTMG. In fact, they use or impact the transmission in the same way. Figure 1 sets forth a side-by-side comparison of the physical configuration of a co-located load at a generator site and a behind the meter generation co-located at the customer’s (load) site.
33 See, e.g., New England Power Generators Ass’n v. FERC, 881, F.3d 202, 210 (D.C. Cir. 2018) (remanding to FERC a decision that treated new generation capacity market entrants differently from existing capacity due to a lack of reasoned explanation departing from its past precedent); Energy Partners, L.P., 120 FERC ¶ 61,086 at P 169 (2007) (there is undue discrimination when two classes of customers are treated differently and the two classes of customers are similarly- situated); PacifiCorp Elec. Operations, 54 FERC ¶ 61,296 at 61,855 (“undue discrimination can only occur when two similarly situated customers are treated differently and there is no justification for the differing treatment.”).34 This section III.B responds to Show Cause Order, P 88, Section a., Question iv.35 Id.
PDF page 15
15
Figure 1: Co-located load at a generator site and Behind-the-Meter at a Customer (Load) site have the same impact on the transmission system.
Specifically, the left illustration in Figure 1 shows a 5 MW load that is co-located at an existing 10 MW generator behind the generator meter. In this scenario, there is a net power flow to the grid of 5 MW. The right illustration in Figure 2 is a depiction of a 10 MW load that has 5 MW behind the meter generation; there is a net power flow of 5 MW from the grid to the load. Importantly, in either scenario, there is a reduced power flow on the transmission system of 5 MW. From a technical perspective, there is no material distinction between a BTM load arrangement relative to a BTMG arrangement. Both arrangements result in the reduced use or burden of the transmission system (thereby minimizing transmission upgrades) that the Commission has recognized as beneficial to all customers. Co-located load is not using or impacting the transmission system any differently than other BTMG customers. Both classes of customers employ similar co- location configurations and should pay for transmission services based on their actual system usage (i.e., based on net use of the transmission system).
PDF page 16
16
In his opening remarks during the November 1, 2024 Technical Conference, Commissioner Rosner observed that there are obvious benefits with co-locating large loads with generation, noting that such arrangement would reduce system costs. He also stated that the “physics” of co-location load arrangements with BTMG arrangements are identical:
[T]he potential benefits of co-locating large loads with generation are pretty obvious. There’s nothing new about this concept. It’s been
happening for many years. You know, siting generation near load
reduce system costs, that’s kind of logical. And what’s happening
here is the inverse we’re siting load near generation, and the physics are kind of – they kind of work the same.36
To expand upon Commissioner’s Rosner’s observation that co-location is nothing new, the co-location construct has been part of the PJM Tariff for over twenty years – since 2004.37 The PJM Tariff defines BTMG as:
“Behind the Meter Generation” shall refer to a generation unit that delivers energy to load without using the Transmission System or any distribution facilities (unless the entity that owns or leases the distribution facilities has consented to such use of the distribution facilities and such consent has been demonstrated to the satisfaction of the Office of Interconnection).38 To reflect that there is no use of the transmission system by BTMG arrangements and that customers do not need to pay transmission charges for the load served by BTMG
36 November 1 Technical Conference Transcript at 14 (emphasis added). 37 See PJM Interconnection, L.L.C., 107 FERC ¶ 61,113 at P 3 (2004) (“2004 BTMG Order”), reh’g denied, 108 FERC ¶ 61,302 (2004) (approving PJM’s behind the meter tariff provisions as just and reasonable and not unduly discriminatory, and finding that no transmission or distribution facilities are used to deliver energy from the generating unit to the load.).38 PJM Tariff, Definition of “Behind the Meter Generation.” (emphasis added). The PJM Operating Agreement and Reliability Agreement contain the same “Behind the Meter Generation” term. See also PJM Manual 14G, Section 1.6 (explaining that Behind the Meter Generation “must deliver energy to load without using the Transmission System.”).
PDF page 17
17
arrangements (either in whole or in part), the PJM Tariff expressly states that the load of a network customer “does not include the load served by operating Behind the Meter Generation.”39 The key characteristic of a BTMG configuration is that it provides for the delivery of power from the generator to the co-located load “without using the Transmission System.”40
In 2004, when the Commission approved PJM’s tariff revisions to implement the BTMG rules, the Commission recognized the benefits of co-location, stating that the BTMG tariff provisions would “encourage qualifying entities with behind the meter generation to reduce their use of the PJM transmission system.”41 As the Commission held, PJM’s BTMG provisions would allocate costs based on the market participant’s “actual use of PJM’s system . . . ” and that this is “consistent with the principle of cost causation.”42
Since 2004, many PSE&G customers have relied upon these netting provisions in the PJM Tariff to reduce their actual use of the PJM’s system to the benefit of customers throughout PJM. These customers use BTMG resources such as solar, reciprocating engine, and gas turbine generation facilities. In New Jersey alone, there are over 200,000 BTMG solar installations, 90,000 of which are located on PSE&G’s system.43 These customers are able to offset their peak load with behind-the-meter solar systems. Indeed,
39 See Section 34.2 of the PJM Tariff (emphasis added).40 Id.41 2004 BTMG Order at P 27 (emphasis added).42 Id. at PP 2, 28 (finding that PJM’s meter generation tariff revisions would benefit “customers by allowing PJM to more appropriately allocate the operating costs of its transmission system.”).43 See https://njcleanenergy.com/renewable-energy/project-activity-reports/project-activity-reports.
PDF page 18
18
homeowners with solar panels are often able to fully offset their electricity usage during peak demand times, therefore eliminating any charge for transmission service. In addition, PSE&G has a number of large customers who rely on BTMG,
including universities like Rutgers, the State University of New Jersey (“Rutgers”), government agencies like the Bergen County Utilities Authority (“BCUA”), manufacturers, real estate companies and pharmaceutical companies. Exhibit 1 to this Response shows that a number of customers on the PSE&G system will experience significant cost increases if the Commission were to adopt gross load pricing. For instance, large university systems in PJM have installed onsite generation to help to meet campus needs for electricity.44 With multiple campuses located on PSE&G’s system, Rutgers owns and operates a number of onsite generating facilities.45 Charging transmission based on a gross load approach would have broad application and adverse impacts on entities like Rutgers and on the customers of QFs across the PJM footprint, and would disrupt the settled expectations of these entities that they need not take transmission service when relying on their on-site generation resources. Accordingly, any replacement rate that the Commission may adopt must not adversely impact existing customers with BTMG and their ability to net and reduce the use of the transmission system.
44 The University of Maryland installed a natural gas-turbine in 1999 to serve its campus load. https://today.umd.edu/new-generation-campus-energy-production-62a512c9-aa8b-4567-ae7c- 5d39051d73b1.45 With the assistance of the New Jersey Board of Public Utilities, Rutgers began construction of a solar energy facility in 2008 to serve a portion of the needs of one of its campuses. https://www.rutgers.edu/news/rutgers-university-breaks-ground-largest-campus-solar-energy- facility-nation. Rutgers more recently contracted in 2023 to have solar canopies installed on parking lots at 17 locations that would meet a portion of its power needs, meeting sustainability objectives and allowing it to capture purchased power cost savings.
PDF page 19
19
C. Co-Located Load Arrangements Are Viable Options For The
Development Of Data Centers And Should be Encouraged46
The Commission and the states have recognized the vital importance for data center development and its importance to the economy and national security. For example, former Chairman (now Commissioner) Phillips has stressed the importance of having “regulatory flexibility” for data centers to “maintaining U.S. leadership in Artificial Intelligence” and “maintaining our national security.”47 He expressed the concern that data centers, artificial intelligence and other information related technologies may be “moving overseas due to lack of power supply and infrastructure, or regulatory barriers, which raise national security concerns for our nation.”
So let me put my cards on the table. In my opinion, data centers, artificial intelligence, indeed the full panoply of information related-technologies that are transforming the world are national resources, with generational significance, and vast national security and national economic
consequences. They belong in the United States, and I believe the federal government, including this agency, should be doing very best they can to nurture and foster their development.48
He emphasized that “FERC can and should play a leadership role” in moving forward with a “positive national initiative.”49 Other FERC Commissioners have similarly expressed support for this sentiment.5046 This section addresses Show Cause Order, P 88, Section (e), Question (vi).47 See PJM Interconnection, L.L.C., 189 FERC ¶ 61,078 (2024), Phillips, Chairman, dissenting statement at P 3.48 Large Loads Co-Located at Generating Facilities, Docket No. AD24-11, November 1, 2024 Technical Conference, Tr. at 8 (emphasis added).49 Id. at 9.50 See, e.g., November 1 Technical Conference, Tr. at 16-17 (Commissioner See stating “Data centers and the promise of AI as critical for our economy, and for matters of national security, and I share an eagerness to find new ways to accommodate these important and increasing loads, and I understand the urgency of the issues in front of us.”); November 1 Technical Conference, Tr. at 19
PDF page 20
20
At the state level, New Jersey has taken steps to attract data centers to the state. In 2024, New Jersey adopted the “Next New Jersey Program” that will provide tax credits to eligible businesses engaged in artificial intelligence work or large-scale artificial data centers. This program is designed to attract new investment into the state’s artificial intelligence industry and recognizes that “AI will be a transformative industry that will change lives and grow our economy and New Jersey is ready to take the lead.”51 In recognition of the importance of data center for economic development and national security issues, the Commission should expeditiously take action in this proceeding to provide much needed clarity and certainty as to the “rules of the road” for co-located load arrangements. In so doing, the Commission should maintain optionality so that customers have the ability to select the best configuration for their particular circumstances and needs. In particular, the Commission should continue to keep in mind of the significant benefits that co-location arrangements provide, including the importance of providing the proper pricing incentives to encourage entities to reduce their usage of the transmission system. This means allocating costs based on the co-located load’s actual use of the transmission system.
(Commissioner Chang stating “the U.S. is leading the world in data science and artificial intelligence. Our role in the energy industry is to support that development in the United States.”).
51 See Governor Murphy signs Legislation to Spur Investment in New Jersey’s AI Sector, https://www.nj.gov/governor/news/news/562024/20240725a.shtml.
PDF page 21
21
IV. CONCLUSION
WHEREFORE, for the reasons discussed herein, the Commission should
expeditiously issue an order that provides timely and needed clarity with respect to co- located load rules and that leads to a result that is (i) consistent with cost causation principles; (ii) avoids adversely impacting existing BTMG customers in PJM; and (iii) preserves co-location as a viable option to support data center development.
Jodi L. Moskowitz
Vice President, Regulatory,
Deputy General Counsel and
RTO Strategy Officer
PSEG Services Corp.
80 Park Plaza, T-20
Newark, NJ 07102
(973) 430-6409
Jodi.Moskowitz@pseg.com
/s/ Viet H. Ngo
Viet H. Ngo
Associate Counsel – Federal Regulatory
PSEG Services Corporation
601 New Jersey Ave, NW Suite 310
Washington, DC 20001
(202) 460-9356
Viet.Ngo@pseg.com
PDF page 22
Exhibit 1
Illustration of Adverse Customer Impacts
Associated with a Gross Load Approach
PDF page 23
23
To the extent that BTMG customers are assessed on a gross load basis, this will in significant adverse impacts on customers on the PSE&G system who have BTMG resources and who have been relying upon the netting provisions under the PJM Tariff for many years.
Examples are provided below. Note that (i) this is not an exhaustive list of all of PSE&G’s BTMG customers; (ii) certain PSE&G BTMG customers have asked for anonymity in the context of disclosing their customer data; and (ii) PSEG would expect the same types of impacts would be experienced by BTMG customers throughout the PJM footprint.
Example 1: Rutgers has 3 gas turbine generators totaling 15 MW (nameplate capacity)52 at its Rutgers Biomedical and Health Sciences (“RBHS”) site, and three gas turbine generators totaling 17 MW (nameplate capacity) at its Busch/Livingston Campuses. The overall annual impact of a gross load approach for both locations is approximately $4.1M.
Rutgers – RBHS
Net Load
Gross Load
Change
Load
MW
16.5
26
9.5
Cost
$
$2,889,648
$4,561,024
$1,671,376
Rutgers–
Busch/Livingston
Campuses
Net Load
Gross Load
Change
Load
MW
20.46
34.51
14.05
Cost
$
$3,589,060
$6,053,943
$2,464,883
Example 2: Large Customer #1 with 3 gas turbine generators totaling 19 MW (nameplate capacity) at two locations is estimated to experience an annual increase of $3.4M.
Large Customer #1
Location 1
Net Load
Gross Load
Change
Load
MW
5.0
14.9
9.9
Cost
$
$877,230
$2,617,436
$1,740,206
Large Customer #1
Location 2
Net Load
Gross Load
Change
Load
MW
1.2
10.6
9.4
Cost
$
$203,495
$1,852,481
$1,648,986
Example 3: Large Customer #2 has a 10 MW gas turbine generator (nameplate capacity) and is expected to experience an approximately $934K annual increase.
52 For the customers in Exhibit 1, the nameplate value of the BTMG differs from the value that is used to net against gross load (which is based on the output of the BTMG resource coincident with the relevant peak hours on PSE&G’s system).
PDF page 24
24
Large Customer #2
Net Load
Gross Load
Change
Load
MW
0.12
5.44
5.32
Cost
$
$20,269
$953,875
$933,607
Example 4: The College of New Jersey (“TCNJ”) with a 5.2 MW solar turbine dual fuel natural gas and oil generator would experience an estimated annual increase of $733k.
TCNJ
Net Load
Gross Load
Change
Load
MW
5.14
9.32
4.18
Cost
$
$901,755
$1,634,326
$732,571
Example 5: Large Customer #3 with a solar facility of 17 MW (nameplate) would be experience an increase of $2 million annually.
Large Customer #3
Net Load
Gross Load
Change
Load
MW
3.47
14.69
11.22
Cost
$
$609,361
$2,576,756
$1,967,395
Example 6: Large Customer #4 with a 10 MW gas turbine generator would experience an estimated annual increase of $2M:
Large Customer #4
Net Load
Gross Load
Change
Load
MW
2.22
13.41
11.19
Cost
$
$389,608
$2,351,884
$1,962,275
Example 7: Essex County Correctional Facility with two engines totaling 6 MW (nameplate) would experience an estimated annual impact of $594k:
Essex County
Net Load
Gross Load
Change
Load
MW
0.001
3.385
3.384
Cost
$
$175
$593,810
$593,635
PDF page 25
25
Example 8: Large Customer #5 with a 4 MW gas turbine generator would have an estimated annual increase of $515k.
Large Customer #5
Net Load
Gross Load
Change
Load
MW
0.01
2.94
2.93
Cost
$
$1,054
$515,854
$514,800
Example 9: Bergen County Utilities Authority (BCUA) with a gas turbine generator of 2.69 MW (nameplate) would experience an estimated annual increase of $472k.
BCUA
Net Load
Gross Load
Change
Load
MW
3.48
6.47
2.69
Cost
$
$610,455
$1,135,730
$471,891
Example 10: Large Customer #6 with a 15 MW generator and a 16 MW solar facility, and would experience an estimated annual increase of $4.3 million (an increase of over 700%):
Large Customer #6
Net Load
Gross Load
Change
Load
MW
3.28
27.59
24.31
Cost
$
$575,739
$4,839,419
$4,263,680
PDF page 26
CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person designated on the official service list compiled by the Secretary in the proceeding. Dated at Newark, New Jersey this 24th day of March, 2025.
/s/ Robert Gardinor
Robert Gardinor