Response of Public Service Electric and Gas Company to Show Cause Order issued on 02/20/2025
Text extracted from the eLibrary original (SHA-256 03849587ef1a1cfe…). Download the original from the official source.
Contents · 9 sections
Read topic-matched comments in EL25-49
Topics in the text: Cost allocation · Connecting load and generation
Source sections
Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.
Opening text
opening text · Topic match: Cost allocation
PSE&G submits this Response to the Commission’s February 20, 2025 Order Instituting Proceeding under Section 206 of the Federal Power Act and Consolidating with Other Proceedings (the “Show Cause Order”).1 In our Response,2 PSE&G proposes a principle-based approach to address the Commission’s…Read this passage Filed comments: Cost allocation
I. EXECUTIVE SUMMARY
printed heading · Topic match: Cost allocation
To comply with cost causation principles, which courts have described as adding “flesh to the bare statutory bones of the just and reasonable requirement” under the Federal Power Act,8 any charges imposed must reflect the use or benefit of the specific co-located load arrangement.Read this passage Filed comments: Cost allocation
II. BACKGROUND
printed heading
II.Read this passage
A. Description of PSE&G
printed heading
Description of PSE&G PSE&G is a regulated electric and gas utility and owns 1,600 circuit miles of electric transmission lines within the PJM region.Read this passage
B. The Show Cause Order
printed heading · Topic match: Connecting load and generation
See also Show Cause Order at P 3 (adopting PJM’s definition of co-located load “as a configuration through which end-use customer load is physically connected to the facilities of an existing or planned generation unit.” 14 Show Cause Order at P 76. 15 Show Cause Order at P 74 (emphasis added).Read this passage Filed comments: Connecting load and generation
III. RESPONSE
printed heading
III.Read this passage
A. The Commission Recognizes The Variety of Co-Located
printed heading · Topic match: Cost allocation
In moving forward, the Commission must continue to be guided by and apply the above-articulated cost causation principles.Read this passage Filed comments: Cost allocation
B. The Commission Should Recognize That There Are Many Customers
printed heading · Topic match: Connecting load and generation
Accordingly, any replacement rate that the Commission may adopt must not adversely impact existing customers with BTMG and their ability to net and reduce the use of the transmission system. 44 The University of Maryland installed a natural gas-turbine in 1999 to serve its campus load.…Read this passage Filed comments: Connecting load and generation
C. Co-Located Load Arrangements Are Viable Options For The
printed heading · Topic match: Connecting load and generation
Co-Located Load Arrangements Are Viable Options For The Development Of Data Centers And Should be Encouraged46 The Commission and the states have recognized the vital importance for data center development and its importance to the economy and national security.Read this passage Filed comments: Connecting load and generation
IV. CONCLUSION
printed heading · Topic match: Cost allocation
CONCLUSION WHEREFORE, for the reasons discussed herein, the Commission should expeditiously issue an order that provides timely and needed clarity with respect to co- located load rules and that leads to a result that is (i) consistent with cost causation principles; (ii) avoids adversely impacting…Read this passage Filed comments: Cost allocation
CERTIFICATE OF SERVICE
printed heading
Dated at Newark, New Jersey this 24th day of March, 2025. /s/ Robert Gardinor Robert GardinorRead this passage