EL25-49-000 · 2025-03-24 · PJM Interconnection, L.L.C.

Answer of PJM Interconnection, L.L.C. to the 02/20/2025 Order Instituting Proceeding Under Section 206 of the Federal Power Act and Consolidating with Other…

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION

PJM Interconnection, L.L.C.
Allegheny Electric Cooperative, Inc. American Transmission Systems,

Incorporated
Atlantic City Electric Company
Baltimore Gas and Electric Company Delmarva Power & Light Company

Duke Energy Ohio, Inc.
Duke Energy Kentucky, Inc.
East Kentucky Power Cooperative, Inc. Essential Power Rock Springs, LLC Hudson Transmission Partners, LLC Jersey Central Power & Light Company Mid-Atlantic Interstate Transmission, LLC Neptune Regional Transmission System, LLC

Old Dominion Electric Cooperative PECO Energy Company

PPL Electric Utilities Corporation Potomac Electric Power Company

Public Service Electric and Gas Company Rockland Electric Company

Trans-Allegheny Interstate Line Company Transource West Virginia, LLC

UGI Utilities, Inc.
Monongahela Power Company
The Potomac Edison Company
Commonwealth Edison Company
Commonwealth Edison Company of
Indiana, Inc.
The Dayton Power and Light Company AEP Appalachian Transmission Company, Inc.

AEP Indiana Michigan Transmission Company, Inc. AEP Kentucky

Transmission Company, Inc.
AEP Ohio Transmission Company, Inc. AEP West Virginia Transmission

Company, Inc. Appalachian Power
Company
Indiana Michigan Power Company
Kentucky Power Company
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
Docket Nos. EL25-49-000

PDF page 2

2
Kingsport Power Company
Ohio Power Company
Wheeling Power Company
Duquesne Light Company
Virginia Electric and Power Company
Linden VFT, LLC
City of Cleveland, Department of Public
Utilities, Division of Cleveland Public
Power
City of Hamilton, OH
Southern Maryland Electric Cooperative,
Inc.
Ohio Valley Electric Corporation
AMP Transmission, LLC
Silver Run Electric, LLC
NextEra Energy Transmission MidAtlantic
Indiana, Inc.
Wabash Valley Power Association, Inc.
Keystone Appalachian Transmission
Company
Large Loads Co-Located at Generating
Facilities
Constellation Energy Generation, LLC
v. PJM Interconnection, L.L.C.
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)
)

AD24-11-000

EL25-20-000
(Consolidated)

ANSWER OF PJM INTERCONNECTION, L.L.C.
Pursuant to Rule 213 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (“Commission”),1 PJM Interconnection, L.L.C. (“PJM”) submits this answer to the Order Instituting Proceeding Under Section 206 of the Federal Power

1 18 C.F.R § 385.213.

PDF page 3

3
Act and Consolidating with Other Proceedings2 issued in the above-captioned proceeding on February 20, 2025.

I. INTRODUCTION
PJM remains committed to supporting its member companies, the states, and the
Commission in the industry’s efforts to integrate large loads, including data centers (“large loads”), including through co-locating with generation (“co-location arrangements”). PJM’s approach to large load expansion—co-located or not—focuses on:

(1) maintaining resource adequacy; (2) enabling reliable system operations; (3) facilitating the states’ and stakeholders’ efforts to timely and effectively integrate large loads in a manner that meets their unique needs; and (4) providing information and analysis that supports the equitable alignment of transmission system usage and compensation.3 Substantial progress can be made in these efforts by leveraging the tools in the existing Tariff4 and exploring with the Commission and stakeholders other potential innovative market solutions, where allowed by state laws, that may specifically define and limit when and how load in a jurisdiction can be served by a supplier other than a franchised public utility.  This means that some existing state regulatory environments may permit certain co-location load arrangements while other existing state regulatory environments may not. Given the novelty and nascence of the issues presented in this proceeding, many of the

2 PJM Interconnection, L.L.C., Order Instituting Proceeding Under Section 206 of the Federal Power Act and Consolidating with Other Proceedings, Docket Nos. EL25-49-000, et al. (Feb. 20, 2025) (“Order”).
3 This is a role reserved to the PJM Transmission Owners for purposes of Network Integration Transmission Service cost allocation.  See Linden VFT, LLC, 161 FERC ¶ 61,264, at P 31 n.44 (2017) (“Although PJM implements the cost allocation provisions of Schedule 12 of the Tariff, the cost allocation method is determined by the PJM Transmission Owners, and it is the PJM Transmission Owners, not PJM, that have the section 205 filing rights for the PJM cost allocation method.” (citing Atl. City Elec. Co. v. FERC, 295 F.3d 1 (D.C. Cir. 2002)).
4 The Order defines Tariff as including the PJM Open Access Transmission Tariff, the Amended and Restated Operating Agreement of PJM (“Operating Agreement”), and the Reliability Assurance Agreement Among Load Serving Entities in the PJM Region (“RAA”).

PDF page 4

4
concepts PJM presents require additional effort to identify and develop Tariff and manual provisions necessary for implementation.

Regardless of what co-location arrangements are ultimately sanctioned by the Commission, permitted by the states, and elected by developers, participants involved in co-location arrangements should pay the costs of any grid services they consume and the arrangements must be reliable and operationally manageable.  As noted in Exhibit A and herein, many co-located load configurations utilize grid support and consume ancillary services (including, for example, frequency regulation, black start service, and reactive service).

PJM continues to work closely with the states and its members to realize the prompt development of substantial new infrastructure, most especially significant electric generation that at least matches if not exceeds load growth forecasts.  This infrastructure should be promptly studied, sited, and constructed to facilitate the projected significant load growth.

What PJM and the industry need now is Commission guidance on a path forward based on the record developed in this proceeding.  The record will support a finding that PJM’s existing Tariff remains just and reasonable, although improvements and clarifications may be appropriate based on Commission guidance.  Multiple existing pathways are available to facilitate co-location arrangements.  Some potential additional pathways are also proposed in this filing.  Given that this is an evolving area, if the Commission believes that the record supports consideration of additional options beyond those that already exist, PJM requests that the Commission issue detailed guiding principles such as those PJM proposes in this filing that PJM can promptly operationalize in a section 205 filing.  Although stakeholder input is critical, the Commission could also issue a

PDF page 5

5
compliance directive under its section 206 authority to set a clear deadline for future filings given the important national interests implicated.  The Commission’s continued leadership will assist the industry in obtaining certainty and clarity about the available pathways for integration of large loads consistent with the principles set forth herein.

II. EXECUTIVE SUMMARY OF EXISTING AND POTENTIAL NEW
OPTIONS TO FACILITATE CO-LOCATION ARRANGEMENTS
At least eight potential options for additional large load co-location (as well as large load integration in general) are summarized in a chart attached as Exhibit A.   This exhibit lays out the key attributes and impacts of each configuration and service option on  load characteristics, services consumed, studies required, rates, operations, and resource adequacy impacts.  Three of the options already exist under PJM’s Tariff.  The other five are potential options that have been proposed by others or developed by PJM in response to issues raised in the various predecessor co-located load proceedings.

To be clear, PJM does not mean to suggest that all identified “options” in Exhibit A are equivalent, desirable, or even necessarily workable.  For example, state laws may specifically limit when and how load in a jurisdiction can be served by a supplier other than a franchised public utility.  Further, identified options are not mutually exclusive, as it is possible several of the options may be used seriatim or concurrently. Each new option outlined herein is conceptual and would benefit from continued input from stakeholders, Commission guidance, and a deadline for submission of any such proposals either in the context of a section 205 filing or in this docket.

Before describing the options, a few points warrant emphasis.  First, as noted above, the availability of various options is dependent on state law.  States may specifically define and limit when and how load in a jurisdiction can be served by a supplier other than a

PDF page 6

6
franchised public utility.  This is a significant point that is explored in greater detail below in response to the Commission’s question A.i about federal and state jurisdiction.  At bottom, a state’s exclusive retail franchise territory law may restrict non-franchised suppliers from serving co-located load.  Further, in deregulated states, state law may (or may not) today (or in the future) require co-located load suppliers to be licensed energy providers and/or otherwise impose limitations on such suppliers by, for example, obliging the designation of the load as Network Load, with or without netting, or the taking of certain types of transmission service that could compel the designation of co-located load as Network Load.

Second, large co-located loads that connect as Network Load realize significant benefits (as discussed in greater detail in response to question B.iii, below).  Six of the eight options PJM outlines (Options 1, 2, 3, 6, 7, and 8) are premised on large co-located load being Network Load.  The remaining two configurations (Options 4 and 5) provide that the load may still be Network Load if designated as such by the customer (whether or not required by state law), but it does not have to be Network Load.  Importantly, where Network Load is designated and coming onto the system, even where necessary transmission upgrades are not yet in service, PJM operations will endeavor to implement interim operating procedures to serve the Network Load in real time because there is an obligation to serve it.

Third, an introductory note about study-related terminology used throughout this submission.  Co-located load arrangements implicate a variety of different but interrelated study frameworks and cost allocation constructs that PJM will describe here in an effort to avoid repetition throughout and promote clarity about terminology used in Exhibit A.  First, traditional Transmission Owner/Load Serving Entity (“LSE”)/Electric Distribution

PDF page 7

7
Company (“EDC”) load interconnection processes (“traditional load interconnection processes”) to add Network Load are generally commenced by performing what PJM will call a “Transmission Owner retail load integration study” to identify local upgrades needed to reliably accommodate the load based on local transmission owner planning criteria.  The results of this study identify local system needs that are presented at the Transmission Expansion Advisory Committee (“TEAC”).  Solutions to these needs typically take the form of Supplemental Projects (following Tariff, Attachment M-3) and are also generally presented at the TEAC.

PJM then performs a “PJM Do No Harm study” to evaluate whether a proposed Supplemental Project will adversely impact the reliability of the Transmission System as represented in the planning models used in other PJM reliability planning studies.  If as a result of the do no harm study, system upgrades are found to be required, such upgrades will be considered part of the Supplemental Project and are the responsibility of the Transmission Owner sponsoring the Supplemental Project.  Supplemental Projects are cost allocated to the local Transmission Owner’s zone pursuant to individual Transmission Owner cost allocation frameworks.

Necessary studies (for additional information, see PJM’s response to question D.i, infra) are essentially generator interconnection modification studies.  Such studies are only performed when a generator is involved, and a party to the interconnection services agreement is proposing to change the interconnection.  Transmission Owners review PJM’s necessary study analysis, and transmission owners may verify that analysis and/or perform additional transmission owner analysis pursuant to their processes or requirements. An aggregation of large load additions could trigger regional (as opposed to local) transmission system needs, which would be identified as part of the Regional

PDF page 8

8
Transmission Expansion Planning (“RTEP”) process in Schedule 6 of the Operating Agreement.  The load that could rise to regional RTEP needs is determined during the annual load forecasting process, when PJM makes a request to the EDCs/Load Serving Entities (“LSEs”) to submit large load additions that would not be captured in the parameters that are typically incorporated.  PJM presents what is ultimately accepted into the Load Forecast for the subsequent year.  PJM then plans its transmission system in light of this load forecast, and RTEP upgrades are identified and ultimately cost allocated pursuant to existing RTEP-specific methodologies.

Before moving off the topic of studies, it is important to re-emphasize that  any configuration where the co-located load is Network Load (Options 2, 3, 7, and 8, and in some circumstances Options 4 and 5) is limited in scope to generator interconnection modifications.  As described above, Transmission Owner retail load integration studies would be performed in addition to necessary studies.  While stakeholder (including the Organization of PJM States, Inc.) and Commission comments and questions probe the sufficiency of the necessary study agreement/study process for load integrations, only two of the proposed options (Options 4 and 5 if load is not designated as Network Load) involve the use of a necessary study without any form of a load interconnection study.  To the extent the Commission sanctions further exploration of Options 4 and 5 and the market is interested in pursuing such options, PJM will explore opportunities to enhance the visibility of the necessary study process and results for interested stakeholders. Fourth, as to the resource adequacy dimension to co-location arrangements where conditions are tight, any additional load on the system requires either the addition of supply resources to serve that load reliably, or flexibility on the part of the load to curtail its consumption from the transmission system when necessary to maintain reliability.  For this

PDF page 9

9
reason,  PJM has outlined three potential options relating to adding additional supply and operational flexibility:  Option 6 (co-located load that elects to be Network Load and leverages provisional interconnection service or State Agreement Approach), Option 7 (co- located load that takes a new non-capacity backed service that could be curtailed in advance of emergency procedures), and Option 8 (co-located participates as Demand Response). And as discussed below, see infra question F.2, PJM is also exploring with regulators and generators opportunities to leverage at least 50 hours (or more) of diesel back-up generator service to enhance the available demand response portfolio.  And even where shorter term resource adequately may not be directly enhanced by a particular co-location arrangement (for example, where new load is not accompanied by additional generation or operational flexibility), longer term resource adequacy interests are certainly indirectly supported by any resulting increased prices from such scenarios.

The options outlined in Exhibit A are briefly summarized as follows:
Options Already Existing in PJM’s Tariff
Option 1: Load with a separate Point of Interconnection that is Network Load

Existing Option 1
*note:  each option is subject to state laws that may
specifically define and limit when and how load in a
jurisdiction can be served by a supplier other than a
franchised public utility
Load with a separate Point of Interconnection (POI) that is Network Load
(Existing NITS rules)
Description
This option is where the load is network load and generation is a capacity resource and they are not electrically co-located.  The load and generation may be physically located at the same location but they are electrically connected to the grid separately.

PJM Preference
Yes - Highest Reliability
Load Status
Network
Generation Capacity Status
Yes
PJM obligation to serve
Yes
Load System Used and Charged
NITS (Full load during coincident peak); Energy; Capacity (Full load during coincident peak) Ancillary Services Used

Reactive, Black Start, Regulation, Sync, Non Sync, Day-ahead Scheduling Reserves

PDF page 10

10
Ancillary Services Charged
Reactive, Black Start, Regulation, Sync, Non Sync, Day-ahead Scheduling Reserves (based on entire load)

Generation Revenue
• Capacity (based on full CIRs)
• Energy and Ancillary Services (based on entire gen output)
Studies
• TO Load Integration study
•PJM Do No Harm study
•RTEP process inclusive of Load Forecast
Load included in Load Forecast (RTEP) Yes
Load included in RPM Reliability
Requirement
Yes
Cost Allocation for Interconnection
Upgrades
• Supplemental projects pursuant to local TO methodology
• RTEP upgrades pursuant to RTEP cost allocation
• No modification to generation.
System Protection Requirements
N/A
Demand Response Eligibility
Yes
Tariff Modifications
No

Option 1 contemplates load becoming traditional Network Load that takes Network Integration Transmission Service (“NITS”) in accordance with traditional load interconnection processes.  Under this existing option, the load has a separate Point of Interconnection with the grid even if physically at the same site.  Because the load is taking NITS, the load and generator do not have to be sited at the same location because the load and the generation are electrically connected to the grid separately with the load enjoying all the benefits of network integration.  For this option, the load uses and pays for NITS, Energy, Ancillary Services, and Capacity.

Option 2: Co-located load that is at the same Point of Interconnection but separately metered that is Network Load

Existing Option 2
*note:  each option is subject to state laws that may
specifically define and limit when and how load in a
jurisdiction can be served by a supplier other than a
franchised public utility
Co-located load that is at the same Point of Interconnection (POI) but separately metered that is Network Load

(Existing NITS rules)
Description
This option is where the load is network load and generation is a capacity resource and they are metered separately

PJM Preference
Yes - Highest Reliability
Load Status
Network

PDF page 11

11
Generation Capacity Status
Yes
PJM obligation to serve
Yes
Load System Used and Charged
NITS (Full load during coincident peak); Energy; Capacity (Full load during coincident peak) Ancillary Services Used

Reactive, Black Start, Regulation, Sync, Non Sync, Day-ahead Scheduling Reserves Ancillary Services Charged

Reactive, Black Start, Regulation, Sync, Non Sync, Day-ahead Scheduling Reserves (based on entire load)

Generation Revenue
• Capacity (based on full CIRs)
• Energy and Ancillary Services (based on entire gen output)
Studies
• TO Load Integration study
•PJM Do No Harm study
•RTEP process inclusive of Load Forecast
•Necessary Study
Load included in Load Forecast (RTEP) Yes
Load included in RPM Reliability
Requirement
Yes
Cost Allocation for Interconnection
Upgrades
• Supplemental projects pursuant to local TO methodology
• RTEP upgrades pursuant ot RTEP cost allocation
• Generator for the changes to its facility to accommodate the load
System Protection Requirements
N/A
Demand Response Eligibility
Yes
Tariff Modifications
No

Option 2 is a co-located configuration, in which the load and generation are, by agreement, behind the same Point of Interconnection.  However, in this configuration, the load is Network Load and the generation is a Capacity Resource.  Each is separately metered.  The load uses and pays for NITS, Energy, Ancillary Services, and Capacity. Additionally, the large load is studied and could be connected to the grid pursuant to the existing Transmission Owner/EDC load interconnection process.  For clarity, there is no change to the generator Capacity Interconnection Rights due to this co-located load configuration.

Option 3: Existing Behind the Meter Generation where the load is the customer

Existing Option 3
*note:  each option is subject to state laws that may
specifically define and limit when and how load in a
jurisdiction can be served by a supplier other than a
franchised public utility
Existing Behind The Meter Generation (BTMG) where the load is the customer Description

This option reflects PJM's existing BTMG rules where the load is primary customer and nets with BTMG. Reliability consideration:  Existing Non-Retail BTMG is annually capped because it does not carry reserves equal to the installed reserve margin (net is zero during coincident peak). Large load behind generation was not intended.

PDF page 12

12
PJM Preference
Not for Large Loads
Load Status
Network
Generation Capacity Status
No
PJM obligation to serve
Yes
Load System Used and Charged
NITS (Net withdrawal during coincident peak); Energy (Net withdrawal); Capacity (Net withdrawal during coincident peak)

Ancillary Services Used
Reactive, Black Start, Regulation, Sync, Non Sync, Day-ahead Scheduling Reserves Ancillary Services Charged

Reactive, Black Start, Regulation, Sync, Non Sync, Day-ahead Scheduling Reserves (Net withdrawal) Generation Revenue

• Capacity (For portion of CIRs retained)
• Energy and Ancillary Services (net injection only)
Studies
• TO Load Integration study
•PJM Do No Harm study
•RTEP process inclusive of Load Forecast
•Necessary Study
Load included in Load Forecast (RTEP) Only if Net Withdrawal >0 during coincident peak Load included in RPM Reliability

Requirement
Only if Net Withdrawal >0 during coincident peak
Cost Allocation for Interconnection
Upgrades
• Supplemental projects pursuant to local TO methodology
• RTEP upgrades pursuant ot RTEP cost allocation
• Generator for the changes to its facility to accommodate the load
System Protection Requirements
N/A
Demand Response Eligibility
Yes if net positive load
Tariff Modifications
No

Option 3 utilizes PJM’s existing Behind the Meter (“BTM”) Generation rules. These rules are explained further below in PJM’s response to question D.iv.  PJM’s BTM Generation rules would require the co-located load to be Network Load.  The rules charge load for its net use of the grid, after deducting BTM Generation.  This option is available in two configurations.  Either the load and generation are co-located at the same Point of Interconnection, or the load is served by municipal utilities or EDCs BTM through a distribution system, if the owner or lessee of such distribution system has consented (which is called “Non-Retail” BTM Generation).  The load uses and pays for NITS, Energy, Ancillary Services, and Capacity based on the net withdrawal quantity and dependent on if that withdrawal is during the Peak (NITS and Capacity).

PDF page 13

13
While this option is already available under the Tariff, it was conceived for, and
has been implemented for, substantially smaller loads (like a large warehouse with solar panels) and not on the scale of large data centers.5

New Potential Options

Option 4: Co-located load with connection to the grid with protections to avoid
delivery of system energy to serve the load

New Option 4
*note:  each option is subject to state laws that
may specifically define and limit when and how
load in a jurisdiction can be served by a supplier
other than a franchised public utility
Co-located load with connection to grid with protections to avoid delivery of system energy to serve the load

Description
This option is when the load is located behind the generation and there are protection mechanisms in place to prevent delivery of energy from the grid to serve the load in the event the generation is offline.

PJM Preference
Less preferred
Load Status
Not unless designated in a manner consistent with state law
Generation Capacity Status
Only for portion of Generation > Load
PJM obligation to serve
Not unless designated in a manner consistent with state law
Load System Used and Charged
If not designated Network Load, assuming no withdrawal of energy during coincident peak then no traditional NITS charges. However, system is still used to support co-location and delivery of ancillary services and should be part of a new rate design.

Ancillary Services Used
Reactive, Black Start, Regulation, Sync, Non Sync, Day-ahead Scheduling Reserves
Ancillary Services Charged
Yes
Generation Revenue
• Capacity (For portion of CIRs retained)
• Energy and Ancillary Services if injecting onto the PJM Grid
Studies
PJM Necessary Study
Load included in Load Forecast
(RTEP)
No for load; only retained CIRs are included in RTEP
Load included in RPM Reliability
Requirement
No for load; only retained CIRs are included in RTEP
Cost Allocation for Interconnection
Upgrades
Generator for the changes to its facility to accommodate the load.
Generator also responsible for any system upgrades to serve the load.
System Protection Requirements
Yes
Demand Response Eligibility
No
Tariff Modifications
Yes

5 The load in this configuration is not required to carry reserves and may lean on the PJM system when the co-located generation is on a full or partial outage or if the load exceeds the rating of the co-located generation.  Therefore, adding load to PJM without reserves will degrade reliability to worse than 1 in 10 (increase loss of load expectation (“LOLE”) to greater than 0.1 days/year).  PJM accommodates some level of this configuration through a settlement agreement in 2006 that allows the PJM LOLE to be relaxed from 1 in 10 years to 1 in 9.5 years.  This analysis is updated each year and, because of the potential reliability impacts of this option, use of this option has been capped at approximately 2000 megawatts (“MW”) of which about 1300 MW are already used.  There are also performance requirements for generation associated with this configuration.  Therefore, large load additions located behind generation are not ideal or contemplated under this existing configuration.

PDF page 14

14

In this option, where state law permits such a configuration, the load is located behind the Point of Change of Ownership between the Transmission Owner and generator, and system protection facilities are installed to prevent delivery of energy from the grid should the generator go offline.  In this configuration, load is not Network Load unless designated by the customer subject to applicable state law.

This configuration has been described as “fully” or “wholly” isolated by others, but this characterization is inconsistent with engineering and economic principles.  This configuration relies on and takes grid services (for example, ancillary services) and should pay its fair share of those charges.  Additionally, this configuration carries operational risk in that there is a dependency on the protection system to support reliability.  If the protection system should fail,6 the large load would instantly withdraw significant energy from the system.  While a few of these configurations may seem tolerable to some, the anticipation of large quantities of these configurations increases the risk.  Tariff modifications would be needed based on the Commission’s November 1, 2024 Order in Docket No. ER24-2172.7

Option 5: Co-located load with connection to the grid with protections to avoid delivery of system energy to load, but with back-up service from PJM with permission

New Option 5
*note:  each option is subject to state laws that
may specifically define and limit when and how
load in a jurisdiction can be served by a supplier
other than a franchised public utility
Co-located load with connection to grid with protections to avoid delivery of system energy to serve the load or receive back-up service from PJM with advanced authorization

6 System protection facilities are discouraged per PJM Manual 7.  System Planning Division, PJM Manual 07: PJM Protection Standards (May 30, 2019), https://www.pjm.com/- /media/DotCom/documents/manuals/m07.ashx. 7 PJM Interconnection, L.L.C., Order Rejecting Amendments to Interconnection Service Agreement, Docket Nos. ER24-2172-000, et al. (Nov. 1, 2024).

PDF page 15

15
Description
This option is when the load is located behind the generation and there is protection mechanisms in place to prevent delivery of energy from the grid to serve the load in the event the generation is offline. It also allows for back-up service from the PJM system with permission. PJM Preference

Less preferred
Load Status
Not unless designated in a manner consistent with state law
Generation Capacity Status
Only for portion of Generation > Load
PJM obligation to serve
Not unless designated in a manner consistent with state law
Load System Used and Charged
If not designated Network Load, assuming no withdrawal of energy during coincident peak then no traditional NITS charges. However, network is still used to support co-location and delivery of ancillary services and should be part of a new rate design

Ancillary Services Used
Reactive, Black Start, Regulation, Sync, Non Sync, Day-ahead Scheduling Reserves Ancillary Services Charged

Reactive, Black Start, Regulation, Sync, Non Sync, Day-ahead Scheduling Reserves (based on entire load)

Generation Revenue
• Capacity (For portion of CIRs retained)
• Energy and Ancillary Services if injecting onto the PJM Grid
Studies
PJM Necessary Study, reduced generator CIRs studied in RTEP
Load included in Load Forecast
(RTEP)
• Load - Only if Net Withdrawal >0 during coincident peak.
• Only CIRs retained included in RTEP.
Load included in RPM Reliability
Requirement
• Load - Only if Net Withdrawal >0 during coincident peak
• Only CIRs retained included in RPM
Cost Allocation for Interconnection
Upgrades
Generator for the changes to its facility to accommodate the load.
Generator also responsible for any system upgrades to serve the load.
System Protection Requirements
Yes and back-up unit required to take forced outage
Demand Response Eligibility
No
Tariff Modifications
Yes

This option is the same configuration as Option 4 above, but with the potential for the load to receive back-up service from the grid with PJM’s advanced authorization (meaning unilateral action by the generator or load to draw from the grid is not permitted). Such authorization from PJM would follow coordination by and among the generator and/or load, PJM, and the Transmission Owner (for matters relating to generator outages or otherwise).  Any PJM approval to take back-up power from the grid would be subject to conditions including the potential withholding of authorization or withdrawing of authorization under conditions that may threaten the integrity or reliability of the PJM Region or the regional power system.  This option requires real-time, bespoke operational decision-making to determine whether load can continue to be served.  Tariff modifications would be needed based on the Commission’s order in Docket No. ER24-2172.8

8 See id.

PDF page 16

16

Option 6: Co-located load that elects to be Network Load and bring its own generation

New Option 6
*note:  each option is subject to state laws that
may specifically define and limit when and how
load in a jurisdiction can be served by a supplier
other than a franchised public utility
Co-located load that elects to be Network Load and bring own generation
BYOG
Description
This option provides an opportunity for to bring your own generation with the incentive for faster interconnection when the load is Network Load

PJM Preference
Yes - maintains Resource Adequacy
Load Status
Network
Generation Capacity Status
Yes
PJM obligation to serve
Yes
Load System Used and Charged
NITS (Full load during coincident peak); Energy; Capacity (Full load during coincident peak) Ancillary Services Used

Reactive, Black Start, Regulation, Sync, Non Sync, Day-ahead Scheduling Reserves Ancillary Services Charged

Reactive, Black Start, Regulation, Sync, Non Sync, Day-ahead Scheduling Reserves (based on entire load)

Generation Revenue
• Capacity (based on full CIRs)
• Energy and Ancillary Services (based on entire gen output)
Studies
• TO Load Integration study
•PJM Do No Harm study
•RTEP process inclusive of Load Forecast
•Generator Interconnection Study
Load included in Load Forecast
(RTEP)
Yes
Load included in RPM Reliability
Requirement
Yes
Cost Allocation for Interconnection
Upgrades
• Supplemental projects pursuant to local TO methodology
• RTEP upgrades pursuant to RTEP cost allocation
• Generator for the generator interconnection
System Protection Requirements
N/A
Demand Response Eligibility
Yes
Tariff Modifications
Maybe

Under this option, large load additions interconnecting as Network Load could also bring to PJM additional generation that could serve as Capacity Resources.  The additional generation could be in the form of new incremental generation or arrangements with generation that otherwise has or is scheduled to deactivate.  This path would also be open for existing generation that could serve the energy needs of the large loads so long as the generator would still be available to PJM as a Capacity Resource if it clears in the capacity market.

PDF page 17

17
Incentives could be explored to offer faster processing of generation that enters the queue through this option, including by way of example:  (1) providing options for accelerating interconnection studies of new generation proposed as part of this option;

(2) enhancing existing provisional interconnection service options at discrete study points in the interconnection cycle so as to accelerate, in  a nondiscriminatory manner, the ability of new generation to achieve commercial operation; and (3) states could remove a barrier to entry for investment in large load infrastructure by assuming cost responsibility for transmission upgrades in the Regional Transmission Expansion Plan (“RTEP”) pursuant to the State Agreement Approach9 to promote state policies to encourage large load (including data center) development in their jurisdictions.

For this Option 6, a physical co-located configuration can still be utilized but there is an additional opportunity for the new generation to enter into a bilateral agreement with the load for financial and contractual purposes.  This scenario would require preparation of an interconnection study for the new generation resource.  Further, the large load would be studied and could be connected to the grid pursuant to the existing Transmission Owner/EDC load interconnection process.  If transmission system upgrades are necessary to connect the load to the grid, the Attachment M-3 Process would be employed, and these upgrades would be proposed and studied as supplemental projects (and costs would be allocated pursuant to a Transmission Owner’s cost allocation methodology).  Other State Agreement Approach-related contracts might also be required on a case-by-case basis. This option offers a potentially faster interconnection path for generation resources supporting co-located loads in states that want them.  It is possible that Tariff revisions

9 Operating Agreement, Schedule 6, section 1.5.9 (State Agreement Approach).

PDF page 18

18
would be required, especially for purposes of enhancing PJM’s existing provisional interconnection service construct or facilitating options to accelerate interconnection studies of new generation proposed as part of this option.

Option 7:  Potential new non-capacity backed service as a Transitional Service

New Option 7
*note:  each option is subject to state laws that
may specifically define and limit when and how
load in a jurisdiction can be served by a supplier
other than a franchised public utility
Co-located load that takes Interruptible Service
(Load willing to curtail in advance of Emergency Procedures)
Description
This option provides an opportunity for large load to integrate as a non-capacity backed load where it avoids capacity costs if willing to curtail to support reliability in advance of emergency conditions. PJM Preference

Yes - maintains Resource Adequacy
Load Status
Network (advance curtailment)
Generation Capacity Status
Yes
PJM obligation to serve
Yes but less priority
Load System Used and Charged
NITS (Full load during coincident peak); Energy, Capacity (only for portion that is not non-capacity backed)

Ancillary Services Used
Reactive, Black Start, Regulation, Sync, Non Sync, Day-ahead Scheduling Reserves Ancillary Services Charged

Reactive, Black Start, Regulation, Sync, Non Sync, Day-ahead Scheduling Reserves (based on entire load)

Generation Revenue
• Capacity (based on full CIRs)
• Energy and Ancillary Services (based on entire gen output)
Studies
• TO Load Integration study
•PJM Do No Harm study
•RTEP process inclusive of Load Forecast
•Necessary Study
Load included in Load Forecast
(RTEP)
Yes
Load included in RPM Reliability
Requirement
• No for non-capacity backed load
• CIRs included in RPM
Cost Allocation for Interconnection
Upgrades
• Supplemental projects pursuant to local TO methodology
• RTEP upgrades pursuant ot RTEP cost allocation
• Generator for the changes to its facility to accommodate the load
System Protection Requirements
N/A
Demand Response Eligibility
No
Tariff Modifications
Yes

This potential new option would allow a large load to integrate as Network Load at a potentially faster pace than under existing load integration frameworks subject to the load electing a new transitional non-capacity backed service offering.  Under this offering, large loads would be offered the option to be classified as a non-capacity backed load for a transitional period until any resource adequacy supply/demand imbalances associated with

PDF page 19

19
the large load addition could be addressed and the load could assume full Network Load status with all of its attendant benefits.

In return for agreeing to take non-capacity backed service, the load would avoid capacity costs during the transition period in return for its willingness to curtail load (or serve its own load through on-site generation10) in those situations where, by way of example, PJM has identified conditions that may threaten the integrity or reliability of the PJM Region or the regional power system.

Potential variations on this option could be explored with the ultimate goal being to enhance resource adequacy and provide opportunities for large loads to efficiently connect to the system by providing incentives for large loads to be more flexible.  The advantage of a physical co-located configuration can still be utilized although all load would be in front of the meter.  Tariff revisions would be required to develop this new type of service.

Option 8: Co-located load participating in Demand Response

New Option 8
*note:  each option is subject to state laws that
may specifically define and limit when and how
load in a jurisdiction can be served by a supplier
other than a franchised public utility
Co-located Load  that elects to be Network Load  and that participates as Demand Response Description

This existing option provides an opportunity for the load to be Network Load and participate as a Demand Response resource.  Options to operate back-up generation provides a mechanism to serve the co-located load when asked to curtail for DR. This option assume the co-located load and generation share the same POI.

Additional review of DR rules and opportunities for relaxation of federal and state emission restrictions provide more incentives.

PJM Preference
Yes - maintains Resource Adequacy
Load Status
Network
Generation Capacity Status
Yes
PJM obligation to serve
Yes
Load System Used and Charged
NITS (Full load during coincident peak); Energy; Capacity (Full load during coincident peak) Ancillary Services Used

Reactive, Black Start, Regulation, Sync, Non Sync, Day-ahead Scheduling Reserves Ancillary Services Charged

Reactive, Black Start, Regulation, Sync, Non Sync, Day-ahead Scheduling Reserves (based on entire load)

10 See infra PJM’s response to question F.ii.

PDF page 20

20
Generation Revenue
• Demand Response Revenue
• Capacity (based on full CIRs)
• Energy and Ancillary Services (based on entire gen output)
Studies
• TO Load Integration study
•PJM Do No Harm study
•RTEP process inclusive of Load Forecast
•Necessary Study
Load included in Load Forecast
(RTEP)
Yes
Load included in RPM Reliability
Requirement
Yes
Cost Allocation for Interconnection
Upgrades
• Supplemental projects pursuant to local TO methodology
• RTEP upgrades pursuant ot RTEP cost allocation
• Generator for the changes to its facility to accommodate the load
System Protection Requirements
N/A
Demand Response Eligibility
Yes
Tariff Modifications
Maybe

This option provides an opportunity for the load to be Network Load and participate as a Demand Response resource.  Although this option already exists in PJM, there could be an additional review of the PJM Demand Response rules.  Also, there may be opportunities for a targeted review of federal and state emission restrictions on back-up generation that would provide more incentives for this option (see infra the discussion of diesel back-up generators in response to question F.ii).  Options to operate back-up generation provide a mechanism to serve the co-located load when asked to curtail for Demand Response.  This option may enhance resource adequacy under tight system conditions in the short term, and realizes other benefits of Network Load status.  For any enhancements to the existing demand response product, potential future Tariff revisions may be required.

PDF page 21

21
III. PJM RESPONSE TO COMMISSION QUESTIONS

A. General
i. Do you agree with the jurisdictional principles outlined in section VI.A and should the Commission reach any other conclusions regarding jurisdiction in a final order it may issue in this proceeding?  Why or why not?

PJM Response:
Although section VI.A of the Commission’s Order outlines the Commission’s jurisdiction in broad strokes, there is nuance regarding the Commission’s jurisdiction that is worth noting and was not addressed in the Order.

Due to deregulation at both the state and federal level, there is the potential for regulatory gaps with respect to co-located load arrangements.  The FPA was written to respect the state’s traditional role with respect to electricity regulation.  To that end, the FPA provides:

(a) It is declared that the business of transmitting and selling electric energy for ultimate distribution to the public is affected with a public interest, and that Federal regulation of matters relating to generation to the extent provided in this subchapter and subchapter III of this chapter and of that part of such business which consists of the transmission of electric energy in interstate commerce and the sale of such energy at wholesale in interstate commerce is necessary in the public interest, such Federal regulation, however, to extend only to those matters which are not subject to regulation by the States.

(b) The provisions of this subchapter shall apply to the transmission of electric energy in interstate commerce and to the sale of electric energy at wholesale in interstate commerce, but shall not apply to any other sale of electric energy or deprive a State or State commission of its lawful authority now exercised over the

exportation of hydroelectric energy which is transmitted across a State line. The Commission shall have jurisdiction over all facilities for such transmission or sale of electric energy, but shall not have jurisdiction, except as specifically provided in this subchapter and subchapter III of this chapter, over facilities used for the generation of electric energy or over facilities used in local distribution or only for the transmission of electric energy in intrastate commerce, or

PDF page 22

22
over facilities for the transmission of electric energy consumed
wholly by the transmitter.
(c) For the purpose of this subchapter, electric energy shall be held
to be transmitted in interstate commerce if transmitted from a State
and consumed at any point outside thereof; but only insofar as such
transmission takes place within the United States.11
The foregoing grants the Commission three categories of jurisdiction:
(i) jurisdiction over “the transmission of electric energy in interstate commerce,”
(ii) jurisdiction over “the sale of such energy at wholesale in interstate commerce,”12 and
(iii) jurisdiction over the facilities used for such wholesale sales and transmission. In addition, the FPA expressly limits the Commission’s jurisdiction over:  (i)  sales of electricity that are not wholesale sales,13 (ii) facilities used for generation, (iii) local distribution facilities (in other words, not associated with high-voltage transmission of electric energy but where the transmitted power was “stepped down” to distribution voltage), and (iv) facilities for the transmission of electric energy consumed wholly by the transmitter (which does not appear implicated by most co-located load arrangements given different identities between transmitter and consumer).

When the FPA was enacted, the industry looked very different than it looks today. Given industry deregulation, the increased interconnectivity of the grid, and advancements in technology, the traditional dividing lines between state and federal jurisdiction have somewhat blurred.  Although Organization of PJM States, Inc. contends that “there is no regulatory gap involving co-location arrangements,”14 it is unclear whether that is the case

11 16 U.S.C. §§ 824(a)-(c). 12 16 U.S.C. §§ 824(a), (b)(1); see N.Y. v. FERC, 535 U.S. 1, 7–8 (2002) (“New York”).
13 See S. Cal. Edison Co. v. FERC, 603 F.3d 996, 1000-01 (D.C. Cir. 2010) (regarding station power); Ind. Mun. Power Agency v. PJM, 173 FERC ¶ 61,243, at PP 89-102 (2020) (same). 14 Order at P 18.

PDF page 23

23
across PJM’s footprint.  The bottom line:  as discussed below, different state laws may impact the permissibility of certain of the potential co-location arrangements summarized in Exhibit A and discussed above.15

Traditionally, utilities were vertically integrated and operated within a franchised service territory selling bundled electricity to end users at state-regulated retail rates.16  Due to this vertical integration, a single company would own the electric generating facilities, transmission lines, and distribution lines needed to serve retail customers.  This market structure was due in part to state law and the Public Utility Holding Company Act of 1935 (“PUHCA”) (which was repealed in 2005).17  State laws typically granted an exclusive retail franchise within their jurisdictions and these utilities provided bundled electric service, and state regulators and state laws typically defined (and still define) the extent of a utility’s legal obligation to serve customers.  PUHCA, for its part, broke up a small number of existing electric utility holding companies into hundreds of smaller, local utility companies or holding company systems.18

Over the last few decades and particularly since the passage of the Public Utility Regulatory Policies Act of 1978 (“PURPA”),19 the electric power industry has evolved

15 See Jon Wellinghoff & Steven Weissman, The Right to Self-Generate as a Grid-Connected Customer, Energy Bar Association, 305 (2015), https://www.eba-net.org/wp-content/uploads/2023/02/11-23-305-326- Wellinghoff_FINAL-11.10.pdf (“In those areas of the country where competitive retail access to electric service does not exist, . . . [there is] a struggle to determine who has the right to supply all or a portion of the electric energy services necessary to meet a consumer’s needs.”).
16 See FERC v. Elec. Power Supply Ass'n, 577 U.S. 260, 266-67 (2016) (“EPSA”).
17 See Public Utility Holding Company Act of 1935, Pub. L. No. 74-333, 49 Stat. 821 (codified as 15 U.S.C. §§ 79-79z-6) (repealed 2005).
18 See The Repeal of the Public Utility Holding Company Act of 1935 (PUHCA 1935) and Its Impact on Electric and Gas Utilities, Congressional Research Service (Nov. 20, 2006), https://www.everycrsreport.com/files/20061120_RL33739_19b253d11f6560b7153533b0430a157fe0effb5f .pdf.
19 Public Utility Regulatory Policies Act of 1978, Pub. L. No. 95-617, 92 Stat. 3117 (codified as 16 U.S.C. § 261).

PDF page 24

24
from one where vertically integrated utility monopolies predominated to an environment that supports more competitive generation supply.  Among other things, PURPA

introduced a new category of wholesale sellers exempt from PUHCA’s “integrated public- utility system” restriction called Qualifying Facilities (“QFs”)—which were either a “cogenerator” or a “small power producer.”  QFs may make retail sales in states where permitted to do so.

A notable exception to the exclusive franchised utility construct that emerged after PURPA was customer self-service in the form of commercial and industrial electrical users (for example, in the pulp and paper industry) that installed “inside the fence” QF cogeneration facilities where permitted by state law.20  Such self-service arrangements appear distinguishable from co-location arrangements because co-location arrangements generally involve the sale of power from generators to intermediaries and then to load.21 Even where these self-servicing industrials consumed the entire output of their generation facilities, these industrials still required electric distribution service from the local utility to provide power in the event on-site generation was on outage or was insufficient to satisfy the full electrical requirements of the operation.  These industrials were not electrically islanded.  In fact, they established and maintained interconnections the terms of which

20 See generally Jackie S. Levinson & Andrew D. Schifrin, Regulatory and Tax Treatment of Electric Interconnection Facilities, Energy Bar Association, 23 Energy L.J. 459, 462 (2002), https://www.eba- net.org/wp-content/uploads/2023/02/6-Vol23_No2_2002_Art_Regulatory-and-Tax.pdf; Douglas M. Roe, Musings from Behind-the-Meter:  A 20th Century Model for a 21st Century World?, Energy Bar Association, 44 Energy L.J. 251, 254-55 & n.16 (2023), https://www.eba-net.org/wp-content/uploads/2023/11/5-Roe251- 300.pdf (“‘Competition for industrial loads from self-generation was present at the turn of [the twentieth] century.’”).
21 See Constellation Energy Generation, LLC v. PJM Interconnection, L.L.C., Comments of East Kentucky Power Cooperative, Inc., Docket No. EL25-20-000, at 3 & n.9 (Dec. 12, 2024) (“EKPC Comments”) (“The colocation issue here is distinguishable from the situation of a load using its own on-site generation resource to provide all or part of its power supply, i.e., self- generation. . . .  Even in the case of back-up generation (in which the load has generation that it can use to self-supply when power from the utility is not available), the load must comply with state law requirements.”).

PDF page 25

25
(including any back-up service) were frequently addressed in separately negotiated agreements or in utilities’ state-regulated retail tariffs.

Several other major changes in the regulatory landscape call into question the
assumption that states necessarily regulate matters outside of the Commission’s
jurisdiction or over which the Commission has not affirmatively regulated.  Starting in the 1990s the Commission ordered utilities that offered unbundled transmission service either voluntarily or as the result of state retail choice programs, to offer non-discriminatory access to their transmission systems.22  The Energy Policy Act of 1992 amended PUHCA to create Exempt Wholesale Generators (“EWGs”), which would—like a QF—be exempt

from PUHCA’s restrictions.  This development further increased the number and diversity of potential wholesale generation competitors (as EWGs were not fuel-type limited).  By definition, an EWG engages in wholesale transactions and cannot make retail sales.23  Yet under certain co-located load arrangements (Options 4 and 5 in Exhibit A, for example), EWGs could seek to sell power to an intermediary that then engages retail sales.24

22 See generally New York (upholding Order No. 888 and surveying industry regulatory developments); see Promoting Wholesale Competition Through Open Access Non-Discriminatory Transmission Services by Public Utilities; Recovery of Stranded Costs by Public Utilities and Transmitting Utilities, Order No. 888, 75 FERC ¶ 61,080, 1991–1996 FERC Stats. & Regs., Regs. Preambles ¶ 31,036 (1996), order on reh’g, Order No. 888-A, 78 FERC ¶ 61,220, 1996–2000 FERC Stats. & Regs., Regs. Preambles ¶ 31,048, order on reh’g, Order No. 888-B, 81 FERC ¶ 61,248 (1997), reh’g denied, Order No. 888-C, 82 FERC ¶ 61,046 (1998), aff’d in part & remanded in part sub nom. Transmission Access Policy Study Group v. FERC, 225 F.3d 667 (D.C. Cir. 2000), aff’d sub nom. New York v. FERC, 535 U.S. 1 (2002).
23 18 C.F.R. § 366.1.
24 See, e.g., Jersey Cent. Power & Light Co., 1996 N.J. PUC Lexis 23 (May 23, 1996); O’Brien (Parlin) Cogeneration, Inc., Application of O’Brien (Parlin) Cogeneration, Inc. for Determination of Exempt Wholesale Generator Status, Docket No. EG96-60-000 (Apr. 29, 1996); O’Brien (Parlin) Cogeneration, Inc., 75 FERC ¶ 61,326 (1996).  Congress would have to amend the FPA to allow EWGs to provide needed energy directly to co-located loads.  See Todd Glass, Achieving AI dominance through competitive power markets, Utility Drive, https://www.utilitydive.com/news/ai-data-centers-competitive-power-markets/738275/ (last visited Mar. 21, 2025).

PDF page 26

26
As a result of this unbundling, electric utilities restructured from vertically
integrated companies, to separately owning generation, transmission, and distribution
facilities.25  In addition, the Energy Policy Act of 2005 repealed the Public Utility Holding Company Act of 1935.26  As a result, “any type of entity can own any type of utility asset and perform any type of electric service function, in any location.”27

Further, between 1996 and 2000, many states in the PJM Region assessed whether
to introduce competition for retail electricity service into historically exclusive service territories.28  This is a significant point because under states that did not pursue

deregulation, a state’s exclusive retail franchise territory law may restrict non-franchised suppliers from serving co-located load.29  Further, in deregulated states, state law may (or

25 EPSA at 267 (“Decades ago, state or local utilities controlled their own power plants, transmission lines, and delivery systems, operating as vertically integrated monopolies in confined geographic areas. That is no longer so. Independent power plants now abound, and almost all electricity flows not through ‘the local power networks of the past,’ but instead through an interconnected ‘grid’ of near-nationwide scope.”). 26 Energy Policy Act of 2005, Pub. L. No. 109-58, §§ 1261-77, 119 Stat. 594.
27 Scott Hempling, Regulating Public Utility Performance: The Law of Market Structure, Pricing and Jurisdiction 93 (2nd ed. 2021) (“Regulating Public Utility Performance”).
28 See Regulating Public Utility Performance at 93 & n.25 (identifying Delaware, District of Columbia, Illinois, Maryland, Michigan, New Jersey, Ohio, and Pennsylvania as among the states that allow retail electricity competition).
29 Some parties have advanced arguments about such state law particulars in related dockets. See, e.g., EKPC Comments at 3 (“Kentucky law is clear that ‘each retail electric supplier shall have the exclusive right to furnish retail electric service to all electric-consuming facilities located within its certified territory.’” (citing KY. REV. STAT. ANN. § 278.018(1) (West))); Baltimore Gas & Electric Co., Comments of Southern Maryland Electric Cooperative, Inc., Docket No. EL24-149-000, at 3 (Oct. 30, 2024) (“[C]onsistent with current Maryland law, a Maryland co-located data center or other large load is a ‘retail electric customer’ similar to any other resident or business situated in [Southern Maryland Electric Cooperative, Inc’s] southern Maryland electric service territory.  Only an ‘electric company’ with relevant franchise rights and other necessary approvals is authorized to serve ‘retail electric customers’ in Maryland.”); State ex rel. Utils. Comm’n v. N.C. Waste Awareness & Reduction Network, 255 N.C. App. 613, 618 (2017) (“Duke Energy has been granted an exclusive right to provide electricity in return for compensation within its designated territory and with that right comes the obligation to serve all customers at rates and service requirements established by the Commission.”), aff’d sub nom., 812 S.E.2d 804 (N.C. 2018).  Further, as others have explained, “some states may require that franchise public utilities not co-locate load at existing generation facilities built and paid for by its retail customers.  Additionally, state law may specifically define and limit when load in a franchise public utility’s territory can be served by a supplier other than the franchise public utility.”  Large Loads Co-located at Generation Facilities, Comments of Dominion Energy Services, Inc., Docket No. AD24-11-000, at 10 (Dec. 9, 2024) (“Dominion Energy Comments”); Dominion Energy Comments at 2 (noting Dominion Energy Virginia is a vertically integrated utility that owns regulated electric transmission,

PDF page 27

27
may not) today (or in the future) require co-located load suppliers to be licensed energy providers and/or otherwise impose limitations on such suppliers by, for example, obliging the designation of the load as Network Load, with or without netting, or take certain types of transmission service that could compel the designation of co-located load as Network Load.30

State law does not necessarily regulate companies making sales to these end users.
There are instances where industrial customers’ self-supply of electricity has been found to fall outside the scope of public utility regulation.  Indeed, even when one large industrial end-user sold electricity to another large industrial end-user within the same complex, such sales were found neither to render the seller a public utility under state law nor violate the local utility’s exclusive franchise territory because it was not offering such sales to the public generally.31

By way of further example, Pennsylvania defines a “public utility” as a person or
corporation that transmits or distributes electricity “to or for the public for
compensation.”32  To the extent a company is found to be a public utility, it would be
subject to regulation by the Pennsylvania Public Utilities Commission (“PA PUC”).

distribution, and generation assets (including two nuclear facilities) and Northern Virginia is in its franchise service territory).  Under Virginia Law, Dominion Energy Virginia appears to have been granted an exclusive franchise by the State Corporation Commission to serve customers as a public utility within its certificated service territory.  See VA. CODE ANN. § 56-265.3A.  It is a monopoly provider of such service and, in accord with that franchise, has an obligation to provide it to all customers within its territory.  See VA. CODE ANN. §§ 56-265.4, 56-234A.

30 Some states appear to have jurisdiction over the terms and conditions in state retail tariffs like Electric Generation Supplier Coordination Tariffs or Supplier Coordination Tariffs.
31 See, e.g., U.S. Steel Corp. v. N. Ind. Pub. Serv. Co., 951 N.E.2d 542, 554-57 (Ind. Ct. App. 2011) (finding that Steel Producer’s sale of electricity to industrial end user within the same complex did not render the Steel Producer a public utility as defined by the Indiana code).  Given the national security interests that may attach to the AI infrastructure co-located load arrangements, it is not clear if state regulators would view new data center loads as being in furtherance of the public interest and the public generally, such that state regulation may be appropriate.
32 66 PA. CONS. STAT. § 102(1)(i) (regarding definition of “public utility”).

PDF page 28

28
However, the PA PUC and Pennsylvania appellate courts have found that service to a
closed, limited, and privileged class of customers pursuant to contract is not service to the “public” and, therefore, PA PUC jurisdiction does not attach.33  In Pennsylvania, these determinations are made based on the control over who can receive service and whether the corporation holds itself out as willing to provide service to the public.34  Because the companies agreeing to sell electricity to data centers may not be offering that service to the public generally, it is possible that courts and state regulators would find that these sales likely will not be subject to public utility regulation in Pennsylvania.35  PJM is unaware of any Pennsylvania state law objections to the proposed co-location arrangement advanced in Docket No. ER24-2172 relating to the Third Revised Co-Located Load Susquehanna

Nuclear, LLC (“Susquehanna”) Interconnection Service Agreement (“ISA”) docket.36
Pennsylvania is not the only state that has declined to regulate sales to large end users in this way.  New Jersey has similarly declined to exercise public utility regulation over sales to large end users.  In 1999, the New Jersey Board of Public Utilities disclaimed jurisdiction over a special purpose entity that was created to resell power from a

cogeneration plant to an inside-the-fence retail customer to allow the owner of the

33 See, e.g., Drexelbrook Assocs. v. Pa. Pub. Util. Comm’n, 212 A.2d 229 (Pa. Super. Ct. 1964) (holding that a landlord who controlled who could be a tenant via a lease was not a public utility).
34 See, e.g., Warwick Water Works, Inc. v. Pa. Pub. Util. Comm’n, 699 A.2d 770 (Pa. Commw. Ct. 1997) (holding that condo association was a public utility because it did not control who could become a condo unit owner).
35 The Philadelphia Navy Yard is similarly regarded as not being subject to Pennsylvania public utility regulation, and holds itself out as an unregulated electric grid.  See Kevin B. Jones, et al., The Urban Microgrid:  Smart Legal and Regulatory Policies to Support Electric Grid Resiliency and Climate Mitigation, Fordham Urban Law Journal, 1695, 1717-19 (2014), https://ir.lawnet.fordham.edu/cgi/viewcontent.cgi?article=2552&context=ulj (“The microgrid structure at the Navy Yard is an anomaly—it operates independent of state regulation” because it is not a “public utility” under applicable law).
36 See, e.g., PJM Interconnection, L.L.C., Comments of the Pennsylvania Public Utility Commission, Docket No. ER24-2172-000 (July 10, 2024) (identifying no state law obstacles).

PDF page 29

29
cogeneration unit to obtain EWG status from the Commission.37  Under New Jersey law, a public utility is defined as an entity that owns, operates, or manages any electrical light plant or equipment for public use.38  In that case, because the entity created would not own or operate any equipment, the New Jersey Board of Public Utilities declined to regulate that entity as a public utility.39

As these examples illustrate, there is risk in painting with too broad a brush.  State law regulatory particulars may, in certain instances, determine whether particular co- location arrangements will be regulated by the states or permitted by states with a

franchised public utility model.  As such, the propriety of the co-location arrangements proposed in Exhibit A are subject to different state law requirements that could disqualify certain options.

Transmission
The Commission’s jurisdiction over the ‘“the transmission of electric energy in
interstate commerce,”’ 16 U.S.C. § 824(b)(1), extends to energy ‘“transmitted from a State and consumed at any point outside thereof.”’40  A jurisdictional determination, therefore,

37 See Jersey Cent. Power & Light Co., 1996 N.J. PUC Lexis 23 (May 23, 1996); O’Brien (Parlin) Cogeneration, Inc., Application of O’Brien (Parlin) Cogeneration, Inc. for Determination of Exempt Wholesale Generator Status, Docket No. EG96-60-000 (Apr. 29, 1996); O’Brien (Parlin) Cogeneration, Inc., 75 FERC ¶ 61,326 (1996).
38 Jersey Cent. Power & Light Co., 1996 N.J. PUC Lexis 23, at *7.
39 Id. at *8.  The Commission’s precedent regarding what is acceptable to do through an affiliate while retaining EWG status is somewhat at odds.  For example, for purposes of determining whether a generating unit qualifies as an EWG under the Public Utility Holding Company Act of 1935, the Commission has found that a company cannot qualify for EWG status if it is engaging in any business even if the company transfers the relevant business to an affiliate.  See PSEG Fossil, LLC, 95 FERC ¶ 61,405 (2001) (rejecting company’s request to confirm EWG status if the company transferred business activities other than wholesale sales of electricity to an affiliate because allowing the company to transfer the business to an affiliate would “elevate form over substance”).  However, the Commission has allowed a company to retain EWG status while selling power to an end-user through an affiliate that was created specifically to effectuate the sale to the end-user. O’Brien Parlin Cogeneration, 75 FERC ¶ 61,326 (1996). 40 Fed. Power Comm’n v. Fla. Power & Light Co., 404 U.S. 453-54 (1972).

PDF page 30

30
turns on a factual question regarding the flow of energy.41  To find the Commission has jurisdiction over wholesale transmission, there must be substantial evidence of energy flowing across state lines.42  However, there is no requirement to trace individual electrons to make a jurisdictional finding (as it would not be possible to do so).  Instead, where a utility’s lines are connected to the interstate grid—even indirectly—this can be sufficient to support a finding of interstate transmission due to the nature of how electricity flows.43 In this regard, the Commission’s jurisdiction can be established through circumstantial evidence that interstate transmission has taken place.44

At a minimum, co-located arrangements implicate the Commission’s transmission
jurisdiction due to PJM’s provision of ancillary services and in light of the wholesale sales taking place over certain facilities.  Even to the extent a co-located data center is primarily obtaining energy from a co-located generator, that data center will be interconnected to the grid such that it will benefit from PJM’s provision of ancillary services, including load following, frequency regulation, and black start.  Therefore, at a minimum, the

Commission has jurisdiction regarding the transmission service associated with the
ancillary services utilized in co-location arrangements.  These ancillary services cannot be delivered without the grid.

41 Id. at 454-55.
42 Id. at 458.
43 New York at 7–8 (“It is only in Hawaii and Alaska and on the ‘Texas Interconnect’—which covers most of that State—that electricity is distributed entirely within a single State.  In the rest of the country, any electricity that enters the grid immediately becomes a part of a vast pool of energy that is constantly moving in interstate commerce.  As a result, it is now possible for power companies to transmit electric energy over long distances at a low cost.” (footnote omitted)).
44 Ind. & Mich. Elec. Co. v. Fed. Power Comm’n, 365 F.2d 180 (7th Cir. 1966) (finding evidence that there was not sufficient generation in state to meet the load as sufficient to show an interstate transmission took place).

PDF page 31

31

Further, the Commission’s jurisdiction over transmission service in interstate
commerce is also necessarily implicated in matters relating to co-located load arrangements where generator interconnections are being modified.  The Commission has jurisdiction over interconnections to the grid, and no entities are disputing the Commission’s jurisdiction over such interconnections, including modifications to add load (which again may include a wholesale sale and transmission).45

Wholesale Sales
The FPA empowers the Commission to regulate wholesale sales of electricity (i.e., sales for resale) in interstate commerce, but reserves to the states the authority to regulate all other sales.46  The Commission’s jurisdiction extends to sales for resale even to the extent such sales are taking place entirely within one state provided sale involves electricity flowing across states lines.47  Given the interconnectivity of the grid, advancements in technology, and industry deregulation, whether or not a wholesale sale has taken place has become an increasingly complicated question.  Moreover, the way the Commission has gone about answering that question depends on the context and has evolved over time.

45 Standardization of Generator Interconnection Agreements and Procedures, Order No. 2003, 104 FERC ¶ 61,103 (2003), order on reh’g, Order No. 2003-A, 106 FERC ¶ 61,220, order on reh’g, Order No. 2003- B, 109 FERC ¶ 61,287 (2004), order on reh’g, Order No. 2003-C, 111 FERC ¶ 61,401 (2005), aff’d sub nom. Nat’l Ass’n of Regul. Util. Comm’rs v. FERC, 475 F.3d 1277 (D.C. Cir. 2007), cert. denied, 552 U.S. 1230 (2008) (the Commission will continue to have exclusive jurisdiction over the rates, terms, and conditions in service agreements).
46 Order at P 67.
47 Fed. Power Comm’n, 376 U.S. 205 (upholding Federal Power Commission jurisdiction over sales of electric energy at wholesale in interstate commerce where a sale was intrastate but power flowing originated out of state).

PDF page 32

32
ii. Does the Tariff sufficiently address co-location arrangements with
respect to each issue listed in this order?  Please include specific
tariff provisions or other governing documents that may apply.
PJM Response:
PJM’s Tariff remains just and reasonable.  The Tariff today permits co-located loads to interconnect through existing load interconnection processes, albeit processes whereby the load is designated Network Load and reported to PJM via the Transmission Owners/Load Serving Entities/EDCs.  Certain entities may prefer, for their own business reasons, alternative pathways to co-location.  But such preferences do not render the Tariff unjust and unreasonable because they do not accommodate such business goals while providing alternative pathways to service.48

Nevertheless, clarifications and enhancements could well be in order given that this is an evolving area and Tariff provisions did not contemplate the type of arrangements at issue in this docket or their implications.  PJM is committed to facilitating and supporting co-location arrangements where permitted by applicable state law.  PJM is proposing various options to facilitate the development of Artificial Intelligence (“AI”)-infrastructure as discussed above and in Exhibit A to this filing.  Pending Commission and stakeholder input, PJM remains open to modifying its Tariff as necessary to clarify any rates, terms, or conditions relating to co-location arrangements to provide the industry with needed regulatory clarity, certainty, and optionality.

As noted previously, given the national interest in development of data centers to ensure the domestic development of AI (among other reasons), PJM’s efforts would be greatly assisted by Commission guidance as to the reasonableness of any of the existing

48 See Anbaric Dev. Partners, L.L.C. v. PJM Interconnection, L.L.C., 171 FERC ¶ 61,241 (2020).

PDF page 33

33
and proposed options for co-located load set forth in Exhibit A and described in this submittal.  Moreover, progress on these issues would be greatly enhanced by the Commission setting a deadline for either submittals of a compliance filing or Section 205 filings to provide a clear pathway of options that meet the Commission’s and industry’s shared interests in advancing this important issue.

iii. If the Tariff does not sufficiently address co-location arrangements, how should the Tariff be modified to do so?  As part of your answer, address whether portions of the Guidance Document may serve as

a just and reasonable and not unduly discriminatory or preferential
replacement rate.  Alternatively, address whether existing rules in
the Tariff may or should be modified to address co-location
arrangements.
PJM Response:
As a threshold matter, PJM rescinds its previously issued Guidance Document pending Commission guidance in this docket about a Commission-approved path forward (including the propriety of Option 4).  As explained in PJM’s submissions in Docket No. EL25-20, the heavily caveated Guidance Document was issued by PJM as an initial attempt to provide limited guidance after over a year’s worth of unfruitful stakeholder discussions.  The Commission has rejected a modified ISA informed by this Guidance Document.49

In this submittal, PJM has set forth possible options for co-location. Some options are already embodied in the existing Tariff while others would require new or enhanced Tariff provisions.  Stakeholder and Commission feedback on these and other options is necessary, as is Commission guidance both on the propriety of proposed options and also

49 See Docket No. ER24-2172.

PDF page 34

34
the timeline for any additional compliance or Section 205 filings to implement such guidance.

iv. Parties may also address how co-located loads are similar to or disparate from other types of arrangements where load and

generation share the same point of interconnection (such as Behind
the Meter Generation as defined in PJM’s Tariff or non-retail
behind the meter generation) and should consider how any
proposed replacement rate would interact with these other
arrangements.
PJM Response:
The co-located load arrangements at issue here, large data centers, could be viewed as similar to BTM Generation that currently exists under PJM’s Tariff (as reflected in Exhibit A, Option 3).  But as explained herein, the BTM Generation paradigm does not fit co-location arrangements particularly well because it was not designed with large load co- location in mind.

BTM Generation is defined as:
[A] generation unit that delivers energy to load without using
the Transmission System or any distribution facilities (unless the
entity that owns or leases the distribution facilities has consented to such use of the distribution facilities and such consent has been

demonstrated
to
the
satisfaction
of
the Office
of
the
Interconnection); provided, however, that Behind The Meter
Generation does not include (i) at any time, any portion of such
generating unit's capacity that is designated as a Generation
Capacity Resource; or (ii) in an hour, any portion of the output of such generating unit that is sold to another entity for consumption at another electrical location or into the PJM Interchange Energy

Market.50
As PJM described in 2004 when it proposed its BTM Generation Tariff revisions, BTM Generation “refers to generating units that are located with load at a single electrical location such that no transmission or distribution facilities are used to deliver energy from

50 Tariff, Part I, Definitions – A - B.

PDF page 35

35
the generating unit to the load.”51  This definition was subsequently expanded to permit inclusion of municipals and EDCs (“Non-Retail”) that use distribution facilities to serve loads, with the consent of the owner or lessee of the distribution facilities.52  Notably, “BTM[] G[eneration] netting is only available to entities that have Network Integration Transmission Service agreements with PJM[,]”53 and are thus taking NITS, as the netting provisions appear in PJM’s NITS Tariff.54

Although all load served by BTM Generation must be designated Network Load
(as the Tariff does not exempt such load from the definition of Network Load), PJM’s BTM Generation rules permit a different rate treatment in the form of netting of loads served BTM.  Under such netting provisions, the Network Customer’s daily load “does not include load served by operating Behind The Meter Generation.”55  The extent to which netting could or should apply to co-located data center load is not clear at this time.

Moreover, while the BTM Generation netting concept was justified as a means of
recognizing that certain market participants “rely to a lesser degree on the PJM integrated

51 PJM Interconnection, L.L.C., 107 FERC ¶ 61,113, at P 4 (2004).
52 PJM Interconnection, L.L.C., 113 FERC ¶ 63,024 (2005), aff’d, 113 FERC ¶ 61,279. 53 Operations Planning Division, PJM Manual 14D: Generator Operational Requirements, PJM Interconnection, L.L.C., Appendix A ¶ 4 (Dec. 18, 2024), https://www.pjm.com/- /media/DotCom/documents/manuals/m14d.pdf (“PJM Manual 14D”).
54 Tariff, Part III, sections 34.2 and 34.3.
55 Id. at section 34.2; PJM Manual 14D, Appendix A ¶ 6.  The load in this configuration is not required to carry reserves and may lean on the PJM system when the co-located generation is on a full or partial outage or if the load exceeds the rating of the co-located generation.  Therefore, adding load to PJM without reserves will degrade reliability to worse than 1 in 10 (increase loss of load expectation (LOLE) to greater than 0.1 days/year).  PJM accommodates some level of this configuration through a settlement agreement in 2006 that allows the PJM LOLE to be relaxed from 1 in 10 years to 1 in 9.5 years.  This analysis is updated each year and historically has resulted in a cap of approximately 2000 MW of which about 1300 MW is already used. Tariff, Part III, section 34.3; PJM Manual 14D, Appendix A ¶ 66.  There are also performance requirements for generation associated with this configuration.  Therefore, large load additions located behind generation is not ideal or was contemplated.

PDF page 36

36
transmission system to serve load,”56 20-years later cost causation principles may dictate a different outcome for co-located data center loads that appear to have different customer profile and load characteristics.57  At the very least, co-located data center configurations appear to require certain ancillary services (load following) and black start service.  In order for a co-location arrangement (i.e., the generator plus data center) to obtain these services, the grid itself must exist.  Ancillary services pass through transmission lines, not the air.  Therefore, cost causation principles appear to support allocating co-located arrangements ancillary service costs (at a minimum).  Further, simple netting may not capture the costs “caused” by co-located data center arrangements.  Indeed, it is possible that such arrangements (depending on how they are structured) could avoid all costs because they would always net to zero (meaning the entire data center load is supplied by the co-located generator).

In addition, the current BTM Generation concept has been used by relatively small loads and there is a Tariff cap on non-retail BTM Generation.  Allowing very large loads like data centers to net is problematic because loads in this configuration do not carry reserves.  Planning and resource adequacy will not account for loads in this configuration. See supra Section II, discussion of Option 3 including note 5 and accompanying text. In sum, discussions in the record regarding PJM’s BTM Generation rules raise questions about the status of those rules.  PJM is open to exploring whether large, co- located load additions can and should be differentiated from instances where the current, BTM Generation rules apply and whether the 20-year-old method of allocating costs

56 PJM Interconnection, L.L.C., 107 FERC ¶ 61,113, at P 7.
57 See generally Cities of Bethany v. FERC, 727 F.2d 1131, 1138 (D.C. Cir. 1984) (recognizing different rates could be charged to different customer groups); Ala. Elec. Coop., Inc. v. FERC, 684 F.2d 20, 27-28 (D.C. Cir. 1982) (explaining undue discrimination).

PDF page 37

37
pursuant to the BTM Generation netting rules remains consistent with cost causation principles.

B. Transmission Service
i. Please explain whether and to what extent different configurations of co-located load rely on or otherwise use the transmission system to receive power, directly or indirectly, from the co-located

generator.
PJM Response:
Please see the chart attached as Exhibit A to this submission and the Executive Summary which describes the various options identified, which explain how different configurations rely on the transmission system.  By way of further response, PJM also directs the Commission to the statement of Stu Bresler filed in the Technical Conference, Docket No. AD24-11, which is attached hereto as Exhibit B.58

ii. Please explain whether and to what extent different co-location configurations impose costs on the transmission system or increase transmission costs allocated to other parties.  How can those costs be approximated, given that certain co-location configurations may change power flows on the grid and necessitate upgrades to the

transmission system?  Retail loads typically take service from
wholesale entities that pay for Network Integration Transmission Service that allocates these costs; co-located loads may not.

Network Loads pay directly for Network Integration Transmission
Service.  How should PJM estimate the effects that different
configurations of co-located load have on the transmission system? Should these costs be passed through to co-location arrangements in some way, and, if so, how?

PJM Response:
PJM looks forward to continued engagement with the Transmission Owners and other stakeholders on these important questions of cost allocation, in particular how PJM

58 Large Loads Co-located at Generation Facilities, Statement of Frederick S. “Stu” Bresler on Behalf of PJM Interconnection, L.L.C., Docket No. AD24-11-000 (Nov. 4, 2024).

PDF page 38

38
should estimate the effects that different configurations of co-located load have on the transmission system and how costs should be passed through.  A few initial observations include that incremental load gives rise to incremental system costs.  But the extent of those costs appears to vary based on the nature of the particular co-location arrangement under discussion.  PJM’s identified options attempt to follow this causal approach when

discussing potential grid services consumed and associated charges.  In some co-location arrangements, it may be worthwhile to consider new rate design constructs and compare them to see how they align with cost causation principles.  These are details that PJM and its stakeholders must continue to work through together.

iii. Please explain whether co-location arrangements are or should be
required to take Network Integration Transmission Service or
Point-to-Point Transmission Service; or whether a more tailored
new category of transmission service is warranted.  Please also
address any cost allocation implications of your position on this
issue.
PJM Response:
Please see the chart attached as Exhibit A to this submission.
By way of further response, PJM continues to prefer that co-location arrangements
be designated “Network Load”59 in front of the meter.  This may be required in some states pursuant to state exclusive franchise territory law, and it may otherwise follow in jurisdictions where the load is designated as such consistent with PJM’s Tariff.  However,

59 Tariff, Part I, Definitions – L - M - N (“Network Load” shall mean the load that a Network Customer designates for Network Integration Transmission Service under Tariff, Part III.  The Network Customer’s Network Load shall include all load (including losses, Non-Dispatched Charging Energy, and Load Serving Charging Energy) served by the output of any Network Resources designated by the Network Customer.  A Network Customer may elect to designate less than its total load as Network Load but may not designate only part of the load at a discrete Point of Delivery.  Where an Eligible Customer has elected not to designate a particular load at discrete points of delivery as Network Load, the Eligible Customer is responsible for making separate arrangements under Tariff, Part II for any Point-To-Point Transmission Service that may be necessary for such non-designated load.  Network Load shall not include Dispatched Charging Energy.”).

PDF page 39

39
PJM does present two options (Option 4 and 5) where the co-located load may not be
designated as Network Load depending on specific state laws.
PJM prefers “Network Load” status because there is:
• Less operating complexity and reduced dependence on protective schemes, which
are designed to address N-1 conditions and can misoperate;60
• More reliable service for these critical loads;61
• Enhanced ability to manage load curtailment priority in emergency conditions;62
• Greater access to potential Demand Response capabilities of large co-located loads, including from switching to backup generation (e.g., diesel units) on site; 63

• More comprehensive and holistic system planning based on Network Load status;
and64

60 See PJM Interconnection, LLC, Exelon and AEP Request for Leave to Answer and Answer to Susquehanna Nuclear LLC, PJM, Constellation, Vistra, Calpine, and PPL, Docket No. ER24-2172-000, at 23 (July 17, 2024) (“We know that a unit at this facility had an unplanned outage in November 2023, and it appears no load was dropped—suggesting that the load just relied on PJM for its supply.”); Event Notification Report for November 13, 2023, United States Nuclear Regulatory Commission, https://www.nrc.gov/reading- rm/doc-collections/event-status/event/2023/20231113en.html (last visited Mar. 21, 2025).
61 When a customer takes Network Service, the transmission provider (here, PJM) offers the Network Customer the ability to serve its Network Load in a manner comparable to that in which each Transmission Owner utilizes the Transmission System to serve its Native Load Customers consistent with their obligation to serve.  Tariff, Part III, Preamble (“Network Integration Transmission Service allows the Network Customer to integrate, economically dispatch and regulate its current and planned Network Resources to serve its Network Load in a manner comparable to that in which each Transmission Owner utilizes the Transmission System to serve its Native Load Customers.  Network Integration Transmission Service also may be used by the Network Customer to deliver economy energy purchases to its Network Load from non- designated resources on an as-available basis without additional charge.”); Tariff, Part I, Definitions — L - M - N ("Native Load Customers" defined as “the wholesale and retail power customers of a Transmission Owner on whose behalf the Transmission Owner, by statute, franchise, regulatory requirement, or contract, has undertaken an obligation to construct and operate the Transmission Owner's system to meet the reliable electric needs of such customers.”).
62 See Tariff, Part III, section 33 (Load Shedding and Curtailments). 63 See infra PJM response to question F.ii.
64 The transmission provider incorporates the Network Customer’s resources and loads into its own long- term planning.  See Transmission Access Pol'y Study Grp. v. FERC, 225 F.3d 667, 725 (D.C. Cir. 2000).  In the context of new Network Load, for planning purposes, PJM assumes that it must serve the customer’s full load during peak conditions on the system.  See id. at 726 (“[N]etwork service, as the Commission defined it, means that network customers can call upon the transmission provider to supply not just some, but all of their load at any given moment, when for instance they experience blackouts or brownouts.”).  As a result, PJM will include the customer’s full load in the RPM for purposes of procuring adequate capacity to serve the load.  In addition, PJM will include the full load in the Load Forecast for purposes of PJM’s transmission planning with RTEP.  Tariff, Part III, section 28.2 (“The Transmission Provider shall include the Network Customer's Network Load in the Transmission System planning and the Transmission Owners shall, consistent with the terms and conditions of the Tariff, the Operating Agreement, and Good Utility Practice, endeavor to construct and place into service sufficient transfer capability to deliver the Network Customer's Network Resources to serve its Network Load on a basis comparable to the delivery of each Transmission Owner's own generating and purchased resources to its Native Load Customers.”).

PDF page 40

40
• Less negative implications for resource adequacy if it is accompanied by some of
the optional service offerings (such as Demand Response, incentives for bringing
incremental generation or the use of a new non-capacity backed service).
Pursuant to the Tariff, new Network Customers must provide PJM as much notice
as reasonably practicable to be added to the system.65  The affected Transmission Owners then use due diligence to install any transmission facilities required to interconnect the new Network Load.66  The costs of new facilities required to interconnect the new Network Load are charged to the Network Customer in accordance with Commission policies.67

In addition, the Commission has previously and recently rejected an argument that
where a generator and load “are all in the same state, NITS charges should not be
assessed[.]”68  It may be an open question what level of NITS charges, if any, should be assessed in certain co-location arrangements in accordance with cost causation principles.

65 Id. at section 31.2.
66 Id. (“The affected Transmission Owners, in accordance with the terms and conditions of the Tariff and the Operating Agreement, will use due diligence to install any transmission facilities required to interconnect a new Network Load designated by the Network Customer.”).
67 Id. 68 Nat'l R.R. Passenger Corp. v. PPL Elec. Utils. Corp., 171 FERC ¶ 61,237, 62,763, at P 43 (“Amtrak concedes that, when power from Safe Harbor is insufficient, it uses PPL transmission facilities to obtain power. This is what it means to take and rely on network service. As the Commission and the D.C. Circuit have recognized, and as PPL argues in this proceeding, this is one of the significant benefits of network service, i.e., the transmission provider plans and provides for firm transmission capacity sufficient to meet the customer's current and projected peak loads and, as a result, a customer can call upon the transmission system to supply all of the customer's load at any given moment, even when behind the meter or alternative supply is unavailable.  Given these benefits, it is appropriate that Amtrak bears the costs associated with its reliance on the transmission system, as its retail supplier, CNE, is a Network Customer relying on a Network Resource.” (emphasis added) (citation omitted)) & n.101, order denying clarification & addressing arguments raised on reh’g, 173 FERC ¶ 61,043 (2020).

PDF page 41

41
iv. What changes to the rates, terms, and conditions of Network
Integration Transmission Service or Point-to-Point Transmission
Service or, alternatively, what new form of transmission service(s)
may be necessary for different configurations of co-location to
ensure that the Tariff is consistent with cost causation principles
and the beneficiary pays principle.
PJM Response:
Please see the chart attached as Exhibit A to this submission for some of PJM’s preliminary observations.

By way of further response, for purposes of NITS cost allocation, “[a]lthough PJM implements the cost allocation provisions of Schedule 12 of the Tariff, the cost allocation method is determined by the PJM Transmission Owners, and it is the PJM Transmission Owners, not PJM, that have the section 205 filing rights for the PJM cost allocation method.”69 PJM retains more robust filing rights over changes to ancillary services cost allocation.  PJM looks forward to continued engagement with the Transmission Owners and other stakeholders on these important questions of cost allocation.

69 See Linden VFT, LLC v. Pub. Serv. Elec. and Gas Co., 161 FERC ¶ 61,264, at P 31 n.44 (2017) (citing Atl. City Elec. Co.,295 F.3d 1).

PDF page 42

42
v. Parties may also wish to address how to determine which co-located
load configurations should be required to take Network Integration
Transmission Service or Point-to-Point Transmission Service or a
new form of transmission service (i.e., whether generalized policies
or tests, such as a multi-factor test, to be applied case-by-case, may
be appropriate), as well as the magnitude (i.e., how the service taken
by co-located load compares to service by other types of load).  For
example, if a co-located generator is synchronized to the grid but
the load can be configured to be wholly isolated from the grid in the
event the co-located generator trips offline, what technical and
operational factors should determine whether the co-location
arrangement still relies on the transmission system in ways that
warrant a requirement that the co-located load take Network
Integration Transmission Service or Point-to-Point Transmission
Service or a new form of transmission service?  Are there potential
co-located load configurations for which tailored approaches may
be appropriate.
PJM Response:
Please see the chart attached as Exhibit A to this submission for some of PJM’s preliminary observations regarding this question.

By way of further response, PJM objects to the question’s use of the phrase “wholly isolated from the grid” as it is contrary to engineering and economic principles.  The notion that any of the proposed co-location arrangements can be “wholly isolated” is misleading. The load and generator are connected to and synchronized with the multi-state bulk power system.  It is not operating as a micro grid (nor can it if the generating facility is a nuclear unit).  Nor is the generator delivering power through an intermediary to a load with a breaker open.  Further, by way of example, there are obligations to ensure power to nuclear plants to ensure safe shutdown (among other things).  The load and generator are benefiting from ancillary services (including but not limited to black start).  Any system protection

PDF page 43

43
facilities are designed to only handle less complex N-1 conditions, and can misoperate (and indeed have misoperated).70

vi. With respect to the Guidance Document, please explain what it means to be “electrically connected and synchronized to the PJM

Transmission System when consuming power” and how that
implicates the use of Network Integration Transmission Service or Point-to-Point Transmission Service or a new form of transmission service.

PJM Response:
Please see the chart attached as Exhibit A to this submission for some of PJM’s preliminary observations regarding the implications of being connected and synchronized to the grid.

Synchronizing to the grid means the generator matches the voltage, frequency, and phase of the entire grid (including all load connected to the system) before connecting to the grid in order to facilitate safe and stable power transfer.

As noted above, co-located load is connected to and synchronized with the multi- state bulk power system.  At bare minimum, it is benefiting from ancillary services.

vii. What operational or commercial factors of a co-location
arrangement would result in a co-located load not needing to take any form of transmission service, including what types of special protection schemes or backup arrangements may be necessary to

ensure the co-located load never takes any form of transmission
service?
PJM Response:
Please see the chart attached as Exhibit A to this submission for some of PJM’s preliminary observations.

70 See also infra response to question B.vii.

PDF page 44

44
Absent an arrangement where both the load and the generator are completely isolated and physically disconnected from the grid, (a situation which is very different from the claimed “totally isolated” configuration offered by some in these proceedings), PJM is not aware of a configuration that would “ensure the co-located load never takes any form of transmission service.”  As noted above, grid-connected facilities benefit from their connection and should pay for grid services consumed.

The challenge with an arrangement where there is load located behind a generator Point of Interconnection lies in how such a configuration or special protection scheme could be designed to never fail and cover all potential operating conditions (including generator outages and complex scenarios beyond the N-1 conditions addressed by the system protection facilities).71

For example, it is possible to develop a special protection scheme that could disconnect the load if the local generator trips.  This scheme could be developed with sufficient redundancy to help better ensure activation.  However, it is always possible that the protection system could misoperate, be disabled, or degrade.  If this occurs, the load would end up taking service from the grid until manual action could be taken to remove the load.  In fact, in the few conditions where such schemes exists on the PJM system, PJM has observed these protection schemes can fail, and the load has taken service from the grid.

In addition to the special protection scheme concerns, there are other challenges with isolating the load that come into play and could not be covered by a special protection scheme.  These include unplanned generator run-backs or reductions in output, generator

71 See also supra PJM’s response to question B.v.

PDF page 45

45
MW output oscillations, and co-located load utilization fluctuations.  When these conditions occur, they result in brief, but routine, imbalances between the load and the generation that would need to rely on the grid to balance.

C. Ancillary or other wholesale services
i. Please explain whether and to what extent different configurations of co-location arrangements rely on or benefit from ancillary services or black start services and, if so, provide specific details about the type of service and how the co-location arrangement relies on it.  To what extent are these benefits distinct from the benefits that other Network Integration Transmission Service and Point-to- Point Transmission Service customers derive from ancillary

services?
PJM Response:
Please see the chart attached as Exhibit A to this submission and associated explanation above, see supra Section II, for some of PJM’s preliminary observations.  PJM looks forward to continued engagement with the Transmission Owners and other stakeholders on these important questions of cost allocation.

ii. Please explain whether and to what extent co-location
arrangements impose costs related to ancillary services or black start services or increase the costs for such services allocated to other parties and how those costs could be approximated.

PJM Response:
Please see the chart attached as Exhibit A to this submission and associated explanation above, see supra Section II, for some of PJM’s preliminary observations.  By way of further response, please see PJM’s responses to questions A.iv.

PDF page 46

46
iii. Please explain whether and to what extent co-location
arrangements use, benefit from, provide, or contribute to the need for transmission system services in a manner that does not fit into a pre-existing category of ancillary services or black start services, and, if so, should new categories of services be created to

accommodate that use?  Alternatively, please explain whether an alternative mechanism of cost allocation for pre-existing ancillary services would be more appropriate.

PJM Response:
Please see the chart attached as Exhibit A to this submission for some of PJM’s preliminary observations.  PJM looks forward to continued engagement with the Transmission Owners and other stakeholders on these important questions of cost allocation.

iv. What changes to rates, terms, and conditions of ancillary services, including ancillary services procured in PJM’s markets, are

necessary for different configurations of co-location arrangements to ensure that the Tariff is consistent with cost causation principles and the beneficiary pays principle.

PJM Response:
Please see the chart attached as Exhibit A to this submission for some of PJM’s preliminary observations.  PJM looks forward to continued engagement with the Transmission Owners and other stakeholders on these important questions of cost allocation.

v. Please explain how PJM should determine which co-located load configurations take ancillary services or black start services (i.e., whether generalized policies or tests, such as a multi-factor test, to be applied case-by-case may be appropriate), as well as the amount of such service (i.e., how the service taken by co-located load compares to service taken by other types of load).

PJM Response:
Please see the chart attached as Exhibit A and associated explanation above, see supra Section II, to this submission for some of PJM’s preliminary observations.  PJM

PDF page 47

47
looks forward to continued engagement with the Transmission Owners and other stakeholders on these important questions of cost allocation.

D. Interconnection Procedures and Cost Allocation
i. Does the necessary study process adequately address potential
impacts caused by a co-location arrangement or is an additional
study or new study process warranted, e.g., a system impact study
or generator deactivation study?  PJM should provide the details
regarding the geographic scope of the existing necessary study
process, what is studied, and how the results are reported, including
what opportunities stakeholders, the interconnected transmission
owner, or the PJM IMM have to review the results, if any.
PJM Response:
As discussed elsewhere in this submission, the necessary study process is among several methods of study that may employed to evaluate co-location arrangements, although the extent to which necessary studies apply and for what purposes varies depending upon the type of co-location arrangement under study.

The necessary study recognizes and evaluates changes that have been made to a generator’s facilities that typically have relatively small MW impacts on its ability to deliver less power to the grid than the configuration reflected in an existing service agreement.  PJM does not have a tariffed study process for load (that is not PJM Network Load) locating behind a generator’s Point of Interconnection.  As a result, PJM has used the necessary study consistent with the Tariff’s intended use:  to study modification to an existing interconnection.  The type of interconnection and whether that load is Network Load or behind the meter load largely drives the scope of the necessary studies process. Before providing a broader overview of the necessary study process, understanding a few threshold points will assist in navigating the discussion about this type of study and when it is implicated.

PDF page 48

48
As explained above, any configuration where the load is Network Load (Options 2, 3, 6, 7, and 8, and in some circumstances Options 4 and 5) results in a necessary study that is limited in scope to generator interconnection modifications.  Load studies would be performed through traditional Transmission Owner/Electric Distribution Company-driven retail load integration processes.72  While stakeholder (including the Organization of PJM States, Inc. and Exelon) and Commission comments and questions probe the sufficiency of the necessary study agreement/study process for load integrations, only two of the proposed options (Options 4 and 5 if load is not designated as Network Load) could involve a load modification study.  Given the other options for co-locating load, concerns about the nature of the necessary study process implicated by Options 4 and 5 may be somewhat relieved. In any event, should the Commission sanction further exploration of Options 4 and 5, PJM will explore opportunities to enhance the visibility of the necessary study process and results where load integrations are introduced through such a process (subject to potential CEII and other concerns).

For a load co-locating with an existing generation resource and not seeking to be a Network Load, a necessary study request must be submitted.  PJM’s necessary study process proceeds pursuant to PJM Tariff, Part VI, Attachment O, Appendix 2, section 3, PJM Tariff, Part IX, Subpart B, Appendix 2, section 3, and section 4.5 of PJM Manual 14G.  In the general run of cases involving co-location arrangements requiring modifications to the interconnection, the generator provides PJM and the Transmission Owner with notice of any planned modifications to a co-located Customer Facility and

72 Where Network Load or when designated as such, the load would submit a request to the relevant Transmission Owner or EDC.  The Transmission Owner would perform load studies to identify upgrades to ensure deliverability and analyze relay and protection scheme changes required to accommodate the load.

PDF page 49

49
shall provide the relevant drawings, plans, specifications, and models to PJM and the Transmission Owner in advance of beginning the work.  Such advance notification is required so that PJM and the Transmission Owner can evaluate potential reliability impacts of the proposed co-located load configuration, including verification about whether and if adequate protection is in place to prevent the unexpected withdrawal of power at the Point of Interconnection for the co-located Customer Facility as may be necessary depending upon the requested configuration.

The necessary studies process provides PJM and the interconnecting Transmission Owner an opportunity to perform studies to evaluate the potential reliability impact of a proposed addition or reduction of a co-located load configuration on the PJM Transmission System, and determine what, if any, system reinforcements are required prior to the addition or reduction of the planned co-located load configuration.  PJM’s studies of co- located load that is not designated as Network Load would be for the full amount of load and reflecting any Capacity Interconnection Rights reductions, and involve generation deliverability, N-1 and N-1-1 thermal and voltage studies, special protection systems review, baseline stability, and, if applicable, a nuclear plant interface requirements voltage analysis.

Prior to beginning the necessary studies process, a necessary studies agreement must be drafted and executed by PJM and the Interconnection Customer, a necessary study deposit provided, and all required technical data submitted. In some instances, the Transmission Owner may require additional studies (such as protection system or metering modifications) based on the planned co-located load configuration, and such studies may result in additional study costs. The execution of a Construction Service Agreement may be required if the results of the necessary studies process identifies the need to construct

PDF page 50

50
system reinforcements and the related PJM interconnection service agreement would be amended to reflect these necessary system upgrades, related costs, and posting of the requisite security.

Any applicable PJM interconnection service agreement must be executed and/or amended by all three parties (PJM, the interconnecting Transmission Owner, and the Interconnection Customer) to reflect all changes resulting from the incorporation of a co- located load configuration.  Service to the co-located load pursuant to the co-located load configuration may not commence until the necessary PJM interconnection service agreement(s) has been fully executed by the parties, filed with and accepted by the Commission, and all required system reinforcements, system protection facilities, and metering are in place.

By way of comparison to the necessary study, a deactivation study would not be appropriate for co-location arrangements, because deactivation studies do not contemplate the complete retirement of the generation resource.  Deactivation studies are designed for the complete cessation of operations by a generator.  In a co-location arrangement, the generator will remain interconnected with the PJM grid and capable of injecting power onto the grid, which is why the facility will retain its Maximum Facility Output.

PDF page 51

51
ii. Please explain whether PJM’s necessary study process allows a co-
location arrangement to demonstrate its capability to flexibly adjust
its withdrawals from or injections to the transmission system (e.g.,
by using secondary backup generation or by curtailing on-site load),
and reflect this capability in the operating assumptions PJM
considers when estimating the co-location arrangement’s impacts
on the transmission system?  If not, would it be appropriate to
establish a new or revised study process that allows for such a
demonstration?
PJM Response:
Yes.  By way of further information, where certain co-located load configurations are involved (particularly Options 4 and 5 in Exhibit A), the base case configuration for the PJM necessary study reflects the generator’s Capacity Interconnection Rights (“CIRs”) being reduced by the expected peak MW utilization of the co-located load.  Under this configuration and study, the load is assumed to never take power from the grid.  And the Maximum Facility Output of the generator is not adjusted in this study, but with the co- located load modeled as always on, this offsets the net generator output.  No sensitivity studies are run with this load taking service from the grid or from any other PJM Network Resource.

If the results of the necessary study indicate a thermal or voltage violation consistent with PJM and/or local Transmission Owner Planning criteria, this violation must be mitigated before the load can be added.  Such violations have been mitigated by generators, and this has been memorialized through an agreed-upon Construction Services Agreement with the Transmission Owner to reflect changes needed on Transmission

PDF page 52

52
Owner systems and associated costs,73 or it is the responsibility of the Generation Owner if the changes are to take place behind the Point of Interconnection.

Under certain co-located load arrangements, it is possible that the Generation
Owner could propose a special protection scheme or Remedial Action Scheme (“RAS”) to reduce the load under certain conditions (where, for example, the generating unit comes offline).  If such a configuration were permitted by the Commission, PJM would require language similar to the protection facilities language proposed in the most- recently filed Susquehanna ISA.74  If and where such facilities might misoperate, additional new language should be developed to require the generator to take immediate steps to stop the flow of energy from the grid to any co-located load or risk breach and non-compliance (given the absence of contractual privity by and among PJM, the Transmission Owner, and the co-located load in certain situations).

iii. What changes to interconnection procedures and agreements may
be necessary to ensure that PJM identifies the reliability impact to
the transmission system of load co-locating with existing generation
including the need for dynamic response models?
PJM Response:
PJM’s sets forth more detailed information about the nature of the studies
performed relating to co-located load by and among the various involved entities throughout this submission.

73 See PJM Interconnection, L.L.C., 190 FERC ¶ 61,080 (2025) (accepting interconnection construction service agreement assigning upgrade costs to generator seeking to modify interconnection to accommodate co-located load).
74 See, e.g., Susquehanna ISA, Schedule F, Part F.4.b (PJM and Transmission “reserve their respective rights to take all actions each may deem necessary to protect the Transmission System, up to and including declaring an Emergency Condition and taking Immediate Action to disconnect the Customer Facility . . . and the Co- Located Load will not be reconnected as co-located load without approval of Transmission Provider and Interconnected Transmission Owner”).

PDF page 53

53
In response to this question’s specific prompt about dynamic response models, today, PJM conducts dynamic studies for co-located load projects.  All applicable North American Electric Reliability Corporation (“NERC”), PJM, and Transmission Owner- specific contingencies and criteria are evaluated.

For such dynamic studies, co-located loads are modeled in detail within both power flow and dynamic models.  Step-down transformers are explicitly represented, and co- located loads are modeled using composite load models, which capture the dynamic behaviors of power electronics, cooling, and lighting loads.

Since 2024, PJM has been also collecting more granular data using the NERC Data Center Load Information Survey template to evaluate the impact of large data center co- located load ramping behaviors.  PJM typically assesses the stability impact of co-located loads under light-load and summer-peak conditions in accordance with its stability analysis methodology.

By way of further response, PJM awaits Commission guidance and stakeholder engagement on the options presented in Exhibit A and on any other options that may be offered in this proceeding.  PJM will continue to evaluate what, if any, changes to interconnection procedures and agreements may be necessary pending receipt of that guidance and feedback.

PDF page 54

54
iv. To what extent does a co-location arrangement raise potentially
distinct cost-allocation issues relative to a deactivating generator
that causes the need for transmission upgrades?  What principles
should the Commission apply to allocate the costs of any
transmission upgrades needed to mitigate the impacts of co-locating
load?  What steps should PJM take to ensure these costs are
transparent to all parties?
PJM Response:
Transmission upgrade costs arising from a deactivating generator are allocated to load consistent with existing RTEP processes and cost allocation methodologies.  And the deactivation process proceeds pursuant to Part V of the PJM Tariff, and relates to situations in which a generating unit will cease to operate in its entirety in a state disconnected from the grid.

In contrast, the transmission upgrade costs for co-location arrangements identified during the necessary study process may be cost allocated differently than the deactivation- related upgrade costs.  For example, in a situation where state law may permit a co-located load to be directly connected to the grid with no back flow (New Options 4 and 5), transmission upgrades may be cost allocated directly to the generator seeking to modify its interconnection to accommodate this configuration.75

In a situation where a co-located load will be Network Load (either outright or in a configuration where it may seek back-up service from the local utility), the large load is studied and could be connected to the grid pursuant to the existing traditional load interconnection processes.  These processes and associated cost allocation methodologies are discussed at the beginning of this submission.

75 See PJM Interconnection, L.L.C., 190 FERC ¶ 61,080 (accepting interconnection construction service agreement assigning upgrade costs to generator seeking to modify interconnection to accommodate co- located load).

PDF page 55

55
v. Are changes needed to how PJM allocates the costs of any
transmission upgrades needed to mitigate the transmission system impacts of co-locating load, if any, including whether the costs of those upgrades can ever be allocated to a party other than the co- located

generator,
co-located
load,
and/or
co-location
arrangement?
PJM Response:
Please see the chart attached as Exhibit A to this submission for some of PJM’s preliminary observations, and PJM’s response to question D. iv, supra.

vi. Are changes to the pro forma interconnection-related agreements necessary to accommodate the addition of co-located load to

existing generation?
PJM Response:
PJM awaits Commission guidance and stakeholder engagement on the options presented in Exhibit A and other options that may be offered in this proceeding.  PJM will evaluate what, if any, changes to interconnection-related agreements may be necessary pending receipt of that guidance and feedback.

vii. Please explain whether changes to interconnection procedures and agreements are necessary to accommodate new generation

interconnecting with co-located load, including whether the existing queue process is sufficient for such arrangements?

PJM Response:
Please see the chart attached as Exhibit A to this submission for some of PJM’s preliminary observations.  To the extent any changes to interconnection procedures and agreements are necessary, PJM awaits Commission guidance on New Option 6 and any guidance on enhancing the transparency of the necessary study process.

PDF page 56

56
viii. Please explain whether or not it would be appropriate to establish an interconnection study process outside of PJM’s interconnection

queue process for newly interconnecting co-location arrangements
that do not exchange power with the transmission system and do not
require network upgrades?
PJM Response:
It would not be appropriate to establish an interconnection study process outside of PJM’s interconnecting queue process.  The necessary study process is already a study process that exists outside the queue and is subject to terms and conditions of Commission- accepted interconnection agreements.  As PJM explained above, the necessary study process is capable of incorporating and evaluating the impact of co-located arrangements. An additional queue, beyond the existing queue and the necessary study process, is not necessary.  Moreover, large load additions that are Network Load are principally studied by individual Transmission Owners/EDCs through their own processes.

ix. A generator with a co-located load that is not a party to a
transmission service agreement is arguably distinguishable from
other generators.  To the extent co-located arrangements create
costs, or benefit from bulk power system services, but the generator and load are not exposed to these costs because of their contractual relationship, should PJM modify the Tariff and related agreements

to allocate those costs to the generator directly?
PJM Response:
Yes.  PJM anticipates that it (and the Transmission Owners) would have to modify its Tariff and related agreements to allocate costs to generators and/or load as the Commission determines necessary and appropriate.

PDF page 57

57
E. PJM Capacity Market, Reliability, and Resource Adequacy
i. What changes to PJM’s capacity market rules are necessary to
ensure that the Tariff specifies how co-located generation and/or
load participates in the capacity market in a way that reflects the
potentially unique physical and operational characteristics of the
co-location arrangement (e.g., the presence of secondary backup
generation, the capability to curtail on-site load or other
operational flexibilities, among others) and is otherwise just,
reasonable, and not unduly discriminatory or preferential?
PJM Response:
PJM’s option 5 addresses the means by which a secondary backup unit at a Customer Facility may operate, and what follows is a rationale for this option and a discussion of factors a generator considering this option should evaluate before pursuing it.  For discussions of other potential operational flexibilities, see the discussions throughout regarding Demand Response/Option 8 and a curtailable non-capacity backed service/Option 7.

As a baseline, PJM does not believe that any changes to PJM’s capacity market rules are necessary to accommodate co-location arrangements.  Depending on the configuration, co-location has the same implications for resource adequacy as load that is not co-located.  These implications then impact the quantities of resources available to clear in the market and the resulting prices paid by customers.  PJM does not believe that broad changes in capacity market design are warranted based on co-located load. All Generation Capacity Resources must offer their full Accredited Unforced Capacity into the capacity market, unless PJM has granted an exception to the must-offer requirement pursuant to the existing rules in Tariff, Attachment DD, section 6.6.  While there is an exception from the must-offer requirement where the Capacity Market Seller “has entered into a unit-specific bilateral transaction for service to load located outside the

PDF page 58

58
PJM Region,”76 there is no exception allowing Capacity Resources to not offer capacity bilaterally committed to serve load in the PJM Region.  Rather, the capacity market was designed with such bilateral intra-PJM arrangements in mind,77 allowing sellers to offer such contracted capacity as “self supply” into RPM Auctions.78  This is consistent with the notion that PJM’s resource adequacy responsibility extends to all load within the PJM Region, and PJM and the Load Serving Entities are responsible for procuring sufficient Capacity Resources to maintain reliability.  Thus, to the extent the co-located load expects to receive PJM’s resource adequacy benefits, then the generation resource must participate as Capacity Resource and could offer as “self supply” and secure a capacity commitment. To the extent the co-located load is not considered Network Load and PJM does not have any resource adequacy obligation with respect to such load, such load may not be served by installed capacity associated with an Existing Capacity Resource, as such Existing Capacity Resource has a legal obligation to offer such capacity to the PJM Region to serve PJM Region Network Load.  Accordingly, before an Existing Generation Capacity Resource (or any portion of the resource) may be allowed to exclusively serve non-PJM load, the Capacity Market Seller must request and obtain removal of Capacity Resource status for the portion of the Existing Generation Capacity Resource to be designated to serve the co-located load.  The process and timelines for removing Capacity Resource status are set forth in Tariff, Attachment DD, section 6.6(g).  The Market Monitor is required to “analyze the effects of the proposed removal of a Generation Capacity Resource

76 See Tariff, Attachment DD, section 6.6(g).
77 See, e.g., Tariff, Attachment DD, sections 3.1 (Support for Self Supply and Bilateral Transactions), 4.6 (Bilateral Capacity Transactions).
78 See Tariff, Attachment DD, section 5.2 (Nomination of Self Supplied Capacity Resources).

PDF page 59

59
from Capacity Resource status with regard to potential market power issues.”79  A request to remove Capacity Resource status will be granted only if the Market Monitor approves it and PJM agrees, or the Commission issues an order terminating the Capacity Resource status.80  Capacity Resources that give up any portion of their Capacity Resource status also forfeit the CIRs supporting such status.81

The following addresses situations that could arise in Options 4 or 5 where the co- located load is not designated Network Load, where there are multiple units at a co-located generator, and where the generator desires to use one of those units to serve as a back up to other units that may have co-located load service obligations.  Absent contrary approval from the Commission and authorization from PJM as contemplated in the Third Revised Co-Located Load filed in Docket No. ER24-2172, no portion of a committed Capacity Resource (whether composed of one or multiple physical generating units) may prioritize serving load that PJM is not responsible for serving.  Simply put, absent Commission guidance to the contrary and PJM authorization, PJM cannot be in competition with non- capacity backed co-located loads for the output of a Capacity Resource.  PJM cannot be simultaneously responsible for ensuring the energy needs of the PJM Region and unsure whether a Capacity Resource will decide to serve PJM loads or co-located loads.  Sellers should not be afforded the economic choice of following through on capacity commitments or incurring Capacity Resource Deficiency Charges and/or Non-Performance Charges. Any portion of an Existing Generation Capacity Resource that would prioritize serving co-

79 Tariff, Attachment DD, section 6.6(g).
80 Id.
81 Id. (“A Generation Capacity Resource that is removed from Capacity Resource status shall no longer qualify as an Existing Generation Capacity Resource, and the Capacity Interconnection Rights associated with such facility shall be subject to termination in accordance with the rules described in Tariff, Part VI, section 230.3.3.”).

PDF page 60

60
located loads over following PJM dispatch—whether on a primary or backup basis— should seek removal of Capacity Resource status.

ii. What Tariff change or changes to the interconnection service
agreement are necessary to ensure that PJM and the interconnected
transmission owner have sufficient visibility into the co-located load
configuration?
PJM Response:
Under PJM’s existing governing documents, there are numerous provisions in the Tariff, Amended and Restated Operating Agreement, RAA, and service agreements that require generators to provide PJM with extensive transmission level equipment modeling and data.82  That being said, unique operational procedures and data exchange requirements like those proposed in the Susquehanna ISA should be developed and specified. To ensure that the overall system will continue to operate reliably as designed or as imposed by any temporary operational conditions on the system, the service agreement (as well as other government documents) may need to further be revised.  These revisions may include obligations on the generator and the co-located end use load (to the extent they can be bound directly or indirectly) to ensure the needed protection schemes (including RAS) will continue to operate as designed and directed by PJM.  Any changes to the co-located load type, connected load level, or how it is served need to be communicated with PJM

82 See, e.g., Tariff, Attachment O, Appendix 2, schedules A-D (requiring site plans, single-line diagrams, list of metering equipment, and technical specification); Operating Agreement, section 11.3.1(b) requiring members to provide facilities as necessary for coordination with the Office of Interconnection);  RAA, Article 9, Section 3 (“[E]ach Party shall submit to the Office of the Interconnection the data and other information necessary for the performance of this Agreement as may be more fully described, in RAA, Schedule 11.”).; System Operations Division, PJM Manual 01: Control Center and Data Exchange Requirements, PJM Interconnection, L.L.C., section 5 & Attachment A (Jan. 23, 2025), https://www.pjm.com/- /media/DotCom/documents/manuals/m01.ashx.  Attachment A to Manual 01 lists the meter requirements and data specification and collections requirements.

PDF page 61

61
prior to these changes taking place and the necessary amendments to the service agreements are approved and implemented.

If the co-located load is PJM Network Load, PJM and the Transmission Owners have means through existing Tariff provisions and agreements to obtain the information to have both sufficient visibility and sufficient control of this load and ensure the load could be served reliably without compromising overall system reliability.  In addition, these documents provide a means for mitigation through Commission action if they are not adhered to.

Under certain configurations, if the co-located load is not PJM Network Load, questions arise as to how any requirements for visibility and control of the co-located load configuration are applied to that customer.  Any interconnection agreement would be between PJM and the Generation Owner because the third-party load is not a signatory to these agreements.  Pro forma agreements may require modification to specify, where applicable:  the entity(ies) that own any co-located load, what people and contact information at the co-located load should be used to communicate with such co-located load during both emergency and non-emergency situations, and whether the generator with co-located load is now functioning as an Electric Distributor under the Tariff (and analogous North American Electric Reliability Corporation requirements pursuant to the current Compliance Registry Criteria).83  In the case of the Susquehanna ISA, for example, PJM requested non-conforming provisions requesting such information relating to the co-

83 Operating Agreement, section 1, Definitions – E - F (defining “Electric Distributor” as “a Member that: 1) owns or leases with rights equivalent to ownership electric distribution facilities that are used to provide electric distribution service to electric load within the PJM Region; or 2) is a generation and transmission cooperative or a joint municipal agency that has a member that owns electric distribution facilities used to provide electric distribution service to electric load within the PJM Region”); Operating Agreement, section 11.3.3.

PDF page 62

62
located load.84  In that situation, the generator reaffirmed its continued rights, duties, and obligations under the ISA, notwithstanding any actions by a third party.85  This provision was in recognition of the fact that “regardless of what entity may be responsible for operational activities of the transmission facilities of the Co-Located Load [at issue in that arrangement] and regardless of the entity that may own or control the Co-Located Load itself, any breaches or non-compliances under this agreement attributed to the activities of such entities or that remain [the generator’s] obligations are the duty and responsibility of [the generator] to cure.”86  Absent such provisions, a regulatory and communication gap could arise increasing risks to reliability, among other possible concerns. By way of further response, see the response to question D.ii, supra.

iii. Please explain whether the existing Tariff rules are sufficient to
ensure resource adequacy if increasing numbers of large existing
generators choose to co-locate with load.
PJM Response:
Any additional load on the system requires either the addition of supply resources to serve that load reliably, or flexibility on the part of the load to curtail its consumption from the transmission system when necessary to maintain reliability.  For this reason, PJM has outlined three potential options relating to these considerations:  Option 6 (co-located load that elects to be Network Load and leverages provisional interconnection service or State Agreement Approach), Option 7 (co-located load that takes a new non-capacity backed service that could be curtailed in advance of emergency procedures), and Option 8 (co-located participates as Demand Response).  And as discussed below, see infra question

84 See Susquehanna ISA, Schedule F, Part G.1.
85 Susquehanna ISA, Schedule F, Part G.2.
86 Susquehanna Deficiency Response at 24.

PDF page 63

63
F.2, PJM is also exploring with regulators and generators opportunities to leverage at least 50 hours (or more) of diesel back-up generator service to enhance the available demand response portfolio.

Furthermore, the PJM markets, including the capacity market, are utilized to procure commitments from resources to provide sufficient capacity and energy to maintain reliability.  PJM has, and continues to, take steps to ensure that needed resources to serve future load requirements, particularly given anticipated resource deactivations due to policy requirements, can be integrated onto the transmission system.  PJM continues to work through the transition to the new interconnection process, and is also in the process of implementing the Reliability Resource Initiative recently approved by the Commission.87  Additional efforts that are largely out of PJM’s control are also necessary, such as more streamlined permitting and siting, to support the addition of resources that will be needed in the future on the timeline by which they will be required. These markets though, were designed and intended to be residual in nature (in fact, the primary auction in the PJM capacity market is called the Base Residual Auction for this reason) to provide physical asset owners and load servers with an additional option to satisfy their obligations, and also to establish prices that represent the marginal cost of satisfying the system’s capacity and energy requirements.  Self-supply, either through direct ownership or longer-term bilateral contracting, is a critical part of how these markets function to ensure resource development to support future reliability.  PJM looks forward to continuing to work with the Commission, states and other stakeholders to enhance

87 Only a few days ago, PJM announced that its Reliability Resource Initiative attracted 94 applications totaling 26.6 gigawatts of nameplate capacity.  See  Reliability Resource Initiative Draws 94 Applications, PJM Inside Lines (Mar. 21, 2025), https://insidelines.pjm.com/reliability-resource-initiative-draws-94- applications/.

PDF page 64

64
opportunities for forward contracting that can serve to simulate the resource additions that will be necessary to maintain system reliability.

iv. What deactivation or interconnection modification studies should
PJM undertake to ensure resource adequacy and/or protect
reliability should an existing generator seek to enter into a co-
location arrangement?  If PJM finds that the co-location would
cause reliability standards violations, what remediation techniques
would be appropriate (e.g., reliability must-run contracts, delaying
the co-location arrangement until the reliability violations are
addressed, etc.)?
PJM Response:
Whether a co-location arrangement results in the capacity associated with the co- located load leaving the capacity market is an open question that varies based upon the potential configuration and timing of the arrangement.

As discussed throughout PJM’s response, there are a number of types of co-location arrangements, and how each arrangement affects the capacity market would necessitate a fact-specific inquiry some details of which are previewed in Exhibit A.  To the extent the Existing Generation Capacity Resource relinquishes Capacity Resource status commensurate with its obligation to the co-located load, PJM’s capacity market is designed to send a price signaling the relative need for additional capacity.  If the arrangement results in the Locational Deliverability Area in which the co-location is sited needing additional capacity, the clearing price for that Locational Deliverability Area may separate from the rest of the regional transmission organization and capacity prices will increase. Further, except as otherwise stated above, PJM is not aware of any modification to PJM’s deactivation or interconnection studies required to accommodate a co-location arrangement.  To the extent the resource seeks removal of its Capacity Resource status, before such request may be granted, the Market Monitor must “analyze the effects of the

PDF page 65

65
proposed removal of a Generation Capacity Resource from Capacity Resource status with regard to potential market power issues.”88

To the extent PJM determines that the co-location arrangement would result in transmission reliability issues, upgrades would have to be funded and constructed.  See the response to question D.iv, supra.

v. What changes are necessary, if any, to other PJM planning
processes to better plan for and address the resource adequacy and
reliability impacts of co-location arrangements, including, for
example, whether or not the frequency of such processes might be
changed?  Similarly, should PJM consider changes to load
forecasting methods, informational postings, or the reserve margin
study process to better plan for and address the resource adequacy
and reliability impacts of co-location arrangements?
PJM Response:
There may be opportunities to clarify or enhance existing planning processes.  One possible area of exploration could relate to addressing risks that arise based on the existing load forecasting process.

During the annual load forecasting process, PJM makes a request to the EDCs/Load Serving Entities (“LSEs”) to submit large load additions that would not be captured in the parameters that are typically incorporated.  This request is made in July of each year for the following year’s forecast.  EDCs/LSEs submit their additions and PJM reviews each one and consults with the submitter to ask questions and conform the data for use in the forecast (e.g. converting capacity to demand, assessing contractual obligations, etc.).  The EDCs/LSEs must present this data at the September/October Load Analysis Subcommittee and defend their submissions to stakeholders.  Finally, PJM presents what is ultimately accepted into the Load Forecast for the subsequent year.

88 Tariff, Attachment DD, section 6.6(g).

PDF page 66

66
With any forecast of future load growth, additional transmission and generation capacity may be required, and there is the risk of overbuilding due to a forecast that is too high, or underbuilding due to a forecast that is too low.  The same is true with respect to large load additions, regardless of whether the load is co-located with generation.  Given the potential size of these individual, large load additions that are in the forecast, uncertainty with respect to whether the large loads are actually added to the system could cause either overbuild or underbuild to occur based on a single customer addition. The method by which any required generation and/or transmission capacity

additions are procured also has implications for who carries the risk of forecasted large load additions not materializing.  For example, if large load additions are added to the load forecast utilized in forward capacity auctions, the additional demand can result in price increases applicable to all demand.  To the extent the forecasted load additions do not actually materialize, these higher capacity costs would be allocated to all other load on the system.  Were the large loads to enter into bilateral or self-supply arrangements to serve their capacity needs, the parties to those arrangements would wear the risk of the large load not actually coming on line.  Similar implications may exist for transmission cost allocation as well.

Given these dynamics, opportunities to enhance the load forecasting process and address the potential consequences of that process may be worthy of exploration. Commission guidance and stakeholder engagement on this specific issue and the options discussed herein and presented in Exhibit A and any other options that may be lodged in this proceeding will assist PJM in evaluating and identifying  any changes to planning processes.

PDF page 67

67
vi. Under what circumstances can PJM direct the operators of co-
location arrangements to shed such load if deemed necessary to
preserve system reliability during a declared emergency?
PJM Response:
PJM has existing authority under its governing documents to direct PJM Members,
both generators and electric distributors, to take certain mitigating actions during an emergency.89  However, PJM does not presently have authority to direct retail end-users, who are not PJM Members and who do not participate in PJM’s markets, to reduce their

load consumption.  Such action would have to be coordinated through the applicable PJM Member—whether a generator or an electric distributor—in the context of shedding a co- located load. If a load is registered as Demand Response, then

89 See, e.g., Tariff, Attachment K-Appendix, section 1.7.15 (“Consistent with Good Utility Practice, the Office of the Interconnection shall be authorized to direct or coordinate corrective action, whether or not specified in the PJM Manuals, as necessary to alleviate unusual conditions that threaten the integrity or reliability of the PJM Region, or the regional power system.”); Operating Agreement, Section 11.3.1 (“To facilitate and provide for the work of the Office of the Interconnection and of the several committees appointed by the Members Committee, each Member shall, to the extent applicable . . . (e) Comply with the requirements of the PJM Manuals and all directives of the Office of the Interconnection to take any action for the purpose of managing, alleviating or ending an Emergency, and authorize the Office of the Interconnection to direct the transfer or interruption of the delivery of energy on their behalf to meet an Emergency and to implement agreements with other Control Areas interconnected with the PJM Region for the mutual provision of service to meet an Emergency, and be subject to the emergency procedure charges specified in Operating Agreement, Schedule 9 for any failure to follow the Emergency instructions of the Office of the Interconnection.”); id. at section 11.3.3 (“In addition to any of the foregoing responsibilities that may be applicable, each Member that is an Electric Distributor, whether or not that Member votes in the Members Committee in the Electric Distributor sector or meets the eligibility requirements for any other sector of the Members Committee, shall . . . (a) Accept, comply with or be compatible with all standards applicable within the PJM Region with respect to system design, equipment ratings, operating practices and maintenance practices as set forth in the PJM Manuals, or be subject to an interconnected Member’s requirements relating to the foregoing, so that sufficient electrical equipment, control capability, information and communication are available to the Office of the Interconnection for planning and operation of the PJM Region . . . (c) Maintain or arrange for a portion of its connected load to be subject to control by automatic under frequency, under-voltage, or other load-shedding devices at least equal to the levels established pursuant to the Reliability Assurance Agreement, or be subject to another Member’s control for these purposes . . . (e) Shed connected load, share Generation Capacity Resources and take such other coordination actions as may be necessary in accordance with the directions of the Office of the Interconnection in Emergencies.”).

PDF page 68

68
PJM may direct curtailment service providers to direct their customers to shed load. If Network Load but that load is not serving as Demand Response, then PJM may issue a load shed directive to a Transmission Owner who in turn determine what customers will shed load. If Network Load but that load is not serving as Demand Response, then PJM may issue a load shed directive to a Transmission Owner who in turn determine what customers will shed load.

F. Other
i. Are any changes to PJM’s energy or ancillary services market rules
necessary to address co-location arrangements?
PJM Response:
Regardless of what co-location arrangements are ultimately sanctioned by the Commission, permitted by the states, and elected by developers, participants involved in co-location arrangements should pay the costs of any grid services they consume and the arrangements should be reliable and operationally manageable.  As noted in Exhibit A and herein, many co-located load configurations utilize grid support and consume ancillary services (including, for example, frequency regulation, black start service, and reactive service).  By way of further response, see PJM’s response to question A.iv, supra.

ii. Please discuss whether back-up service can provide benefits to
customers or otherwise help minimize system costs, including with
specific examples or best practices, if possible.
PJM Response:
Even when co-located with an existing generator, co-located load is often (but not always) built with an on-site backup generator to ensure continuity of operations in the event its primary power source is disrupted.  These back-up generators have the potential to provide benefits to customers and minimize system costs by participating in the PJM

PDF page 69

69
markets, but currently their use is limited by the Environmental Protection Agency’s (“EPA”) National Emissions Standards for Hazardous Air Pollutants (“NESHAP”) for stationary reciprocating internal combustion engines (“RICE”) regulations as well as other environmental restrictions depending on their particular location and permit restrictions. PJM understands that most back-up generators installed at large load centers for backup power are Tier 2 under the EPA’s regulations.  Under the EPA’s NESHAP regulations, a Tier 2 RICE that provides back-up power for a co-located load may only be used in emergency situations as declared by the Reliability Coordinator or other authorized entity or for limited periods for non-emergency purposes.  For non-emergencies, the NESHAP regulations generally prohibit Tier 2 RICE units from providing non-emergency demand response, generating income for a facility to an electric grid, or otherwise supplying power as part of a financial arrangement with another entity.90  In certain situations, the RICE Tier 2 units may provide demand response or peak load shaving in non-emergencies when local system conditions could lead to a blackout.  Specifically, these Tier 2 units may run for up to 50 hours a year when called upon by the local balancing authority or local transmission system and distribution operator to mitigate or avert voltage collapse or line overloads that could interrupt power.91  However, this run-time counts towards the unit’s overall 100-hour annual run-time limit.  As a result, these back-up generators have historically been viewed as limited in being able to provide customer and system benefits by either being a demand response resource or selling excess power into the market.  Therefore, regulatory changes to allow such unit’s ability to provide additional

90 40 C.F.R. § 60.4211(f)(3).
91 78 Fed. Reg. 6674, 6680 (2013); 40 C.F.R. § 60.4211(f)(3)(i).

PDF page 70

70
back-up service during the pendency of a declared energy emergency could be an important mechanism to address resource adequacy concerns in the short term.  Accessing this additional capability more actively may also facilitate large load interconnections, which is why PJM has included Option 8 in this response.  PJM will continue to engage with generators and state and federal regulators on these issues to further realize potential opportunities relating to back-up capabilities.

iii. Parties may also choose to address how co-location arrangements
may provide benefits, including potentially reducing required
transmission upgrades to interconnect large loads, reducing
congestion, or providing operational flexibility during system peaks
or emergencies?
PJM Response:
PJM acknowledges that participants in these proceedings have offered for consideration potential benefits of co-location arrangements, including efficiencies of siting load close to generation to conserve certain facility construction and siting costs. PJM looks forward to continued engagement with stakeholders on this issue.

iv. Parties may also address whether, and if so, how, the Tariff should be modified to best accommodate or encourage co-location

arrangements to be constructed in such a way as to minimize total
system costs or otherwise provide certain benefits, including
protections for existing customers and allocation of costs consistent
with the cost-causation principle.
PJM Response:
PJM looks forward to engagement with stakeholders and the Commission regarding the eight options outlined in Exhibit A.

PDF page 71

71
v. What Tariff provisions, if any, are necessary to ensure clarity
regarding the aspects of service to co-located load and generation
facilities that may be administered through the Tariff versus state
jurisdictional retail tariffs?
PJM Response:
Generators are obliged to comply with applicable law and requirements, including state law.92  So, too, is PJM.93  While additional Tariff revisions may not be necessary to clarify the division of labor between PJM’s federally regulated Tariff and the state retail tariffs, generators, load, and PJM will need to have assurances and an understanding of relevant law to respect the jurisdictional principles described in PJM’s answer to question A.i.

vi. We also encourage parties to address any national security
implications associated with co-location arrangements, including
with respect to the specific issues discussed in this show cause order,
and what actions, if any, the Commission should take in response.
PJM Response:
PJM acknowledges that participants in these proceedings have offered for
consideration national security implications associated with co-location arrangements, particularly where large data center loads are involved.  It is a matter of public record that there is data center development focused on directly supporting national security interests

92 See, e.g., Tariff, Attachment O, Appendix 2, section 23.1.4 (Consent and Approval) (“Such Interconnected Entity has sought or obtained, or, in accordance with the Interconnection Service Agreement will seek or obtain, each consent, approval, authorization, order, or acceptance by any Governmental Authority in connection with the execution, delivery and performance of the Interconnection Service Agreement and it will provide to any Governmental Authority notice of any actions under this Appendix 2 that are required by Applicable Laws and Regulations.”); Tariff, Part IX, subpart B, Appendix 2, section 23.1.4 (Consent and Approval) (“Such Interconnected Entity has sought or obtained, or, in accordance with the Generation Interconnection Agreement will seek or obtain, each consent, approval, authorization, order, or acceptance by any Governmental Authority in connection with the execution, delivery and performance of the Generation Interconnection Agreement and it will provide to any Governmental Authority notice of any actions under this Appendix 2 that are required by Applicable Laws and Regulations.”).
93 See, e.g., Tariff, Attachment O, Appendix 2, section 23.1.4.

PDF page 72

72
in collaboration with various government agencies.  In addition, the need to serve large data center loads is essential to furthering the nation’s strategic interests in supporting the continued growth of our nation’s AI capabilities.  PJM continues to support and facilitate attempts to develop the critical infrastructure needed to support these national security imperatives, and looks forward to continued engagement with the Commission and

stakeholders on this issue.
vii. Finally, for generation units paid for originally by consumers in
base rates prior to restructuring, is it fair and/or just and reasonable
if these units are taken out of the system’s supply stack and devoted
exclusively to serving co-location arrangements with one or a few
large customers?
PJM Response:
Exhibit A and the explanations contained herein identify potential negative
implications for resource adequacy based on the various options identified.  This question goes further and asks about whether customers have an ongoing entitlement to units remaining as capacity resources based on their previous regulatory status prior to restructuring.  Whether a specific cost is eligible for recovery is for stakeholders, the Commission, and/or appropriate state or local entities to decide.94

Respectfully submitted,

/s/ Andrew T. Swers

Craig Glazer
Vice President–Federal Government Policy
PJM Interconnection, L.L.C.
1200 G Street, N.W., Suite 600
Washington, D.C.  20005
(202) 423-4743
craig.glazer@pjm.com
Ryan J. Collins
Andrew T. Swers
Ruth M. Porter
Wright & Talisman, P.C.
1200 G Street, N.W., Suite 600
Washington, D.C.  20005
(202) 393-1200

94 See, e.g., Tariff, Part V, section 119 (“[A] Generation Owner with a generating unit proposed for Deactivation that continues operating beyond its proposed Deactivation Date may file with the Commission a cost of service rate to recover the entire cost of operating the generating unit until such time as the generating unit is deactivated.”); Operating Agreement, Schedule 6, section 1.5.8(e) (“In evaluating any cost, ROE and/or capital structure proposal, PJM is not making a determination that the cost, ROE or capital structure results in just and reasonable rates, which shall be addressed in the required rate filing with the FERC.”).

PDF page 73

73

Mark J. Stanisz
Associate General Counsel
PJM Interconnection, L.L.C.
2750 Monroe Blvd.
Audubon, PA  19403
(610) 666-8800
mark.stanisz@pjm.com
collins@wrightlaw.com
swers@wrightlaw.com
porter@wrightlaw.com

Attorneys for
PJM Interconnection, L.L.C.
March 24, 2025

PDF page 74

DRAFT  3-23-25 (6am EPT)
CERTIFICATE OF SERVICE

I hereby certify that I have this day served the foregoing document upon each person designated on the official service list compiled by the Secretary in this proceeding.

Dated at Washington, D.C., this 24th day of March 2025.
/s/ Andrew T. Swers

Andrew T. Swers

Wright & Talisman, P.C.
1200 G Street, N.W., Suite 600
Washington, D.C.  20005
(202) 393-1200

swers@wrightlaw.com

Attorney for
PJM Interconnection, L.L.C.