EL25-49-000 · 2025-03-24 · PJM Interconnection, L.L.C.

Answer of PJM Interconnection, L.L.C. to the 02/20/2025 Order Instituting Proceeding Under Section 206 of the Federal Power Act and Consolidating with Other…

Text extracted from the eLibrary original (SHA-256 c4dd59718570ea6e…). Download the original from the official source.

Contents · 9 sections
  1. I. INTRODUCTION p. 3
  2. II. EXECUTIVE SUMMARY OF EXISTING AND POTENTIAL NEW p. 5
  3. III. PJM RESPONSE TO COMMISSION QUESTIONS p. 21
  4. A. General p. 21
  5. B. Transmission Service p. 37
  6. C. Ancillary or other wholesale services p. 45
  7. D. Interconnection Procedures and Cost Allocation p. 47
  8. E. PJM Capacity Market, Reliability, and Resource Adequacy p. 57
  9. F. Other p. 68

Read topic-matched comments in EL25-49

Topics in the text: Connecting load and generation · Cost allocation · Reliability and curtailment

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

UNITED STATES OF AMERICA BEFORE THE FEDERAL ENERGY REGULATORY COMMISSION PJM Interconnection, L.L.C.
Read this passage

I. INTRODUCTION

printed heading · Topic match: Cost allocation

See Linden VFT, LLC, 161 FERC ¶ 61,264, at P 31 n.44 (2017) (“Although PJM implements the cost allocation provisions of Schedule 12 of the Tariff, the cost allocation method is determined by the PJM Transmission Owners, and it is the PJM Transmission Owners, not PJM, that have the section 205…
Read this passage Filed comments: Cost allocation

II. EXECUTIVE SUMMARY OF EXISTING AND POTENTIAL NEW

printed heading · Topic match: Connecting load and generation

Further, in deregulated states, state law may (or may not) today (or in the future) require co-located load suppliers to be licensed energy providers and/or otherwise impose limitations on such suppliers by, for example, obliging the designation of the load as Network Load, with or without netting,…
Read this passage Filed comments: Connecting load and generation

III. PJM RESPONSE TO COMMISSION QUESTIONS

printed heading

III.
Read this passage

A. General

printed heading · Topic match: Connecting load and generation

Even in the case of back-up generation (in which the load has generation that it can use to self-supply when power from the utility is not available), the load must comply with state law requirements.”). 25 (including any back-up service) were frequently addressed in separately negotiated…
Read this passage Filed comments: Connecting load and generation

B. Transmission Service

printed heading · Topic match: Connecting load and generation

By way of further response, for purposes of NITS cost allocation, “[a]lthough PJM implements the cost allocation provisions of Schedule 12 of the Tariff, the cost allocation method is determined by the PJM Transmission Owners, and it is the PJM Transmission Owners, not PJM, that have the section…
Read this passage Filed comments: Connecting load and generation

C. Ancillary or other wholesale services

printed heading · Topic match: Cost allocation

Please explain how PJM should determine which co-located load configurations take ancillary services or black start services (i.e., whether generalized policies or tests, such as a multi-factor test, to be applied case-by-case may be appropriate), as well as the amount of such service (i.e., how…
Read this passage Filed comments: Cost allocation

D. Interconnection Procedures and Cost Allocation

printed heading · Topic match: Connecting load and generation

Any applicable PJM interconnection service agreement must be executed and/or amended by all three parties (PJM, the interconnecting Transmission Owner, and the Interconnection Customer) to reflect all changes resulting from the incorporation of a co- located load configuration.
Read this passage Filed comments: Connecting load and generation

E. PJM Capacity Market, Reliability, and Resource Adequacy

printed heading · Topic match: Connecting load and generation

Pro forma agreements may require modification to specify, where applicable: the entity(ies) that own any co-located load, what people and contact information at the co-located load should be used to communicate with such co-located load during both emergency and non-emergency situations, and…
Read this passage Filed comments: Connecting load and generation

F. Other

printed heading · Topic match: Connecting load and generation

This question goes further and asks about whether customers have an ongoing entitlement to units remaining as capacity resources based on their previous regulatory status prior to restructuring.
Read this passage Filed comments: Connecting load and generation

CERTIFICATE OF SERVICE

printed heading

Dated at Washington, D.C., this 24th day of March 2025. /s/ Andrew T.