EL25-49-000 · 2025-04-09 · Talen Energy Corporation

Answer of Talen Energy Corporation in Opposition to Vistra Corp.'s Motion for Clarification and Request for Expedited Treatment

PDF page 1

UNITED STATES OF AMERICA
BEFORE THE
FEDERAL ENERGY REGULATORY COMMISSION
PJM Interconnection, L.L.C., et al.

)

Docket No. EL25-49-000
PJM Interconnection, L.L.C.

)

Docket No. ER24-2172-000

(not consolidated)

ANSWER OF
TALEN ENERGY CORPORATION
IN OPPOSITION TO
VISTRA CORP.’S MOTION FOR CLARIFICATION
AND REQUEST FOR EXPEDITED TREATMENT1

Talen Energy Corporation (“Talen”) urges the Commission to act as soon as possible to opine on the merits of Talen’s November 20, 2024 Request for Rehearing in Docket No. ER24- 2172-000 (the “SSES ISA Docket”).2  The Motion for Clarification and Request for Expedited Treatment filed by Vistra Corp. (“Vistra”) in Docket No. EL25-49-000 (the “Co-Location Show Cause Docket”) requests that the Commission act on a narrow subset of the issues raised in Talen’s Request for Rehearing and closely mirrors the issues Vistra raised in the Motion for Clarification it filed in the SSES ISA Docket.3  With respect, the Commission should not, at Vistra’s request, act in a piecemeal manner.  Talen does not seek piecemeal answers and therefore asks that the Commission deny Vistra’s motion.  Instead, the Commission should issue an order as

expeditiously as possible that substantively addresses all of the issues raised in Talen’s Request for Rehearing.4

1 This answer is submitted pursuant to Rule 213 of the Rules of Practice and Procedure of the Federal Energy Regulatory Commission (“Commission” or “FERC”).

2 PJM Interconnection, L.L.C., Docket No. ER24-2172-000, Request for Rehearing of Susquehanna Nuclear, LLC (Nov. 20, 2024) (“Request for Rehearing”).
3 PJM Interconnection, L.L.C., Docket No. ER24-2172-000, Motion for Clarification of Vistra Corp. (Dec. 2, 2024).
4 Talen filed a Petition for Review with the United States Court of Appeals for the Fifth Circuit that broadly challenges the Commission’s Order Rejecting Amendments to Interconnection Service Agreement issued in Docket No. ER24-

PDF page 2

2
I. ANSWER
Talen filed a Request for Rehearing in response to the Susquehanna ISA Order several months ago and waits for the Commission to take substantive action on its request.5  When it does speak, the Commission should provide more certainty on all the issues raised in Talen’s rehearing request.  For instance, Talen avers in its Request for Rehearing that the Commission departed from the “necessity standard” it has historically used to evaluate the need for deviations from the pro forma Interconnection Service Agreement in the Susquehanna ISA Order.6  The Request for Rehearing also asks the Commission to clarify its usage of the new “unique interest” standard which it used to evaluate Susquehanna’s amended Interconnection Service Agreement.7  Without an understanding of the circumstances under which the unique interest standard will be applied and how to meet the standard, Regional Transmission Organizations and Independent System Operators will be unable to detail the rationale for essential modifications with terms acceptable to the Commission.

The Commission’s November 1, 2024 order erred in its rulings on these issues and an appeal is pending.  Redress on these issues is just as important to Talen as the issues Vistra selectively included in its motion.  Talen would welcome a prompt and comprehensive order granting rehearing.  Indeed, granting Talen’s Request for Rehearing would be logically consistent with, and inclusive of, the findings Vistra seeks.  Talen would welcome these findings as part of a comprehensive order granting Talen’s rehearing request.8

2172-000 on November 1, 2024, including issues that go beyond those raised by Vistra in its motion.  Susquehanna Nuclear, LLC v. Federal Energy Regulatory Commission, No. 25-60019 (5th Cir. 2025).

5 See generally Request for Rehearing,
6 Id. at 8-12.
7 Id.
8 Vistra requests the Commission to clarify that “the Susquehanna ISO Order should not be read to (1) prejudge the permissibility of any particular co-location configuration, (2) indicate that the Commission generally opposes fully

PDF page 3

3
Simply put, the clarifications Vistra seeks should be made in the SSES ISA Docket, where the Commission can address all the issues pending before it.  As such, rather than issuing an order responding to Vistra’s selective requests in the Co-Location Show Cause Order docket,9 the Commission should deny Vistra’s motion and promptly issue an order granting Talen’s Request for Rehearing in the SSES ISA Docket.

II. CONCLUSION
For the aforementioned reasons, we respectfully ask the Commission to deny Vistra’s motion and provide the relief Talen requests.

Respectfully submitted,
/s/ William S. Scherman
William S. Scherman
Melinda J. Warner
Vinson & Elkins LLP
2200 Pennsylvania Avenue NW
Suite 500 West
Washington, DC 20037

Jennifer Mansh
Talen Energy Corporation
Senior Vice President, Regulatory and
External Affairs
600 Hamilton St.
Suite 600
Allentown, PA 18101
Jennifer.Mansh@TalenEnergy.com
Counsel for Talen Energy Corporation
April 9, 2025

isolated behind the meter co-located load, or (3) prohibit parties form following the currently effective tariff rules and negotiating the terms of non-conforming ISAs pursuant to existing tariff provisions.”  Motion at 5.

9 PJM Interconnection, L.L.C., et al., Docket No. EL25-49-000, Order Instituting Proceeding Under Section 206 of the Federal Power Act and Consolidating with Other Proceedings (“Show Cause Order”).

PDF page 4

4
CERTIFICATE OF SERVICE
I hereby certify that I have this day served the foregoing document upon each person designated on the official service lists compiled by the Secretary in these proceedings. Dated at Washington, DC, this 9th day of April 2025.

/s/ Melinda J. Warner
Melinda J. Warner
Vinson & Elkins LLP