EL25-49-000 · 2025-04-23 · North American Electric Reliability Corporation

Comments of the North American Electric Reliability Corporation

Text extracted from the eLibrary original (SHA-256 cde416e9a4a06f7c…). Download the original from the official source.

Contents · 5 sections
  1. I. INTRODUCTION p. 1
  2. II. COMMENTS p. 3
  3. III. CONCLUSION p. 11
  4. Attachment A p. 13
  5. Attachment B p. 23

Read topic-matched comments in EL25-49

Topics in the text: Reliability and curtailment

Source sections

Printed headings where available; page ranges otherwise. Excerpts below are selected from the text by keyword.

Opening text

opening text

EL25-49-000.1 NERC respectfully requests that the Commission accept these comments to supplement the record and provide insights into reliability considerations and NERC activities related to large loads connected to the Bulk-Power System (“BPS”).
Read this passage

I. INTRODUCTION

printed heading · Topic match: Reliability and curtailment

In addition, the Show Cause Order requests information from interested parties about the reliability and resource adequacy implications of co-located large loads.6 Through these comments, NERC seeks to provide insights into its activities examining the implications of co-located large loads and to…
Read this passage Filed comments: Reliability and curtailment

II. COMMENTS

printed heading

In February 2025, the Board held a panel discussion addressing risks related to integrating large loads.19 The Board recognized that large loads are increasingly connecting to the grid, and emphasized that integration must support reliable BPS operations rather than reduce performance.
Read this passage

III. CONCLUSION

printed heading

CONCLUSION WHEREFORE, for the reasons stated above, NERC respectfully requests that the Commission accept the comments herein.
Read this passage

CERTIFICATE OF SERVICE

printed heading

Dated at Washington, D.C. this 23rd day of April, 2025. /s/ Caelyn Palmer Caelyn Palmer Counsel for the North American Electric Reliability Corporation RELIABILITY | RESILIENCE | SECURITY
Read this passage

Attachment A

printed heading · Topic match: Reliability and curtailment

Attachment A NERC Activities and Plans to Address Reliability Impacts from Large Load Integration RELIABILITY | RESILIENCE | SECURITY NERC Activities and Plans to Address Reliability Impacts from Large Load Integration Mark Lauby, Senior Vice President and Chief Engineer FERC Open Meeting April 17,…
Read this passage Filed comments: Reliability and curtailment

Attachment B

printed heading

Typically, transferring the load back to the grid from the DRUPS system must be done manually.